Korean Journal of Construction Engineering and Management
/
v.6
no.5
s.27
/
pp.177-185
/
2005
Construction uncertainties are frequently exposed to the claims. In most cases, an interpretation of the claims is based on the construction contract. Therefore, the key points of contract negotiation are how to fairly distribute the contract risks to the client and contractor. For these, a FIDIC that is considered as an international standard contract form would be a good reference to decide reasonable contract risk distribution. In order to find out any unreasonable and unfair contract clauses at the general conditions of contract applying generally to public construction project in Korea, this study surveys, analyses and evaluates the general conditions of contract based on a FIDIC, and then proposes a risk mitigation methodology to response those clauses' risk factors reasonably.
The incentive and reasons to publish FIDIC Conditions of Contract for Design, Build and Operate Projects(DBO Form) are manifold. It is partly a response to the increasing need for sophisticated project delivery methods in both the public and private sectors and the already widespread use of the FIDIC Yellow Book with operation and maintenance obligations and partly a response to the challenge to decrease maintenance cost to a minimum by means of a new procurement route. As a result, FIDIC has developed a new model form to meet this market place requirement. On the other hand, FIDIC did not simply adapt the Yellow Book but has developed a new form from it, whilst preserving the style of the already known FIDIC Forms and maintaining the wording where it was not necessary to change it for the purposes of a DBO Form. Moreover DBO Form fills up supposed gaps in other FIDIC Forms and ameliorates the claim management and dispute management framework. FIDIC DBO approach may be shortly summarized as follows. First, DBO Form provides for single project responsibility. Second, DBO Form has the clear objective of ensuring the use of a most reliable and efficient technology at the lowest life-cycle cost. Third, DBO Form is intended to operate as an effective quality increase in the design and construction of projects. Fourth, DBO Form is intended to provide significant benefits with regard to system integration and reduction of risks. Fifth, DBO Form accelerates and enhances completion schedule compliance. Sixth, DBO takes care of all three supporting pillars of sustainability(including economical, environmental and social elements). DBO Form is obviously a good starting point for negotiations and the preparation of calls for tenders, thus saving the parties time and money. However, existing cultural and legal differences, particular local conditions and the particular needs of some branches of the industry may require the form to be adapted according to the particular needs of a project. And Civil law practitioners are strongly recommended to verify carefully the underlying legal concepts and background of each clause of the General Conditions in order to avoid unnecessary and sometimes unnatural changes and amendments being made. Note that when preparing the Particular Conditions ensure that terminology is consistent and that existing inherent concepts should not be ignored.
KSCE Journal of Civil and Environmental Engineering Research
/
v.42
no.3
/
pp.439-448
/
2022
Recently, domestic small and medium-sized subcontractors participating in the overseas construction market are suffering from the continuous loss and damage due to the insufficient recognition of the importance of risk Sub-Clauses among conditions of subcontracts. Therefore, the need to derive risk Sub-Clauses for conditions of the subcontract has been raised, but until now, previous studies have been conducted focusing on deriving risk Sub-Clauses for standard conditions of contract for construction between the Employer and the Contractor. In this study, 52 risk Sub-Clauses were derived on the basis of the influence size of the Sub-Clauses through the Delphi technique targeting 94 Sub-Clauses of conditions of standard subcontract for construction edition 2011, issued by the International Federation of Consulting Engineers (FIDIC) and In addition, 33 key risk Sub-Clauses were finally derived through the PI Risk Matrix by Probability and Impact. The results of this study provide will useful information on key risk Sub-Clauses that need to be reviewed in advance to minimize contractual risks at the stage of bidding and signing contracts for overseas subcontract construction projects.
