• Title/Summary/Keyword: 수직 갱도

Search Result 37, Processing Time 0.02 seconds

The study of operation mode of ventilation system in the longitudinal ventilation system tunnel (조합환기 방식 터널의 환기기 운전 단계에 관한 연구)

  • Yoo, Ji-Oh;Shin, Hyun-Jun;Lee, Dong-Ho;Lee, Young-hwa
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.4 no.4
    • /
    • pp.343-353
    • /
    • 2002
  • In the past many tunnels have been built to lowest capital investment cost without adequate regard for the cost of operation. But according to increasing the capacity of a ventilation system and to becoming diverse, it is to become more important to come up with the optimal operation stage of ventilation system. In this study, the tunnel ventilation dynamic simulation program had been developed. it is used to calculate the unsteady-state tunnel air velocity and concentration of pollutants according to the assumed average day traffic profile and summarize the energy consumption for the operation of ventilation system. And the operation energy consumption for the electric precipitation system and vertical vent shaft system are evaluated and compared in various operation mode. As the results of this study, the optimal operation stage for these ventilation system are provided.

  • PDF

Development of an In Situ Direct Shear Test Apparatus and Its Field Application (현장직접전단시험기의 개발 및 현장적용에 관한 연구)

  • Kim, Yong-Phil;Lee, Young-Kyun;Lee, Sung-Kook;Um, Jeong-Gi
    • Tunnel and Underground Space
    • /
    • v.21 no.3
    • /
    • pp.181-191
    • /
    • 2011
  • It is very difficult to prepare a lab. test specimen from weak rock masses affected by faults, highly fractured zone or weathered zone. In conventional method of in situ direct shear test a rock block is sheared inside galleries, where reactions for the hydraulic jacks are available. A new in situ direct shear test apparatus has been developed in this study to perform the test inside galleries as well as open pit conditions. The apparatus is composed of normal and shear reaction plates including load transfer plates, hydraulic cylinder systems, load cells, multistage shear boxes with fixing devices, and needle rollers. Maximum size of the test block is $400{\times}400{\times}460$ mm, and procedures of the test block preparation has been suggested. To explore the field applicability of in situ direct shear test apparatus, proper test block site was investigated by extensive geological field survey. In situ direct shear test has been successful in producing most of information related to strength and deformability of the weak rock.

Analysis of Mechanical Behavior of Existing Tunnel by the Construction of Shaft Nearby (근접한 수직구 건설에 따른 기존 터널의 역학적 거동 분석)

  • 이석원;조만섭;이성원
    • Journal of the Korean Geotechnical Society
    • /
    • v.19 no.5
    • /
    • pp.109-122
    • /
    • 2003
  • In order to release the pressure fluctuations and micro-pressure wave induced by the entering of train into the small cross sectional tunnel, it has been reported that the construction of air shaft has more advantages with respect to economy and constructability than the enlargement of cross section of existing tunnel. The field monitorings and analytical studies were conducted simultaneously in this study to analyze the mechanical behavior of existing railway tunnel, new cross tunnel and new shaft by the construction of new shaft nearby. The results showed that the minimum distance from existing tunnel to new shaft which secures the stability of existing tunnel was found to be half diameter of existing tunnel. On the three dimensional mechanical behavior of existing tunnel by the construction of new shaft, the results from the analytical study and field monitoring had a similar trend. The analytical study and field monitoring results, however, produced somewhat different results on the mechanical behavior of new shaft itself. These conclusions induce that the analytical method which has been applied on the analyses of horizontal tunnel could not be applied in the same way on the analysis of vertical shaft.

