Korean Journal of Construction Engineering and Management
/
v.8
no.1
s.35
/
pp.78-86
/
2007
Top priority to manage construction projects is given to the planning and scheduling in order to keep the project duration, which is one of the most important factors in construction management. However, recently most of public construction projects especially for civil projects are delays and preventive research, many efforts were made concerning construction delays and preventive management methods. But analysis of delay causation, which is a main key to solve the problems is not done, yet. Therefore, in this research causation delays are analyzed by characteristics of construction projects, which are type of projects, type of contracts, project participants, and general condition. As a result of the analysis, delay causation are proved to be different by characteristics of the projects. The research results will be used for prevention of time extension and dispute resolution.
Korean Journal of Construction Engineering and Management
/
v.12
no.6
/
pp.31-41
/
2011
Since the cases of time extension have continuously transpired in the public construction project, the potential of economical loss and claims is increasing because the concerned parties such as an owner or a contractor have not properly performed their own responsibility for time extension. One of the main reasons is that the present planning and scheduling do not support the method to apportion the proper responsibility to the right party. This problem has repeatedly led to time extension and made it difficult for the concerned parties to perform the responsibility for time extension. In order to overcome this problem, a framework of delay administration is required as the method to apportion the proper responsibility to the right party. To solve this problem, this paper aimed to develop the conceptual model and prototype system as the practical method to administrate delay causation. Furthermore, the verification result for the reliability and applicability throughout the case studies on real construction projects shows that the conceptual model and prototype system developed would help efficiently to administrate the delay causation.
Korean Journal of Construction Engineering and Management
/
v.8
no.3
/
pp.125-133
/
2007
If project time extension were required in the construction projects, either liquidated damages or extension costs should be applied according to causation of the schedule delays. However, in actual cases it is not applied so far according to the contract conditions. The reason why this situation happened Is that function of the present planning and scheduling is not working feasibly. The CPM schedule could not provide a proper solution for apportioning responsibility for the schedule delays. This situation could be considered as breach of contract and will cause potential disputes for schedule delay. Therefore, in this research process based contract administration model for construction delay claim is proposed to prevent schedule delay and solve the claims. The model is based on pro-active management for causation of delay to provide apportionment of responsibility and written evidences.
Proceedings of the Korean Institute Of Construction Engineering and Management
/
2007.11a
/
pp.60-67
/
2007
Cases of the time extension have continuously transpired in the public construction projects. The potential of economical loss and claims is increased because the concerned parties such as an owner or a contractor have not properly performed their own responsibility for the time extension. Therefore, this paper aimed to improvement of apportioning responsibility for the time extension in construction projects.
Song, Joon Young;Kim, Cheol Min;Shin, Young Lim;Yoo, Han Wook
Clinical and Experimental Pediatrics
/
v.45
no.10
/
pp.1278-1282
/
2002
Glutaric aciduria(type 1) is characterized clinically by progressive dystonia and dyskinesia in childhood, pathologically by degeneration of caudate and putamen, biochemically by tissue deficiency of glutaryl-CoA dehydrogenase(GCDH), and is transmitted as an autosomal recessive traits. Mutations of the GCDH gene on chromosome 19 have been implicated in the causation of glutaric aciduria(type 1). Macrocephaly in infancy and crossing of percentiles for head circumference are real clues to early diagnosis. Acute neuroregression of dystonia following an initial phase of normal or almost normal development is a common mode of presentation, at times preceded by seizures. We experienced a case of glutaric aciduria(type 1) in a 13-month old girl. She was admitted due to development delay and choreoasthetoid movememt that developed after generalized tonic-clonic type seizures. She was diagnosed as having glutaric aciduria(type 1) based on brain MRI and urine organic acid analysis finding.
In Count case, the owners claimed from the charterers the amount of their loss resulting from the delay to the Count caused by the blockage of the channel due to stranding of the Pongola on the ground that this loss resulted from breach by the charterers of the safe port provisions. The Claim was referred to arbitration and dealt with on written submission. In a reasoned award, the arbitrators upheld the owners' claim. The charterers seek an order reversing the award or remitting it to the arbitrators for further consideration : (1) That the tribunal was wrong to find that the port of Beira was unsafe and that in consequence the charterers were liable to the owners in damages for detention. (2) That the tribunal was wrong to find that the port was unsafe in the abstract by reference to the fact that two other vessels had grounded there. (3) Having held that the Count was delayed for a little over four days by the fact that, after the charterers had nominated the port, the Pongola had grounded in the access channel, the tribunal should have held that the port was not prospectively unsafe. On the that the grounding the Pongola was caused by the characteristics which made the port an unsafe port to nominate for the Count. The court was held that it was not an independent event which broke the chain of causation between the breach of contract and the owner's loss. For those reasons, the court was upheld the arbitrator's award.