Journal of the Korea Institute of Building Construction
/
v.20
no.6
/
pp.527-535
/
2020
This study analyzed main causes of claims in EPC/Turnkey projects. For this purpose, this study referred to the FIDIC silver book, which lists the international standard contract conditions for EPC/Turnkey projects. The most frequent cause of claim was delay. A process was then proposed to determine whether the owner or contractor was the responsible party when the delay claim occurred. The proposed process was for damages for delay which is the conditions of contract for indemnities against delay claim. The process was based on conditions of the contract of two previous EPC/Turnkey projects that were constructed in 2010, the FIDIC silver book, as well as the obligations of owner and contactors. The proposed process is applicable depending on the conditions of the contract and the owner's meaning. Furthermore, by identifying the responsible party, this study will contribute in identifying the possible claim types before concluding a contract and writing the specific contract.
It is common that several kind of claims between the parties are arising in carrying out international construction works. Therefore, it is very important for them to settle the claims effectively in order to get expected profits and purposes in international construction works. In this article, the author have studied on the procedures and contents on the settlement of claims between the parties based on the FIDIC contracts for major works which are newly prepared in 1999 by FIDIC. Especially, the arbitration clause in the FIDIC contracts for major works attempts to deal with a number of complex contractual and legal matters, sometimes in a very harsh way, e.g. by cutting off a party's rights. It has never been an easy clause to understand or to observe. Nevertheless, the author hopes he has been able in this article to clarify for the reader some of the issues raised by it. I'd like to suggest that our overseas construction companies refer to the FIDIC contracts for major works(especially article 20 : claims, disputes and arbitration) directly or indirectly for their contract of international construction works with overseas employers.
KSCE Journal of Civil and Environmental Engineering Research
/
v.43
no.2
/
pp.239-247
/
2023
The FIDIC Red Book is an international standard contract condition in which the Employer designs and the Contractor performs the construction. The Engineer of FIDIC Red Book shall agree or determine any matter or Claim in accordance with Sub-Clause 3.7 neutrally, not as an agent of the Employer. This study aimed to derive Key Risk Sub-Clauses out of 49 Sub-Clauses that the Engineer of FIDIC Red Book recently revised in 18 years shall agree or determine according to Sub-Clause 3.7 using the Delphi method. A panel of 35 experts with more than 10 years of experience and expertise in international construction contracts was formed, and through total three Delphi surveys, errors and biases were prevented in the judgment process to improve reliability. As for the research method, 49 Sub-Clauses that engineers shall agree on or determine according to Sub-Clause 3.7 of the FIDIC Red Book were investigated through the analysis of contract conditions. In order to evaluate the probability and impact of contractual risk for each 49 Sub-Clause, the Delphi survey conducted repeatedly a closed-type survey three times on a Likert 10-point scale. The results of the first Delphi survey were delivered during the second survey, and the results of the second survey were delivered to the third survey, which was re-evaluated in the direction of increasing the consensus of experts' opinions. The reliability of the Delphi 3rd survey results was verified with the COV value of the coefficient of variation. The PI Risk Matrix was applied to the average value of risk probability and impact of each of the 49 Sub-Clauses and finally, 9 Key Risk Sub-Clauses that fell within the extreme risk range were derived.
Korean Journal of Construction Engineering and Management
/
v.18
no.6
/
pp.65-77
/
2017
Recently, many Korean major construction companies are suffering from profit loss mainly due to a direct impact from delays in their overseas projects. In general, changes are inevitable in a large-scale project, and most of changes are directly linked to construction delay. Therefore, in the event that an extension of time is necessary due to a change, the contractor must manage the delay based on the condition of the contract to effectively manage risks from delay to the completion date. Thus it is important to understand delay protocol defined in the condition of the contract early in the project, but there have been few or no study to propose methodology or tool to support this effort. This paper presents a review on the project planning and controling practices of major Korean construction companies along with the issues on delay claims and disputes in mega-international projects and suggests a tool to assess delay risk in the condition of the contract. To propose a delay risk assessment model for international construction projects, major standard conditions of contract have been reviewed including FIDIC Red Book(1999), PSSCOC(2014) and SIA 9th Edition(2010). To reflect recent trend of major international owners, standard conditions which they are utilizing for their projects also have been reviewed including those of ARAMCO and QP. The model provides a categories of risks to be reviewed on the condition of the contract along with standard level of the risk which is common in the international standard form of the contracts. This study also performed a case study on an actual international project to confirm the effectiveness of proposed model to identify and respond to a delay risk of a project.
