Advancement of Blast Effect by Inducing Drill Jumbo on Automatic Drilling System (점보드릴 자동천공 시스템 도입에 의한 발파효과 향상)

  • Kim, Seung-Jun;Kim, Jeong-Gyu;Ko, Young-Hun;Ahn, Je-Min;Kim, Nam-su;Yang, Hyung-Sik
    • Explosives and Blasting
    • /
    • 제34권2호
    • /
    • pp.10-17
    • /
    • 2016
  • Drilling operation for blasting is an important factor to determine blast effect. Drilling errors that arise from performing drilling for blasting purposes can reduce blasting effect causing residual holes, overbreak, and heterogeneous fragmentation, etc. Automatic drilling system was induced for precise drilling. As a result, drilling error caused by spaces between holes and burden was minor at 0~2.6% and accordingly, blasting effect was improved with over 90% drilling rate, the ratio of overbreak amount to total drilling amount at 4.3%, proportion of fragmentation rock under 50cm at 89~95% and so from this analyses, it was estimated to reduce the total cycle times related to blasting process.

A Study on Estimating Time for PRD (Percussion Rotary Drill) Piling Work (도심지 토공사 PRD (Percussion Rotary Drill) 공법의 천공작업 소요시간 산정 방안에 관한 연구)

  • Kim, Yong-Gyu;Choi, Chang-Hoon;Han, Choong-Hee;Lee, Junbok
    • Korean Journal of Construction Engineering and Management
    • /
    • 제19권3호
    • /
    • pp.3-10
    • /
    • 2018
  • In recent years, mechanized construction has become commonplace due to increases in the scale and complexity of construction, and construction machinery is a major factor in successful construction. However, even though the proportion of construction machinery is increasing, analysis of the work capacity of construction machinery is inadequate. In addition, since the standards for all construction machines are currently not defined in quantity-per-unit, the construction period is arbitrarily applied according to the operator at the time of the construction plan. As a result, the construction period of the actual construction is insufficient, and rushed work or construction delays occur. Therefore, in this study, in order to calculate the construction period of the piling work of the pile driver used in the PRD method more accurately than the existing method, the formula for calculating the time required for the piling work of the pile driver was established by collecting piling time data from the daily task reports through the field survey. If the precise construction period of piling work is estimated based on the results of this study, it will be possible to prevent the rushed work and construction delays that occur due to the short construction period.

A Study on the Drilling Methods to reduce Overbreak in Tunnel Blasting (터널발파 작업시 여굴 저감을 위한 천공방법 연구)

  • 김양균;김형철;유정훈
    • Explosives and Blasting
    • /
    • 제21권2호
    • /
    • pp.1-13
    • /
    • 2003
  • Overbreak or underbreak is one of the most important factors in evaluating the results of a tunnel blasting. Overbreak, which depends on the quality of rock, the type and quantity of explosives, and drilling conditions, has been a target of challenge to many blasting engineers because it directly affects construction cost. Drilling is generally known as one of the primary factors to generate overbreak. This study presents a real working model to reduce overbreak based on the analysis of drilling accuracy and overbreak generated from various working methods related to drilling. As the first step of the study, 45 experiments have been performed. The factors investigated are: marking contour line, the position of perimeter holes, the change of look-out with drilling rig position, and the proper space between perimeter holes. It is concluded that workers and engineers' will and efforts are the most important factors to reduce overbreak and that improving drilling method and pattern could reduce overbreak to a considerable amount.

Hole Navigation System Development in Drilling Rig (천공기의 천공위치 안내 시스템 개발)

  • Kim, Je-Dong;Kang, Byung-Soo;Hahm, Young-Gook;Yoo, Jae-Sung;Lee, Duck-Hwan;Cho, Jae-Sang
    • Proceedings of the Korea Information Processing Society Conference
    • /
    • 한국정보처리학회 2016년도 추계학술발표대회
    • /
    • pp.783-784
    • /
    • 2016
  • 천공위치 안내 시스템은 천공작업 Hole의 정확한 위치를 추적하는 시스템이다. 천공작업의 정확성과 안정성, 그리고 장비 조작의 용이성을 위하여 범지구 위성 항법 시스템(Global navigation satellite system, GNSS)을 이용하여 지표면의 천공위치를 찾아주는 안내 시스템을 연구 개발하였다.

Effect of RMR and rock type on tunnel drilling speed (RMR과 암석종류가 터널 천공속도에 미치는 영향)

  • Kim, Hae-Mahn;Lee, In-Mo;Hong, Chang-Ho
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • 제21권4호
    • /
    • pp.561-571
    • /
    • 2019
  • Drilling and charging of the blast holes during NATM tunneling works take more than 30% of construction time among the whole tunneling work process. Prediction of ground condition ahead of tunnel face has been studied by several researchers by correlating percussion pressure and drilling speed during tunneling work with the ground condition and/or RMR values. However, most of the previous researches were conducted in the granite rock condition which is the most representative igneous rock in the Korean peninsula. In this study, drilling speeds in igneous rocks were analyzed and compared with those in sedimentary rocks (most dominantly composed of conglomerates, sandstones, and shales) under the similar RMR ranges; it was identified that the drilling speed is pretty much affected by rock types even in a similar RMR range. Under the similar RMR values, the drilling speed was faster in sedimentary rocks compared with that in igneous rock. Moreover, while the drilling speed was not much affected by change of the RMR values in igneous rocks, it became faster in sedimentary rocks as the RMR values got lower.