본 웹사이트에 게시된 이메일 주소가 전자우편 수집 프로그램이나
그 밖의 기술적 장치를 이용하여 무단으로 수집되는 것을 거부하며,
이를 위반시 정보통신망법에 의해 형사 처벌됨을 유념하시기 바랍니다.
[게시일 2004년 10월 1일]
이용약관
제 1 장 총칙
제 1 조 (목적)
이 이용약관은 KoreaScience 홈페이지(이하 “당 사이트”)에서 제공하는 인터넷 서비스(이하 '서비스')의 가입조건 및 이용에 관한 제반 사항과 기타 필요한 사항을 구체적으로 규정함을 목적으로 합니다.
제 2 조 (용어의 정의)
① "이용자"라 함은 당 사이트에 접속하여 이 약관에 따라 당 사이트가 제공하는 서비스를 받는 회원 및 비회원을
말합니다.
② "회원"이라 함은 서비스를 이용하기 위하여 당 사이트에 개인정보를 제공하여 아이디(ID)와 비밀번호를 부여
받은 자를 말합니다.
③ "회원 아이디(ID)"라 함은 회원의 식별 및 서비스 이용을 위하여 자신이 선정한 문자 및 숫자의 조합을
말합니다.
④ "비밀번호(패스워드)"라 함은 회원이 자신의 비밀보호를 위하여 선정한 문자 및 숫자의 조합을 말합니다.
제 3 조 (이용약관의 효력 및 변경)
① 이 약관은 당 사이트에 게시하거나 기타의 방법으로 회원에게 공지함으로써 효력이 발생합니다.
② 당 사이트는 이 약관을 개정할 경우에 적용일자 및 개정사유를 명시하여 현행 약관과 함께 당 사이트의
초기화면에 그 적용일자 7일 이전부터 적용일자 전일까지 공지합니다. 다만, 회원에게 불리하게 약관내용을
변경하는 경우에는 최소한 30일 이상의 사전 유예기간을 두고 공지합니다. 이 경우 당 사이트는 개정 전
내용과 개정 후 내용을 명확하게 비교하여 이용자가 알기 쉽도록 표시합니다.
제 4 조(약관 외 준칙)
① 이 약관은 당 사이트가 제공하는 서비스에 관한 이용안내와 함께 적용됩니다.
② 이 약관에 명시되지 아니한 사항은 관계법령의 규정이 적용됩니다.
제 2 장 이용계약의 체결
제 5 조 (이용계약의 성립 등)
① 이용계약은 이용고객이 당 사이트가 정한 약관에 「동의합니다」를 선택하고, 당 사이트가 정한
온라인신청양식을 작성하여 서비스 이용을 신청한 후, 당 사이트가 이를 승낙함으로써 성립합니다.
② 제1항의 승낙은 당 사이트가 제공하는 과학기술정보검색, 맞춤정보, 서지정보 등 다른 서비스의 이용승낙을
포함합니다.
제 6 조 (회원가입)
서비스를 이용하고자 하는 고객은 당 사이트에서 정한 회원가입양식에 개인정보를 기재하여 가입을 하여야 합니다.
제 7 조 (개인정보의 보호 및 사용)
당 사이트는 관계법령이 정하는 바에 따라 회원 등록정보를 포함한 회원의 개인정보를 보호하기 위해 노력합니다. 회원 개인정보의 보호 및 사용에 대해서는 관련법령 및 당 사이트의 개인정보 보호정책이 적용됩니다.
제 8 조 (이용 신청의 승낙과 제한)
① 당 사이트는 제6조의 규정에 의한 이용신청고객에 대하여 서비스 이용을 승낙합니다.
② 당 사이트는 아래사항에 해당하는 경우에 대해서 승낙하지 아니 합니다.
- 이용계약 신청서의 내용을 허위로 기재한 경우
- 기타 규정한 제반사항을 위반하며 신청하는 경우
제 9 조 (회원 ID 부여 및 변경 등)
① 당 사이트는 이용고객에 대하여 약관에 정하는 바에 따라 자신이 선정한 회원 ID를 부여합니다.
② 회원 ID는 원칙적으로 변경이 불가하며 부득이한 사유로 인하여 변경 하고자 하는 경우에는 해당 ID를
해지하고 재가입해야 합니다.
③ 기타 회원 개인정보 관리 및 변경 등에 관한 사항은 서비스별 안내에 정하는 바에 의합니다.
제 3 장 계약 당사자의 의무
제 10 조 (KISTI의 의무)
① 당 사이트는 이용고객이 희망한 서비스 제공 개시일에 특별한 사정이 없는 한 서비스를 이용할 수 있도록
하여야 합니다.
② 당 사이트는 개인정보 보호를 위해 보안시스템을 구축하며 개인정보 보호정책을 공시하고 준수합니다.
