Owner-driven Lean Construction based on Participants' Needs Analysis (건설주체간의 니즈분석을 통한 발주자 참여형 린 건설 연구)

  • Lee, Kang-Woo;Ryu, Chung-Gyu;Park, Hee-Dae;Han, Seung-Heon
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2008.11a
    • /
    • pp.222-226
    • /
    • 2008
  • The construction industry has remained stagnant for a long time. So many researchers have wanted to solve this problem not only focusing on enhancement of construction process, but also introducing the culture of cooperation. The Last Planner System(LPS), one of the elementary techniques of Lean Construction, aims for improving the work reliability and reducing variability by measuring and managing the daily or weekly performance for overcoming the weakness of recent complex schedule management tools such as Critical Path Method. This research propose a framework for implementation of LPS conducted by owner focused on construction stage and introduce optimal owner participation model in plant construction, based on needs analysis for construction participants. Furthermore, this research introduce a modified needs analysis, so called IPBA(Importance-Performance-Betterment Analysis), and an advanced LPS procedure which add the needs analysis during pre-LPS and(or) main LPS stages.

  • PDF

Development of CM Model for BTL Projects in a Public Educational Facilities (공공교육시설 BTL사업의 CM적용모델 개발)

  • Shin, Nam-Kyoung;Woo, Kwang-Min;Lee, Hak-Ki
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2006.11a
    • /
    • pp.338-341
    • /
    • 2006
  • After the revision of Private Investment Law in January 2005, BTL is introduced to expand the social infrastructures as a major business procedure. Especially, the size of the public educational infrastructure ordered by each city education office is increased by 45% compared to last year, so it is major in BTL Project. However, in the process of practicing BTL Project by now, there are a lot of problems specially in the public educational infrastructure. As a result, this study gives the solutions in the process of BTL Project, the CM models to support the Education Office${\square}{\square}$job and the suggestions for the working scope of the participating construction companies.

  • PDF

Research on the Plans of Construction Information for National Infrastructure in Public Construction Projects (공공건설사업에서의 국가기반시설 건설정보 서비스 방안에 관한 연구)

  • Ok, Hyun;Kim, Jin-Uk
    • The Journal of the Korea Contents Association
    • /
    • v.13 no.12
    • /
    • pp.1026-1035
    • /
    • 2013
  • The construction field is implementing cost savings and business process improvements by adopting and applying various information technologies to secure the construction sector's technological competitiveness amid the economic recessions inside and outside South Korea. Therefore, affiliated agencies of the Ministry of Land, Infrastructure, and Transport are reinforcing transparency and efficiency in construction project management through informatization. These agencies are also performing construction project management and maintenance and management businesses by constructing various information systems to create higher added values and secure competitiveness. However, as the application of the constructed information system is limited to a portion of public construction projects, it is not yet possible to understand the whole status of the national infrastructures. Therefore, this paper aims to propose a construction information service plan, its future promotion method and procedure of application on the entire national infrastructures. This plan would be carried out by collecting, linking and fabricating the main construction information from the information systems of the affiliated agencies around the construction project information system(Construction CALS System) being applied at the organizations under the Ministry of Land, Infrastructure, and Transport. Such a plan is expected to facilitate effective project management and maintenance of public construction projects and serve as a useful tool for major decision making endeavors such as future policy planning. The proposed plan is also expected to facilitate the management and application of construction information from the construction up to the maintenance management of the national infrastructures.

Development of DL-MCS Hybrid Expert System for Automatic Estimation of Apartment Remodeling (공동주택 리모델링 자동견적을 위한 DL-MCS Hybrid Expert System 개발)