Hyunsang Lee;Wonseok Lee;Bogeun Jo;Heejun Lee;Sangjin Oh;Sangwoo You;Maru Nam;Hyunsik Lee
KIPS Transactions on Software and Data Engineering
/
v.12
no.11
/
pp.471-480
/
2023
The Korean construction order volume in South Korea grew significantly from 91.3 trillion won in public orders in 2013 to a total of 212 trillion won in 2021, particularly in the private sector. As the size of the domestic and overseas markets grew, the scale and complexity of EPC (Engineering, Procurement, Construction) projects increased, and risk management of project management and ITB (Invitation to Bid) documents became a critical issue. The time granted to actual construction companies in the bidding process following the EPC project award is not only limited, but also extremely challenging to review all the risk terms in the ITB document due to manpower and cost issues. Previous research attempted to categorize the risk terms in EPC contract documents and detect them based on AI, but there were limitations to practical use due to problems related to data, such as the limit of labeled data utilization and class imbalance. Therefore, this study aims to develop an AI model that can categorize the contract terms based on the FIDIC Yellow 2017(Federation Internationale Des Ingenieurs-Conseils Contract terms) standard in detail, rather than defining and classifying risk terms like previous research. A multi-text classification function is necessary because the contract terms that need to be reviewed in detail may vary depending on the scale and type of the project. To enhance the performance of the multi-text classification model, we developed the ELECTRA PLM (Pre-trained Language Model) capable of efficiently learning the context of text data from the pre-training stage, and conducted a four-step experiment to validate the performance of the model. As a result, the ensemble version of the self-developed ITB-ELECTRA model and Legal-BERT achieved the best performance with a weighted average F1-Score of 76% in the classification of 57 contract terms.
본 웹사이트에 게시된 이메일 주소가 전자우편 수집 프로그램이나
그 밖의 기술적 장치를 이용하여 무단으로 수집되는 것을 거부하며,
이를 위반시 정보통신망법에 의해 형사 처벌됨을 유념하시기 바랍니다.
[게시일 2004년 10월 1일]
이용약관
제 1 장 총칙
제 1 조 (목적)
이 이용약관은 KoreaScience 홈페이지(이하 “당 사이트”)에서 제공하는 인터넷 서비스(이하 '서비스')의 가입조건 및 이용에 관한 제반 사항과 기타 필요한 사항을 구체적으로 규정함을 목적으로 합니다.
제 2 조 (용어의 정의)
① "이용자"라 함은 당 사이트에 접속하여 이 약관에 따라 당 사이트가 제공하는 서비스를 받는 회원 및 비회원을
말합니다.
② "회원"이라 함은 서비스를 이용하기 위하여 당 사이트에 개인정보를 제공하여 아이디(ID)와 비밀번호를 부여
받은 자를 말합니다.
③ "회원 아이디(ID)"라 함은 회원의 식별 및 서비스 이용을 위하여 자신이 선정한 문자 및 숫자의 조합을
말합니다.
④ "비밀번호(패스워드)"라 함은 회원이 자신의 비밀보호를 위하여 선정한 문자 및 숫자의 조합을 말합니다.
제 3 조 (이용약관의 효력 및 변경)
① 이 약관은 당 사이트에 게시하거나 기타의 방법으로 회원에게 공지함으로써 효력이 발생합니다.