A Case Study of Electrical Resistivity and Borehole Imaging Methods for Detecting Underground Cavities and Monitoring Ground Subsidence at Abandoned Underground Mines (폐광산 지역의 공동 탐지 및 지반침하 모니터링을 위한 전기비저항탐사와 시추공영상촬영기법 적용 사례)

  • Choi, Jeong-Ryul;Kim, Seung-Sep;Park, Sang-Kyu;Shin, Kwang-Soo;Kang, Byung-Chun
    • Journal of the Korean earth science society
    • /
    • v.34 no.3
    • /
    • pp.195-208
    • /
    • 2013
  • We employed electrical resistivity and optical borehole imaging methods to identify underground cavities and determine ground subsidence rate at the study area affected by land subsidence due to abandoned underground mines. At the study site 1, the anomalous zones of low resistivity ranging between 100 ohm-meter and 150 ohm-meter were observed and confirmed as an abandoned underground mine by subsequent borehole drilling and optical borehole imaging. Although the electrical resistivity survey was unavailable due to the paved surface of the study site 2, we were able to locate another abandoned underground mine with the collapsed mine shaft based on the distribution of the ore veins and confirmed it with borehole drilling. In addition, we measured vertical displacements of underground features indicating underground subsidence by conducting optical borehole imaging 6 times over a period of 43 days at the study site 2. The displacement magnitude at the deep segment caused by subsidence appeared to be 3 times larger than those at the shallow segment. Similarly, the displacement duration at the deep segment was 4 times longer than those at the shallow segment. Therefore, the combination of electrical resistivity and optical borehole imaging methods can be effectively applicable to detect and monitor ground subsidence caused by underground cavities.

A Study on Ventilation System of Underground Low-Intermediate Radioactive Waste Repository (지하 동굴식 중-저준위 방사성 폐기물 처분장의 환기시스템 고찰)

  • Kim, Young-Min;Kwon, O-Sang;Yoon, Chan-Hoon;Kwon, Sang-Ki;Kim, Jin
    • Journal of Nuclear Fuel Cycle and Waste Technology(JNFCWT)
    • /
    • v.5 no.1
    • /
    • pp.65-78
    • /
    • 2007
  • The pollutants (Rn, CH, CO, HS, radioactive gas from radiolysis) were generated from the process of construction and operation of underground repository, and after disposal of low-intermediate radioactive waste inside there must be controlled by a ventilation system to distribute them in area where enough air is supported. Therefore, a suitable technical approach is needed especially at an underground repository that is equipped with many entry tunnels, storage tunnels, exhaust-blowing tunnels, and vertical shafts in complicated network form. For the technical approach of such a ventilation system, WIPP (Waste Isolation Pilot Plant) in U. S and SFR (Slutforvar for Reaktorafall) low-intermediate radioactive waste repository in Sweden were selected as the models, for calculating the required air quantity, organizing a ventilation network considering cross section, length, surface roughness of the air passage, and describing a calculation of resistance of each circuit. Based on these procedures, a best suited ventilation system was completed with designing proper capacity of fans and operating plan of vertical shafts. As a result of comparing the two repositories based on the geometry dimensions and ventilation facility equipment operation, more parallel circuit as in WIPP, brought decrease in resistance for entire system leading to reduce of operating costs, and the larger cross-sectional area of the SFR, the greater the percentage of disposal capacity. Accordingly, the mixture of parallel circuit of WIPP repository for reducing resistance and SFR repository formation for enlargement of disposal capacity would be the most rational and efficient ventilation system.

  • PDF

Stability Analysis of Multiple Thermal Energy Storage Caverns Using a Coupled Thermal-Mechanical Model (열-역학적 연계해석 모델을 이용한 다중 열저장공동 안정성 분석)

  • Kim, Hyunwoo;Park, Dohyun;Park, Eui-Seob;Sunwoo, Choon
    • Tunnel and Underground Space
    • /
    • v.24 no.4
    • /
    • pp.297-307
    • /
    • 2014
  • Cavern Thermal Energy Storage system stores thermal energy in caverns to recover industrial waste heat or avoid the sporadic characteristics of renewable-energy resources, and its advantages include high injection-and-extraction powers and the flexibility in selecting a storage medium. In the present study, the structural stability of rock mass pillar between these silo-type storage caverns was assessed using a coupled thermal-mechanical model in $FLAC^{3D}$. The results of numerical simulations showed that thermal stresses due to long-term storage depended on pillar width and had significant effect on the pillar stability. A sensitivity analysis of main factors indicated that the influence on the pillar stability increased in the order cavern depth < pillar width < in situ condition. It was suggested that two identical caverns should be separated by at least one diameter of the cavern and small-diameter shaft neighboring the cavern should be separated by more than half of the cavern diameter. Meanwhile, when the line of centers of two caverns was parallel to the direction of maximum horizontal principal stress, the shielding effect of the caverns could minimize an adverse effect caused by a large horizontal stress.

