A Study on Considering Non-Working Days for Determination Normal Project Duration in the Railway Bridgework Construction (철도 교량공사의 적정공사기간 산정을 위한 비작업일 산정에 관한 연구)

  • Chae, Su Min;Lee, Sang Hyuck;Park, Hyung Keun
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.41 no.5
    • /
    • pp.601-608
    • /
    • 2021
  • Recently, despite a decrease in the number of working days and an increase in the number of non-working days due to an increase in the abnormal climate and the revision of the Labor Standards Act, a standard construction period reflecting this has not been established. For this reason, even if the appropriate construction period is calculated at the site, there is a situation where delays occur due to unexpected circumstances. Therefore, this study proposes a method of calculating the number of non-working days for railway bridgework construction that reflects changes in construction conditions and climate change and reflects this to railway bridgework construction, and the number of working days was calculated. As a result, the number of non-working days by region and month in Korea was derived, and through this, the necessity of regulations and standards for appropriate construction periods reflecting regional characteristics and characteristics of each construction type was presented.

Optimization of Estimating Duration of the Structural Frame for the High-rise Apartment Housing during the Winter season -Focusing on One Cycle Time Scheduling Mechanism of the Typical Floor- (동절기 아파트 골조공사의 적정공기 산정에 관한 연구 - 기준층 사이클 공정분석을 중심으로 -)

  • Bang Jong-Dae;Han Choong-Hee;Kim Sun-Kuk
    • Korean Journal of Construction Engineering and Management
    • /
    • v.5 no.6 s.22
    • /
    • pp.170-178
    • /
    • 2004
  • Public construction companies have strictly followed a rule that they should not work in the wet area such as structural frame for a certain period during the winter season. It is usually known that the non-working period during the winter causes increase of the project duration, and the project cost escalation. Also, it makes negative effects on national economy because it reduces workers income. Therefore, the site work for the structural frame should be performed even during the whiter season. But the site work for the structural frame during that period cannot proceeds in the same way as during other periods, and requires a different method for estimating project duration. Through an analysis of time scheduling mechanism, actual working days are obtained for 1 cycle of typical floors in the structural frame during these periods, and non-working days of 5 years average are calculated based on calendar day using data of 5 years weather forecasts for that season. This study proposes an optimized way of estimating project duration for 1 cycle of typical floors in the structural frame during these periods. This estimating method uses the combined actual working days and non-working days of 5 years' average, and the estimated results are confirmed by being compared with field data. This study is expected to be used in estimating the construction duration of the structural frame during the winter season.