② 당 사이트는 이 약관을 개정할 경우에 적용일자 및 개정사유를 명시하여 현행 약관과 함께 당 사이트의
초기화면에 그 적용일자 7일 이전부터 적용일자 전일까지 공지합니다. 다만, 회원에게 불리하게 약관내용을
변경하는 경우에는 최소한 30일 이상의 사전 유예기간을 두고 공지합니다. 이 경우 당 사이트는 개정 전
내용과 개정 후 내용을 명확하게 비교하여 이용자가 알기 쉽도록 표시합니다.
제 4 조(약관 외 준칙)
① 이 약관은 당 사이트가 제공하는 서비스에 관한 이용안내와 함께 적용됩니다.
② 이 약관에 명시되지 아니한 사항은 관계법령의 규정이 적용됩니다.
제 2 장 이용계약의 체결
제 5 조 (이용계약의 성립 등)
① 이용계약은 이용고객이 당 사이트가 정한 약관에 「동의합니다」를 선택하고, 당 사이트가 정한
온라인신청양식을 작성하여 서비스 이용을 신청한 후, 당 사이트가 이를 승낙함으로써 성립합니다.
② 제1항의 승낙은 당 사이트가 제공하는 과학기술정보검색, 맞춤정보, 서지정보 등 다른 서비스의 이용승낙을
포함합니다.
제 6 조 (회원가입)
서비스를 이용하고자 하는 고객은 당 사이트에서 정한 회원가입양식에 개인정보를 기재하여 가입을 하여야 합니다.
제 7 조 (개인정보의 보호 및 사용)
당 사이트는 관계법령이 정하는 바에 따라 회원 등록정보를 포함한 회원의 개인정보를 보호하기 위해 노력합니다. 회원 개인정보의 보호 및 사용에 대해서는 관련법령 및 당 사이트의 개인정보 보호정책이 적용됩니다.
제 8 조 (이용 신청의 승낙과 제한)
① 당 사이트는 제6조의 규정에 의한 이용신청고객에 대하여 서비스 이용을 승낙합니다.
② 당 사이트는 아래사항에 해당하는 경우에 대해서 승낙하지 아니 합니다.
- 이용계약 신청서의 내용을 허위로 기재한 경우
- 기타 규정한 제반사항을 위반하며 신청하는 경우
제 9 조 (회원 ID 부여 및 변경 등)
① 당 사이트는 이용고객에 대하여 약관에 정하는 바에 따라 자신이 선정한 회원 ID를 부여합니다.
② 회원 ID는 원칙적으로 변경이 불가하며 부득이한 사유로 인하여 변경 하고자 하는 경우에는 해당 ID를
해지하고 재가입해야 합니다.
③ 기타 회원 개인정보 관리 및 변경 등에 관한 사항은 서비스별 안내에 정하는 바에 의합니다.
제 3 장 계약 당사자의 의무
제 10 조 (KISTI의 의무)
① 당 사이트는 이용고객이 희망한 서비스 제공 개시일에 특별한 사정이 없는 한 서비스를 이용할 수 있도록
하여야 합니다.
② 당 사이트는 개인정보 보호를 위해 보안시스템을 구축하며 개인정보 보호정책을 공시하고 준수합니다.
③ 당 사이트는 회원으로부터 제기되는 의견이나 불만이 정당하다고 객관적으로 인정될 경우에는 적절한 절차를
거쳐 즉시 처리하여야 합니다. 다만, 즉시 처리가 곤란한 경우는 회원에게 그 사유와 처리일정을 통보하여야
합니다.
제 11 조 (회원의 의무)
① 이용자는 회원가입 신청 또는 회원정보 변경 시 실명으로 모든 사항을 사실에 근거하여 작성하여야 하며,
허위 또는 타인의 정보를 등록할 경우 일체의 권리를 주장할 수 없습니다.
② 당 사이트가 관계법령 및 개인정보 보호정책에 의거하여 그 책임을 지는 경우를 제외하고 회원에게 부여된
ID의 비밀번호 관리소홀, 부정사용에 의하여 발생하는 모든 결과에 대한 책임은 회원에게 있습니다.
