A Study on Proto-type Development of BIM based Stochastic Duration Estimation Module (BIM기반 추계학적 공기 예측 모듈 프로토 타입 개발에 관한 연구)

  • Park, Jae-Hyun;Yun, Seok-Heon;Paek, Joon-Hong
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2009.05b
    • /
    • pp.159-162
    • /
    • 2009
  • Today's construction is more various and more complex. Because of that, a lot of uncertain factors are occurred and they related uncertain construction duration. For management complex architecture project, importance of construction schedule management also increased. In previous studies, one of solutions to overcome those problems is suggested. It was BIM based construction simulation process which focused on construction schedule and construction schedule management. But latest process had limited point which has no duration estimation function. So this paper suggested duration estimation method and developed duration estimation module. Duration estimation module developed with current scheduling tool MS Project and their macro function. However, this module has just developed Reinforced Concrete Structure and has to do more development and research.

  • PDF

ENHANCEMENT OF AVAILABILITY OF 4D SIMULATION BASED ON BUILDING INFORMATION MODEL TECHNOLOGY

  • Jong Jin Park;Eon Yong Kim;Hyun Cho;Han Jong Jun
    • International conference on construction engineering and project management
    • /
    • 2009.05a
    • /
    • pp.579-586
    • /
    • 2009
  • 4D simulation integrates the 3 dimensional model of a building with the construction schedule, and it leads to the possibility of virtually checking the construction process and the building itself in advance. However, the existing problem of 4D simulation is the difference between the demands of architects, engineers, and construction site workers in 4D simulation. This study suggests the possible way to enhance the availability of 4D simulation, considering more the practical demands from the construction site. In order to conduct this study, we build a 3D BIM model of a business-residential complex and link the model with the pre-defined construction schedule in order to make a 4D simulation. This study concludes with the optimized 4D simulation methodology based on BIM model considering the demands in perspective of the construction site. It would contribute to the harmonic collaboration among architects, engineers, and labors in the construction site when using 4D simulation based on BIM model.

  • PDF

A Study on the Enablers and Barriers of BIM-based Assembling Collaboration for Designers' Communication and Socio-Psychological Mechanisms (BIM기반의 어셈블링 협업이 설계자 간의 의사교환과 사회심리학적 기제에 미치는 효과와 한계에 관한 연구)

  • Hong, Seung-Wan;Jeong, Yongwook
    • Journal of KIBIM
    • /
    • v.7 no.1
    • /
    • pp.36-44
    • /
    • 2017
  • While previous studies argue that BIM-based assembling collaboration promotes the communication and process management among participants in architectural design projects, it is still unknown which communication and socio-psychological factors are more and less activated in use of BIM-based collaboration. To investigate this research aim, in authentic BIM-used architectural retrofitting projects, the participants (N=36) collaborated and assessed the communication factors on (1) perceiving design results, (2)understanding partners'design intention, (3) proposing and converging opinions, the interpersonal design process management factors on (1) managing design process, (2) managing collaboration schedule, and the complementedness factors on (1) understanding partners' expertise, and comradeship. Statistical analyses reveal that the factor relevant to perceiving design results is better activated than the other factors (p<0.05), but all other factors are not much activated compared to perceiving design results. Deduced from the previous BIM studies and interviews, a reason roots in the shared forms and semantics of BIM. The shared semantics represent collaborators' information and allow the participants to perceive design changes explicitly. Meanwhile, BIM-based assembling collaboration is limited to represent observable, experience-able processes of design, and thus, several key socio-psychological factors, such as proposing and converging opinions and managing design process, are less activated.

BIM based Integration Method of Cost and Schedule Information (BIM기반 비용.일정 통합관리 방안에 관한 연구)

  • Jung, Do-Young;Baek, Yuong-In
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2008.11a
    • /
    • pp.321-325
    • /
    • 2008
  • 3D and BIM technology are presumed to be used more and more in the construction industry. The scope of this paper arose from a general wondering of how the constructor in general can benefit from the use of 3D models. Presented herewith is the first application of BIM in Korea to a actual bridge construction site located in Cheongpoong in Chooncheongbook-Do. This paper tries to integrate design, cost and schedule under location-based conditions with industry-specific solution for 3D modeling. 292 activities constitute the cable-stayed bridge of 442m long with a main span of 327m long. Integration of 3D model, cost and schedule is shown by comparing the measurements of works at a specific time by use of 2 different construction sequencing scenarios and cost breakdown structures.

  • PDF

Method of Deriving Activity Relationship and Location Information from BIM Model for Construction Schedule Management (공정관리 활용을 위한 BIM모델의 공정별 수순 및 위치정보 추출방안)

  • Yoon, Hyeongseok;Lee, Jaehee;Hwang, Jaeyeong;Kang, Hyojeong;Park, sangmi;Kang, Leenseok
    • Korean Journal of Construction Engineering and Management
    • /
    • v.23 no.2
    • /
    • pp.33-44
    • /
    • 2022
  • The simulation function by the 4D system is a representative BIM function in the construction stage. For the 4D simulation, schedule information for each activity must be created and then linked with the 3D model. Since the 3D model created in the design stage does not consider schedule information, there are practical difficulties in the process of creating schedule information for application to the construction stage and linking the 3D model. In this study, after extracting the schedule information of the construction stage using the HDBSCAN algorithm from the 3D model in the design stage, authors propose a methodology for automatically generating schedule information by identifying precedence and sequencing relationships by applying the topological alignment algorithm. Since the generated schedule information is created based on the 3D model, it can be used as information that is automatically linked by the common parameters between the schedule and the 3D model in the 4D system, and the practical utility of the 4D system can be increased. The proposed methodology was applied to the four bridge projects to confirm the schedule information generation, and applied to the 4D system to confirm the simplification of the link process between schedule and 3D model.