The Effect of Drilling Patterns and Rock Mass Conditions on Fragmentation and Ground Vibration in Quarry Blasting (천공방식과 암질등급이 파쇄도와 진동수준에 미치는 영향)

  • 정영준;양형식;이상은
    • Explosives and Blasting
    • /
    • 제20권1호
    • /
    • pp.5-14
    • /
    • 2002
  • 파쇄 암석의 파쇄도는 발파효율을 나타내는 중요 척도로서 적재와 분쇄 작업에 큰 영향을 미친다. 그러나 현장에 쌓여 있는 발파암 더미로부터 파쇄도를 조사한다는 것은 용이한 작업이 아니다. 본 연구에서는 석산 발파에서 가장 중요한 요소인 천공방식과 암질의 변화가 파쇄도와 발파진동에 미치는 영향을 조사하였다. 파쇄 입도에 영향을 미치는 중요한 변수인 천공방식, 암질등급(RMR), 현지 암반의 블록 크기, 발파진동 등의 영향을 파쇄암의 평균입도(MFS)와 상위 5개의 대괴 평균치$(L_5)$로 나타내었다. 연구결과, 파쇄암의 평균입도는 상위 5개의 대괴 평균치와 선형적인 관계를 보였다. 발파방법과 파쇄도 평가 결과 재래식 발파에서는 파쇄도를 예측할 수 없었고 커다란 옥석이 생성되었으나, 벤치발파에서는 평균파쇄암의 크기가 비교적 양호한 파쇄 상태를 유지하였다. 현지 암반 블록 크기는 평균 파쇄암의 크기와 선형적 관계를 나타내었다. RMR값이 커짐에 따라 발파진동 추정식의 진동상수 K와 감쇠지수 n의 절대값과 평균 파쇄암의 크기, 그리고 상위 대괴의 크기는 대체적으로 증가하는 경향을 나타내었고, 진동상수 K와 감쇠지수 n도 증가하는 경향을 보였다.

Estimation of Rock Drilling Work Size for Mountain Forest Road Construction (산악지(山岳地) 임도시설(林道施設)을 위한 암석천공(岩石穿孔) 작업량(作業量)의 예측(豫測))

  • Ma, Sang Kyu
    • Journal of Korean Society of Forest Science
    • /
    • 제76권3호
    • /
    • pp.193-199
    • /
    • 1987
  • Simple estimating method of rock drilling and blasting work size is necessary to apply as a guidance of general road plan and a cost analysis of mountain forest road construction. For this work study, 11 cycles were divided in 5km route at Hyeonnammeon Yangyang-gun and the mountain slope at every 20m interval was measured. During working days all kind of works concerned on drilling and blasting was investigated in every cycle. Depending on the simple work study results it's work size can bef estimated with high correlation between drilling length in meter and frequency percentage of mountain slope more than 70%. With total drilling length known the machinery hours, drillers and explosive quantify can be estimated by the regression with high correlation. Estimation of drilling and blasting work by mountain slope gradient in road route is proposed like table 5 with estimating value of machinery hour, drillers and explosive in granite gneiss region.

  • PDF

Improvement on the estimation of workable-quantity per unit time for boring machine (기초공사 천공기계 시간당작업량 산정 개선방안)

  • Ahn, Bang-Ryul
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 한국건축시공학회 2015년도 춘계 학술논문 발표대회
    • /
    • pp.138-139
    • /
    • 2015
  • Human productivity of Boring Machine for stack is provided but not its hourly workable quantity(Q-value) in the Equipment ownership cost and expenses section of the Poom-Same that is used for construction cost estimation of public sectors in Korea, which leads to less realistic and subjective estimation for the works. The optimized Q-value of the machine is proposed as a result of thorough investigation into many of its operations.

  • PDF

Analytic Hierarchy Process Analysis on Correlation Between Drilling Error and Blasting Accuracy (발파공의 천공오차와 발파정확도의 상관성에 관한 현장조사 및 계층분석기법 연구)

  • Lee, Deok-Hwan;Choi, Sung-Oong;Kim, Chang-Oh
    • Tunnel and Underground Space
    • /
    • 제24권5호
    • /
    • pp.386-394
    • /
    • 2014
  • Drilling accuracy is known to be one of the most important factors determining blasting efficiency in mining by blast operation. Therefore analysing the causes of drilling error and preparing a countermeasure for minimizing drilling error are very important for blasting efficiency and safety. In this study, causes of drilling error are analyzed with dividing them into controllable factors and uncontrollable factors, and relationship between each cause is also comprehended through field measurement and AHP analysis. Finally, effective measures to help lower the drilling error are proposed with the results from weighting analysis for each factor.