③ 회원은 당 사이트 및 제 3자의 지적 재산권을 침해해서는 안 됩니다.
제 4 장 서비스의 이용
제 12 조 (서비스 이용 시간)
① 서비스 이용은 당 사이트의 업무상 또는 기술상 특별한 지장이 없는 한 연중무휴, 1일 24시간 운영을
원칙으로 합니다. 단, 당 사이트는 시스템 정기점검, 증설 및 교체를 위해 당 사이트가 정한 날이나 시간에
서비스를 일시 중단할 수 있으며, 예정되어 있는 작업으로 인한 서비스 일시중단은 당 사이트 홈페이지를
통해 사전에 공지합니다.
② 당 사이트는 서비스를 특정범위로 분할하여 각 범위별로 이용가능시간을 별도로 지정할 수 있습니다. 다만
이 경우 그 내용을 공지합니다.
제 13 조 (홈페이지 저작권)
① NDSL에서 제공하는 모든 저작물의 저작권은 원저작자에게 있으며, KISTI는 복제/배포/전송권을 확보하고
있습니다.
② NDSL에서 제공하는 콘텐츠를 상업적 및 기타 영리목적으로 복제/배포/전송할 경우 사전에 KISTI의 허락을
받아야 합니다.
③ NDSL에서 제공하는 콘텐츠를 보도, 비평, 교육, 연구 등을 위하여 정당한 범위 안에서 공정한 관행에
합치되게 인용할 수 있습니다.
④ NDSL에서 제공하는 콘텐츠를 무단 복제, 전송, 배포 기타 저작권법에 위반되는 방법으로 이용할 경우
저작권법 제136조에 따라 5년 이하의 징역 또는 5천만 원 이하의 벌금에 처해질 수 있습니다.
제 14 조 (유료서비스)
① 당 사이트 및 협력기관이 정한 유료서비스(원문복사 등)는 별도로 정해진 바에 따르며, 변경사항은 시행 전에
당 사이트 홈페이지를 통하여 회원에게 공지합니다.
② 유료서비스를 이용하려는 회원은 정해진 요금체계에 따라 요금을 납부해야 합니다.
제 5 장 계약 해지 및 이용 제한
제 15 조 (계약 해지)
회원이 이용계약을 해지하고자 하는 때에는 [가입해지] 메뉴를 이용해 직접 해지해야 합니다.
제 16 조 (서비스 이용제한)
① 당 사이트는 회원이 서비스 이용내용에 있어서 본 약관 제 11조 내용을 위반하거나, 다음 각 호에 해당하는
경우 서비스 이용을 제한할 수 있습니다.
- 2년 이상 서비스를 이용한 적이 없는 경우
- 기타 정상적인 서비스 운영에 방해가 될 경우
② 상기 이용제한 규정에 따라 서비스를 이용하는 회원에게 서비스 이용에 대하여 별도 공지 없이 서비스 이용의
일시정지, 이용계약 해지 할 수 있습니다.
제 17 조 (전자우편주소 수집 금지)
회원은 전자우편주소 추출기 등을 이용하여 전자우편주소를 수집 또는 제3자에게 제공할 수 없습니다.
제 6 장 손해배상 및 기타사항
제 18 조 (손해배상)
당 사이트는 무료로 제공되는 서비스와 관련하여 회원에게 어떠한 손해가 발생하더라도 당 사이트가 고의 또는 과실로 인한 손해발생을 제외하고는 이에 대하여 책임을 부담하지 아니합니다.
제 19 조 (관할 법원)
서비스 이용으로 발생한 분쟁에 대해 소송이 제기되는 경우 민사 소송법상의 관할 법원에 제기합니다.
[부 칙]
1. (시행일) 이 약관은 2016년 9월 5일부터 적용되며, 종전 약관은 본 약관으로 대체되며, 개정된 약관의 적용일 이전 가입자도 개정된 약관의 적용을 받습니다.