③ 당 사이트는 회원으로부터 제기되는 의견이나 불만이 정당하다고 객관적으로 인정될 경우에는 적절한 절차를
거쳐 즉시 처리하여야 합니다. 다만, 즉시 처리가 곤란한 경우는 회원에게 그 사유와 처리일정을 통보하여야
합니다.
제 11 조 (회원의 의무)
① 이용자는 회원가입 신청 또는 회원정보 변경 시 실명으로 모든 사항을 사실에 근거하여 작성하여야 하며,
허위 또는 타인의 정보를 등록할 경우 일체의 권리를 주장할 수 없습니다.
② 당 사이트가 관계법령 및 개인정보 보호정책에 의거하여 그 책임을 지는 경우를 제외하고 회원에게 부여된
ID의 비밀번호 관리소홀, 부정사용에 의하여 발생하는 모든 결과에 대한 책임은 회원에게 있습니다.
③ 회원은 당 사이트 및 제 3자의 지적 재산권을 침해해서는 안 됩니다.
제 4 장 서비스의 이용
제 12 조 (서비스 이용 시간)
① 서비스 이용은 당 사이트의 업무상 또는 기술상 특별한 지장이 없는 한 연중무휴, 1일 24시간 운영을
원칙으로 합니다. 단, 당 사이트는 시스템 정기점검, 증설 및 교체를 위해 당 사이트가 정한 날이나 시간에
서비스를 일시 중단할 수 있으며, 예정되어 있는 작업으로 인한 서비스 일시중단은 당 사이트 홈페이지를
통해 사전에 공지합니다.
② 당 사이트는 서비스를 특정범위로 분할하여 각 범위별로 이용가능시간을 별도로 지정할 수 있습니다. 다만
이 경우 그 내용을 공지합니다.
제 13 조 (홈페이지 저작권)
① NDSL에서 제공하는 모든 저작물의 저작권은 원저작자에게 있으며, KISTI는 복제/배포/전송권을 확보하고
있습니다.
② NDSL에서 제공하는 콘텐츠를 상업적 및 기타 영리목적으로 복제/배포/전송할 경우 사전에 KISTI의 허락을
받아야 합니다.
③ NDSL에서 제공하는 콘텐츠를 보도, 비평, 교육, 연구 등을 위하여 정당한 범위 안에서 공정한 관행에
합치되게 인용할 수 있습니다.
④ NDSL에서 제공하는 콘텐츠를 무단 복제, 전송, 배포 기타 저작권법에 위반되는 방법으로 이용할 경우
저작권법 제136조에 따라 5년 이하의 징역 또는 5천만 원 이하의 벌금에 처해질 수 있습니다.
제 14 조 (유료서비스)
① 당 사이트 및 협력기관이 정한 유료서비스(원문복사 등)는 별도로 정해진 바에 따르며, 변경사항은 시행 전에
당 사이트 홈페이지를 통하여 회원에게 공지합니다.
② 유료서비스를 이용하려는 회원은 정해진 요금체계에 따라 요금을 납부해야 합니다.
제 5 장 계약 해지 및 이용 제한
제 15 조 (계약 해지)
회원이 이용계약을 해지하고자 하는 때에는 [가입해지] 메뉴를 이용해 직접 해지해야 합니다.
제 16 조 (서비스 이용제한)
① 당 사이트는 회원이 서비스 이용내용에 있어서 본 약관 제 11조 내용을 위반하거나, 다음 각 호에 해당하는
경우 서비스 이용을 제한할 수 있습니다.
- 2년 이상 서비스를 이용한 적이 없는 경우
- 기타 정상적인 서비스 운영에 방해가 될 경우
② 상기 이용제한 규정에 따라 서비스를 이용하는 회원에게 서비스 이용에 대하여 별도 공지 없이 서비스 이용의
일시정지, 이용계약 해지 할 수 있습니다.
제 17 조 (전자우편주소 수집 금지)
회원은 전자우편주소 추출기 등을 이용하여 전자우편주소를 수집 또는 제3자에게 제공할 수 없습니다.
제 6 장 손해배상 및 기타사항
제 18 조 (손해배상)
당 사이트는 무료로 제공되는 서비스와 관련하여 회원에게 어떠한 손해가 발생하더라도 당 사이트가 고의 또는 과실로 인한 손해발생을 제외하고는 이에 대하여 책임을 부담하지 아니합니다.
제 19 조 (관할 법원)
서비스 이용으로 발생한 분쟁에 대해 소송이 제기되는 경우 민사 소송법상의 관할 법원에 제기합니다.
[부 칙]
1. (시행일) 이 약관은 2016년 9월 5일부터 적용되며, 종전 약관은 본 약관으로 대체되며, 개정된 약관의 적용일 이전 가입자도 개정된 약관의 적용을 받습니다.