Passive control of unsteady compression wave using vertical bleed ducts (수직갱을 이용한 터널내 비정상 압축파의 피동제어)

  • Kim, Hui-Dong;Setoguchi, Toshiaki
    • Transactions of the Korean Society of Mechanical Engineers B
    • /
    • v.21 no.9
    • /
    • pp.1095-1104
    • /
    • 1997
  • When a high-speed railway train enters a tunnel, a compression wave is generated ahead of the train and propagates along the tunnel, compressing and accelerating the rest air in front of the wave. At the exit of the tunnel, an impulsive wave is emitted outward toward the surrounding, which causes a positive impulsive noise like a kind of sonic boom produced by a supersonic aircraft. With the advent of high-speed train, such an impulsive noise can be large enough to cause the noise problem, unless some attempts are made to alleviate its pressure levels. For the purpose of the impulsive noise reduction, the present study investigated the effect of a vertical bleed duct on the compression wave propagating into a model tunnel. Numerical results were obtained using a Piecewise Linear Method and testified by experiment of shock tube with an open end. The results showed that the vertical bleed duct reduces the maximum pressure gradient of compression wave front by about 30 percent, compared with the straight tunnel without the bleed duct. As the width of the vertical bleed duct becomes larger, reduction of the impulsive noise is expected to be greater. However the impulsive noise is independent of the height of the vertical bleed duct.

Determination of Surge Tank Scale for Dam Safety Management (댐 안전관리를 위한 조압수조의 규모 결정)

  • Lee, Ho Jin
    • Journal of the Korea institute for structural maintenance and inspection
    • /
    • v.11 no.2
    • /
    • pp.164-174
    • /
    • 2007
  • Phenomena of hydraulic transient such as water hammer should be analyzed to design the pipeline systems effectively in dam. Surge tanks generally are used to reduce change in pressure caused by hydraulic transient from load changes on the turbines. In this study, the appropriate scale of surge tank with chamber is investigated for dam safety management. The variation of water level in the surge tank are computed using governing equation. Using the Thoma-Jaeger's stability condition, static and dynamic stability are investigate for the cases of flood water level, normal high water level, rated water level and low water level. Finally appropriate diameters of shaft and chamber are determined in the surge tank with chamber.

Exploration and Development in the Janggun Pb-Zn Mine (장군광산(將軍鑛山)의 탐사(探査)와 개발현황(開發現況))

