• Title/Summary/Keyword: 책임일수 산정 시스템

Search Result 3, Processing Time 0.018 seconds

Estimating System for Responsible Days of Schedule Delay for Construction Projects through Time Impact Analysis (건설공사 공기지연 영향분석을 통한 책임일수 산정체계 구축방안)

  • Kang, Leen-Seok;Kwon, Jung-Hee
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.28 no.5D
    • /
    • pp.685-694
    • /
    • 2008
  • Recently, construction projects are being gradually changed to large projects with complicated work processes. As a result, claims are increasing as well. Of these, the claims by delayed construction duration are given much weight in the general construction claims. To solve this problem, researches to estimate damages due to delay are carried out in research institutes by analyzing the causes of schedule delay. A system to easily estimate responsible days by analyzing the complicated processes needs for project manager. This study suggests a methodology based on the time impact analysis method, which can utilize the consequential analytical method with the consideration of reduced construction period. The suggested methodology is verified by comparing with actual data of case study by the computerized system for estimating the responsible days.

Function Development for Apportioning System of Responsible Number of Days by Construction Delay (공기지연에 따른 책임일수 산정 시스템 구축방안)

  • Kang, Leen-Seok;Kwon, Jung-Hui;Park, Seo-Young;Yun, Seon-Mi
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2007.11a
    • /
    • pp.805-808
    • /
    • 2007
  • Recently there are many contract claims, which are caused by duration delay, in construction industry. Many kinds of research for solving such duration delay problem are being progressed and an effective computerized system needs to improve it. This study suggests an improved methodology and necessary functions to make a time impact analysis system. This results will be useful for quantifying responsible number of days caused by duration delay.

  • PDF

Apportionment of Liquidated Damages and Compensation for Delay Damages in Domestic Construction Project : Analysis and Improvement (국내 현행 공기지연 책임에 따른 지체상금 및 손실보상의 문제점 및 개선방안)

  • Kim, Kyong Ju;Kim, Kyoungmin;Kim, Jong Inn;Wei, Ameng;Kim, Eu Wang
    • Korean Journal of Construction Engineering and Management
    • /
    • v.24 no.1
    • /
    • pp.12-20
    • /
    • 2023
  • To calculate the amount of owner-caused and contractor-caused delays based on a simplified delay analysis, which has been customarily used in Korea, has a limitation in reflecting the impact of the concurrent delay and the acceleration work. It also resulted in the apportionment of liquidated damages by applying the ratio of the number of delays between the owner and the contractor. This study analyzes that the conventional method does not meet the international standards. In order to improve the problem of construction delay analysis and the apportionment of liquidated damages based on it, owner delays, contractor delays, concurrent delays, and the impact of acceleration should be analyzed together. This study suggests that in the apportionment of liquidated damages, the extension of time should be extended by the sum of concurrent delays and the owner-caused delays, and liquidated damages should be imposed on delays incurred after the extension of time. It can be seen that it conforms to the international standards. The results of this study are expected to contribute to improving the problems of delay analysis and liquidated damages calculation, which have been conventionally accepted.