Automated Generation of a Construction Schedule Based on the Work Method Template for 4D Simulation (4D 시뮬레이션을 위한 공법 템플릿 기반의 건설공정 자동 생성)

  • Song, Sung-Yol;Yang, Jeong-Sam;Myung, Tae-Sik
    • IE interfaces
    • /
    • v.25 no.2
    • /
    • pp.216-228
    • /
    • 2012
  • BIM-based 4D simulation makes people easily understand complex construction process using 3D graphics model and helps them review and identify the construction schedule in each phase of the construction process. Moreover, 4D simulation can be used as reference data to determine the validity of the process in the design phase and will be utilized as a measure for checking the construction process. Therefore 4D simulation of construction improves efficiency of project management. However, current commercial applications available for 4D simulation do not provide sufficient functions for connection of 3D models and process information. In this paper, we propose an automated generation method through the definition of the process based on a work method template and developed the template based schedule generation system (TSGS).

Development of a Project Schedule Simulation System by a Synchronization Methodology of Active nD Object and Real Image of Construction Site

  • Kim, Hyeon Seung;Shin, Jong Myeong;Park, Sang Mi;Kang, Leen Seok
    • International conference on construction engineering and project management
    • /
    • 2015.10a
    • /
    • pp.344-348
    • /
    • 2015
  • The image data of the web camera is used to identify the construction status of the site in a remote office and it can be used for safety management. This study develops a construction schedule simulation system based on the active nD object linked with real image data of web camera from the construction site. The progress control method by 4D object uses a method that the progress of each activity is represented with different colors by progress status. Since this method is still based on a virtual reality object, it is less realistic description for practical engineers. Therefore, in order to take advantage of BIM more realistic, the real image of actual construction status and 4D object of planned schedule in a data date should be compared in a screen simultaneously. Those methodologies and developed system are verified in a case project where a web camera is installed for the verification of the system.

  • PDF

3D BIM-based Building Energy Efficiency Solution for Carbon Emission Reduction (탄소저감을 위한 3D BIM 기반 건물 에너지 효율화 방안)

  • Lee, Dong Hwan;Kwon, Kee Jung;Shin, Ju Ho;Park, Seunghee
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.33 no.3
    • /
    • pp.1235-1242
    • /
    • 2013
  • This study deals with the BIM (Building Information Modeling)-based energy performance analysis implemented in EnergyPlus. The BIM model constructed at Revit is updated at Design Builder, adding HVAC models and converted compatibly with the EnergyPlus. We can obtain the input values about HVAC system and building environment such as HVAC system efficient, the number of air changes and energy consumption of equipment on applying GAs (Genetic algorithms). After modification about HVAC system, Optimization about HVAC system energy consumption can be analyzed. In order to maximize the building energy performance, a genetic algorithm (GA)-based optimization technique is applied to the modified HVAC models. Throughout the proposed building energy simulation, finally, the best optimized HVAC control schedule for the target building can be obtained in the form of "supply air temperature schedule". Throughout the supply air temperature schedule is applied to energy performance simulation, we obtained energy saving effect result on simulation.

A Development of Unified and Consistent BIM Database for Integrated Use of BIM-based Quantities, Process, and Construction Costs in Civil Engineering

  • Lee, Jae-Hong;Lee, Sung-Woo;Kim, Tae-Young
    • Journal of the Korea Society of Computer and Information
    • /
    • v.24 no.2
    • /
    • pp.127-137
    • /
    • 2019
  • In this study, we have developed a calculation system for BIM-based quantities, 4D process, and 5D construction costs, by integrating object shape attributes and the standard classification system which consist of Cost Breakdown System(CBS), Object Breakdown System(OBS) and Work Breakdown System(WBS) in order to use for the 4 dimensional process control of roads and rivers. First, a new BIM library database connected with the BIM library shape objects was built according to the CBS/OBS/WBS standard classification system of the civil engineering field, and a integrated database system of BIM-based quantities, process(4D), and construction costs(5D) for roads and rivers was constructed. Nextly, the process classification system and the cost classification system were automatically disassembled to the BIM objects consisting of the Revit-family style elements. Finally, we added functions for automatically generating four dimensional activities and generating a automatic cost statement according to the combination of WBS and CBS classification system The ultimate goal of this study was to extend the integrated quantities, process(4D), and construction costs(5D) system for new roads and rivers, enabling the integrated use of process(4D) and construction costs(5D) in the design and construction stage, based on the tasks described above.

A Study on the Construction Management Method based on BIM for Civil Engineering Project (토목시설물에 대한 BIM기반 공사관리 기법 연구)

  • Kim, Sung-Hoon;Lee, Sang-Ho;Nam, Sang-Hyeok;Sun, Oh-Young
    • Journal of the Computational Structural Engineering Institute of Korea
    • /
    • v.24 no.4
    • /
    • pp.463-469
    • /
    • 2011
  • BIM(Building Information Modeling) technologies should be applied for the construction life cycle to maximize its efficiency, but the utilization for the construction phase has been significantly lower than that for the planning and design phase. Recently, some of BIM techniques such as 3D design review, 4D schedule management and so on are being introduced for efficient managing to the big national construction projects. In this study, the utilization plans of BIM are presented for the construction phase of civil engineering facilities. The methods of utilization of BIM are discussed for each type of construction, and the techniques applied to the Seoul Subway Lot No. 919 are analyzed for checking the applicability and usability. In particular, a web construction management system based on BIM can help field engineers, headquarters and contractors to use BIM more effectively, and it can be extended to maintenance phase for more efficiencies.