  • Kim, Jun;Cha, Heesung
    • Korean Journal of Construction Engineering and Management
    • /
    • v.21 no.6
    • /
    • pp.113-124
    • /
    • 2020
  • Social movements to improve the performance of buildings through remodeling of aging apartment houses are being captured. To this end, the remodeling construction cost analysis, structural analysis, and political institutional review have been conducted to suggest ways to activate the remodeling. However, although the method of analyzing construction cost for remodeling apartment houses is currently being proposed for research purposes, there are limitations in practical application possibilities. Specifically, In order to be used practically, it is applicable to cases that have already been completed or in progress, but cases that will occur in the future are also used for construction cost analysis, so the sustainability of the analysis method is lacking. For the purpose of this, we would like to suggest an automated estimating method. For the sustainability of construction cost estimates, Deep-Learning was introduced in the estimating procedure. Specifically, a method for automatically finding the relationship between design elements, work types, and cost increase factors that can occur in apartment remodeling was presented. In addition, Monte Carlo Simulation was included in the estimation procedure to compensate for the lack of uncertainty, which is the inherent limitation of the Deep Learning-based estimation. In order to present higher accuracy as cases are accumulated, a method of calculating higher accuracy by comparing the estimate result with the existing accumulated data was also suggested. In order to validate the sustainability of the automated estimates proposed in this study, 13 cases of learning procedures and an additional 2 cases of cumulative procedures were performed. As a result, a new construction cost estimating procedure was automatically presented that reflects the characteristics of the two additional projects. In this study, the method of estimate estimate was used using 15 cases, If the cases are accumulated and reflected, the effect of this study is expected to increase.

Cost Analysis for Assessment of Reconstruction Projects (재건축사업의 진단평가를 위한 비용분석)

  • Kwon Dong-Chan;Lee Chan-Sik
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.477-480
    • /
    • 2003
  • The objective procedure and criterion needs to efficiently perform the safety assessment and improve reliability for results of the cost analysis. There are many studies about cost analysis of safety assessment, but the these studies have problems such as non-quantification of criterions and methods. The purpose of this study to suggest the procedure and criterion for successful cost analysis and quantify cost factors. First, in the cost analysis of the housing reconstruction that is presented this study, determinate the life-cycle and the discount rate, then estimate reconstruction cost and remodeling cost. Finally, compare the annual equivalent LCC of two costs for decision malting to reconstruction or remodeling.

  • PDF

A Suggestion of Claims Preparation Procedure in the Public Sector (공공건설사업에서 업무단계별 클레임준비 절차)

  • Cho Young-Jun;Hyun Chang-Taek
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.54-62
    • /
    • 2001
  • Although claims and disputes may be never avoided in construction industry, until 1998, there are no systematic claims in the public sector in Korea. But, because of IMF, Contractors have been recognized that cost management is essential factor and contractual right can be demanded against the Public Orderer. Many affirmative effect such as, appearance of new professional service, prevention of lower quality construction, restrain of unnecessary budget expenditure, arrangement of duplicated or triplicated liability and revision of unnecessary administrative control may be anticipated through alleging claims, but in site representative manager and construction company may have ambiguous fear, somebody tried to allege claims. Therefore, to activate systematic construction claims, 32 public construction project claims alleged by contractors from 1998 to 2001 were analyzed, inactivated reasons of claims were examined and contractor's action plan to allege claims was suggested in this paper.

  • PDF

The Process Development and Application of the Contingency Management by the Performance Analysis (성과분석을 통한 건설공사 예비비 관리 프로세스 및 적용)

  • Lee, Man-Hee;Lee, Hak-Ki
    • Korean Journal of Construction Engineering and Management
    • /
    • v.8 no.2
    • /
    • pp.84-92
    • /
    • 2007
  • To reduce uncertainties and make rational plans, the presumption of contingency against a failure of projects and an occurrence of unpredictable risks is important with accurate estimations as the work progressing. Therefore, if the presumption of contingency reflecting uncertainties carries out at a decision making point of time, be able to prepare for risks. The purpose of this paper is to present a management process of contingency through the performance analysis of project. In the cost planning phase, this study offers a process which is predictable contingency and predicts the range of fluctuation of the cost, laking an advantage of EVM in construction phase. With reflecting the results from this procedure, this study presents a process, rationally manageable contingency.

