Schedule Computation Method of Two-way Multiple Overlapping Relationships on BDM Technique (BDM 기법에서 양방향 다중 중복관계 일정계산 방법)

  • Kim, Seon-Gyoo;Noh, Seong-Beom;Lee, Yong-Hyun;Yu, Young-Jeong;Kim, Jin-Bong;Koo, Jae-Oh
    • Korean Journal of Construction Engineering and Management
    • /
    • v.13 no.2
    • /
    • pp.120-127
    • /
    • 2012
  • Today, most construction projects have been higher, bigger, and more complicated gradually. So the domestic construction companies have been trying to understand overall construction process and relationships between activities, and adopted various management techniques and tools in order to perform a systematic and effective scheduling. However numerous problems have been occurred on the practical applications because most existing scheduling softwares adapt ADM and PDM techniques. One of them, PDM, is so uneffective because it represents the overlapping relationships between two consecutive activities only by the combinations of start and finish points between two activities. In order to supplement the demerit of PDM, Beeline Diagramming Method(BDM) is proposed as a new networking technique, it can represent two-way multiple overlapping relationships between two activities directly. However there are occurring a loop phenomenon on applying two-way multiple overlapping relationships. This research proposes and verifies the schedule computation method of two-way multiple overlapping relationships on the BDM network.