  • Kho, Suck Jin
    • Economic and Environmental Geology
    • /
    • v.20 no.4
    • /
    • pp.289-303
    • /
    • 1987
  • 당(當) 광산(鑛山)은 1936년(年) 금(金), 은(銀) 광종(鑛種)으로 출원(出願)하였다가 1940년(年) 망간을 추가(追加)하여 망간 광산(鑛山)으로 1975년(年)까지 Mn(30~35%) 110,000여(餘)톤을 생산(生産), 국내생산량(國內生産量)의 70%를 점(占)하였고 1976년(年) Mn광상(鑛床) 하부(下部)에 연(鉛), 아연(亞鉛) 유화광(硫化鑛)을 발견(發見), 현재(現在)까지 Pb十Zn=10% 이상(以上) 원광석(原鑛石) 500,000여(餘)톤을 처리(處理), 연정광(鉛精鑛)(Pb : 62%) 37,000여(餘)톤, 아연정광(亞鉛精鑛)(Zn : 46.5%) 37,000여(餘)톤, 유비광정광(硫砒鑛精鑛)(As : 30%) 5,000여(餘)톤을 생산(生産)하였다. 현재(現在) 일처리(日處理) 220톤 선광장(選鑛場)을 일처리(日處理) 400톤 규모(規模)로 증설계획중(增設計劃中)이다. 당(當) 광산(鑛山)에서 현재(現在)까지 시행(施行)한 갱외시추(坑外試錐)는 75개공(個孔) 18,500여(餘)m, 갱내시추(坑內試錐) 750개공(個孔) 40,000여(餘)m 갱도(坑道) 총연장(總延長) 13,000m에 달(達)하며 지표(地表)(623ML)로 부터 수직(垂直) 300m 하부(下部)까지 갱도(坑道)가 개착(開鑿)되어 있다. 당(當) 광산(鑛山)의 지질(地質)은 여러 조사서(調査書)에 의(依)하여 견해(見解) 차이(差異)를 보여주고 있으나 대체(大體)로 다음과 같은 쪽으로 인정되고 있다. 즉(卽) 본지역(本地域) 루층군(累層群)의 층순(層順)을 하위(下位)로 부터 상위(上位)로 향(向)하여 원남층(遠南層)${\rightarrow}$율리통(栗里統)${\rightarrow}$장산규암층(壯山珪岩層)${\rightarrow}$두음리층(斗音里層)${\rightarrow}$장군석회암층(將軍石灰岩層)${\rightarrow}$동수곡층(東水谷層)${\rightarrow}$재산층(才山層)의 순위(順位)로 보며 장산규암층(壯山珪岩層)과 두음리층(斗音里層)을 조선계(朝鮮系)의 양덕통(陽德統)으로, 장군석회암층(將軍石灰岩層)을 대석회암통(大石灰岩統)으로, 동수곡층(東水谷層)과 함탄층(含炭層)인 재산층(才山層)을 평안계(平安系) 지층(地層)으로 대비(對比)한다. 이들은 본지역(本地域) 북(北)쪽에서는 선(先)캠브리아기(紀)의 원남층(遠南層)과 율리통(栗里統)을 불정합(不整合)으로 덮고 남측(南側)에서는 재산층(才山層)과 원남층(遠南層)이 단층접촉(斷層接觸)하고 있다. 이들 지층(地層)의 주향(走向)은 $N60^{\circ}{\sim}80^{\circ}W$, $N60^{\circ}{\sim}80^{\circ}E$이며 경사(傾斜)는 대체(大體)로 $50^{\circ}{\sim}80^{\circ}N$이며 전체적(全體的)으로 역전(逆轉)된 층서(層序)를 보여주는 바 지질구조(地質構造)에 있어서 단사구조(單斜構造)인지 등사(等斜)습곡의 향사(向斜), 또는 등사(等斜)습곡이 배사구조(背斜構造)인지 아직 밝혀지지 않고 있다. 화성암체(火成岩體)는 본지역(本地域) 서측(西側)에 쥬라기(紀) 춘양화강암(春陽花崗岩)이 불규칙(不規則)한 실입(實入) 접촉면(接觸面)을 보여주며 시대미상(時代未詳)(백악기(白堊紀)?)의 거정화강암(巨晶花崗岩), 반화강암(半花崗岩)이 소암주상(小岩株狀)으로 몇 곳 실입(實入)하고 산성(酸性)~중성(中性)의 맥암(脈岩)과 염기성(鹽基性) 안산암질암(安山岩質岩)이 실입(實入)해 있다. 광상(鑛床)은 장군석회암층(將軍石灰岩層)에 배태(胚胎)되어 있는 열수교대(熱水交代) 연(鉛), 아연(亞鉛), 은등(銀等)의 혼합(混合) 유화광상(硫化鑛床)으로 다량(多量)의 Mn분(分)을 수반(隨伴)하며 지표부(地表部)에 Mn광상(鑛床)을 형성(形成)하고 있다. 광상(鑛床)의 형태(形態)는 괴상(塊狀), 각력(角礫)pipe상(狀), 맥상(脈狀)으로 나타난다. 광상(鑛床)의 성인(成因)과 생성시기(生成時期)에 대(對)하여 많은 논란(論難)이 있다. 즉(卽) 열수교대(熱水交代)냐, 접촉교대(接觸交代)냐, 동시퇴적기원(同時堆積起源)이냐, 또는 생성시기(生成時期)가 쥬라기(紀)인지 백악기(白堊紀)인지에 대해 이론(異論)이 있다. 