The Case and Implications of Terminology Mapping for Development of Dankook University Hospital EHR-Based MOA CDM (단국대학교병원 EHR 기반 MOA CDM 구축을 위한 용어 매핑 사례와 시사점)

  • Yookyung Boo;Sihyun Song;Jihwan Park;Mi Jung Rho
    • Korea Journal of Hospital Management
    • /
    • v.29 no.1
    • /
    • pp.1-18
    • /
    • 2024
  • Purposes: The Common Data Model(CDM) is very important for multi-institutional research. There are various domestic and international CDM construction cases to actively utilize it. In order to construct a CDM, different terms from each institution must be mapped to standard terms. Therefore, we intend to derive the importance and major issues of terminology mapping and propose a solution in CDM construction. Methodology/Approach: This study conducted terminology mapping between Electronic Health Record(EHR) and MOA CDM for constructing Medical Record Observation & Assessment for Drug Safety(MOA) CDM at Dankook University Hospital in 2022. In the process of terminology mapping, a CDM standard terminology process and method were developed and terminology mapping was performed by applying this. The constructions of CDM mapping terms proceeded in the order of diagnosis, drug, measurement, and treatment_procedure. Findings: We developed mapping guideline for CDM construction and used this for mapping. A total of 670,993 EHR data from Dankook University Hospital(January 1, 2013 to December 31, 2021) were mapped. In the case of diagnosis terminology, 19,413 were completely mapped. Drug terminology mapped 92.1% of 2,795. Measurement terminology mapped 94.5% of 7,254 cases. Treatment and procedure were mapped to 2,181 cases, which are the number of mapping targets. Practical Implications: This study found the importance of constructing MOA CDM for drug side effect monitoring and developed terminology mapping guideline. Our results would be useful for all future researchers who are conducting terminology mapping when constructing CDM.

  • PDF

A Study on Estimation Model of Construction Duration for Public Construction (공공건설공사 공사기간 산정모델에 관한 연구)

  • Kim, Byeong-Soo;Chun, Jin-Ku
    • Korean Journal of Construction Engineering and Management
    • /
    • v.6 no.6 s.28
    • /
    • pp.142-151
    • /
    • 2005
  • On public constructions, that the first planed projects delay than the scheduled completion day occurrence frequently because gap between the scheduled construction durations and the actual construction durations. These facts connect with not only problems of the construction during as the construction delay but also brought about the distribution costs increase as the failure of facility use plan and the people discomfort weight, failure of the production and the supply using facility then tremendous loss of each part etc. For reduce these loss, it must improve accuracy of the scheduled construction duration estimating when it order. This study try contribute to a successful manage of public project and reduce the construction duration extension frequent of the construction during, and then ensure the suitable construction duration by present the estimation model of the scheduled construction duration that include the construction duration correct element using as an index on the scheduled construction duration estimation.

Development of wall-thinning evaluation procedure for nuclear power plant piping - Part 2: Local wall-thinning estimation method

  • Yun, Hun;Moon, Seung-Jae;Oh, Young-Jin
    • Nuclear Engineering and Technology
    • /
    • v.52 no.9
    • /
    • pp.2119-2129
    • /
    • 2020
  • Flow-accelerated corrosion (FAC), liquid droplet impingement erosion (LDIE), cavitation and flashing can cause continuous wall-thinning in nuclear secondary pipes. In order to prevent pipe rupture events resulting from the wall-thinning, most NPPs (nuclear power plants) implement their management programs, which include periodic thickness inspection using UT (ultrasonic test). Meanwhile, it is well known in field experiences that the thickness measurement errors (or deviations) are often comparable with the amount of thickness reduction. Because of these errors, it is difficult to estimate wall-thinning exactly whether the significant thinning has occurred in the inspected components or not. In the previous study, the authors presented an approximate estimation procedure as the first step for thickness measurement deviations at each inspected component and the statistical & quantitative characteristics of the measurement deviations using plant experience data. In this study, statistical significance was quantified for the current methods used for wall-thinning determination. Also, the authors proposed new estimation procedures for determining local wall-thinning to overcome the weakness of the current methods, in which the proposed procedure is based on analysis of variance (ANOVA) method using subgrouping of measured thinning values at all measurement grids. The new procedures were also quantified for their statistical significance. As the results, it is confirmed that the new methods have better estimation confidence than the methods having used until now.