본지역(本地域) 광상(鑛床)은 남본(南本), 100우(右), 북(北), 유비철(硫砒鐵), 동(東), 서(西), 재남(才南), 재동(才東), 110호(號) 등(等)이 지표(地表) Mn로두광화대(露頭鑛化帶)와 관련(關聯) 명명(命名)된 바 전(前)4자(者)는 하부(下部)에서 유화광상(硫化鑛床)이 확인(確認)되었으나 나머지 후자(後者)에서는 아직 하부(下部)에 유화광상(硫化鑛床)이 확인(確認)되지 않고 있으며 남본광상(南本鑛床)으로 부터 남동(南東) 300여(餘)m 지점에 장군석회암층(將軍石灰岩層)과 동수곡층(東水谷層) 경계부(境界部)에 Fe 55~60% 자철광상(磁鐵鑛床)이 확인(確認)된 바 신례미(新禮美) 자철광상(磁鐵鑛床)과 유사성(類似性)이 있는 것 같아 흥미(興味)롭다. 당(當) 광산(鑛山)의 현재(現在)까지의 탐광(探鑛)은 남본광상(南本鑛床) 지표로두(地表露頭)(Mn) 하부(下部)에서 확인(確認)된 연(鉛), 아연(亞鉛), 은(銀) 유화광체(硫化鑛體) 하부(下部)와 전탐(電探)에 의(依)해 확인(確認)된 북광체(北鑛體), 갱도접근중(坑道接近中)에 확인(確認)된 100우광체(右鑛體), 유비철광체(硫砒鐵鑛體) 등(等)의 하부(下部) 탐광(探鑛)을 주(主)로 하고 지표(地表) Mn로두(露頭) 하부(下部)에 대(對)한 시추탐광(試錐探鑛0을 병행(竝行)하고 있으며 시추(試錐)에 의(依)해서 지표(地表)로 부터 790m 하부(下部)(해발(海拔) 200ML)까지 광화대(鑛化帶)가 확인(確認)되었다. 향후(向後) 탐광방침(探鑛方針)을 확고(確固)히 수립(樹立)하기 위(爲)하여는 광상(鑛床)의 성인구명(成因究明)은 물론(勿論) 광상(鑛床)의 배태조건(胚胎條件)에 있어 지질구조규제(地質構造規制)와 화강암(花崗岩)의 실입상(實入狀)과의 관계(關係), 광액(鑛液)의 통로(通路)에 대(對)한 지질구조(地質構造), 모암(母岩)의 화학(化學) 물리적(物理的) 특성(特性)에 대(對)한 연구(硏究) 검토(檢討)가 었어야 하겠다.

  • PDF

A Study on Evaluation of Thermal Environment using Heat Stress Indices for Deep Coal Mine in Korea (열적지표를 적용한 국내 고심도 석탄광산의 열환경 평가 연구)

  • Park, Seon-Oh;Roh, Jang-Hoon;Kim, Jin
    • Tunnel and Underground Space
    • /
    • v.24 no.2
    • /
    • pp.166-175
    • /
    • 2014
  • In this study, the thermal environment in a large scale coal mine located in Taebaek, Gangwondo was assessed by a field survey. In order to estimate the thermal environment, various heat stress indices such as WBGT, HSI, ESI, KATA index and effective temperature were investigated. Correlation analysis was also conducted. It was found that the thermal environment in most workplace was high. In particular, the correlation coefficient between HSI reflected in physiological fatigue characteristic and the maximum sweat evaporation heat was -0.834. This shows that the correlation coefficient have the most influence on HSI index. The factor which has the most influence on the maximum sweat evaporation heat is velocity of air. The thermal environment of high-depth coal mines is likely to be improved by installing a structure that enables the maximum prevention of extended digging, air doors, or the leakage of the inflow of air in the first shaft.