• Title/Summary/Keyword: 굴착량

Search Result 300, Processing Time 0.028 seconds

Damage Analysis of Nearby Structures with the Consideration of Tunnel Construction Conditions in Sandy and Clayey Ground (모래 및 점토지반에서 터널시공조건을 고려한 인접구조물의 손상도 분석)

  • Son, Moorak;Yun, Jongcheol
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.31 no.1C
    • /
    • pp.53-63
    • /
    • 2011
  • This paper investigates the effects of tunnelling-induced ground movements on nearby structures, considering soil-structure interactions of different ground (loose sand, dense sand, soft clay, stiff clay) and construction conditions (ground loss). The response of four-story block structures, which are subjected to tunnelling-induced ground movements, has been investigated in different ground and construction conditions (ground loss) using numerical analysis. The structures for numerical analysis has been modelled using Discrete Element Method (DEM) to have real cracks when the shear and tensile stress exceed the maximum shear and tensile strength. The response of four-story block structures has been investigated with a ground movement magnitude and compared in terms of ground and construction conditions (ground loss) considering the magnitude of deformations and cracks in structures. In addition, the damage levels, which are possibly induced in structures, has been provided in terms of ground and construction conditions (ground loss) using the state of strain damage estimation criterion (Son and Cording, 2005). The results of this study will provide a background for better understandings for controlling and minimizing building damage on nearby structures due to tunnelling-induced ground movements.

Forecasting and Assessment of the Grouting Effect, using a Numerical Model, to Prevent Groundwater Inflow during Excavation of a Vertical Shaft for a Selective Intake Structure (선택취수설비 굴착시 지하수 유입 방지를 위한 그라우팅 효과의 모델링 예측 및 평가)

  • Kim, Gyoo-Bum;Kim, Wan-Soo;Park, Jung-Hoon;Son, Yeong-Cheol;Kim, Jin-Woo
    • The Journal of Engineering Geology
    • /
    • v.23 no.3
    • /
    • pp.227-234
    • /
    • 2013
  • The vertical shaft of a selective intake structure, which is constructed in a large reservoir, is required to be impermeable and to employ a grouting technology to prevent water inflow from the reservoir or surrounding ground. In this study, groundwater inflow is estimated using a numerical model for two cases (i.e., grouting or non-grouting cases at the exterior of a vertical shaft) and compared with data measured during an excavation at the construction site of a selective intake structure in the Soyang reservoir, Korea. Groundwater inflow is estimated to range from 444 to 754 $m^3/d$ in the case of non-grouting and from 58 to 95 $m^3/d$ in the case of grouting. The groundwater inflow measured in a vertical shaft, which ranges from 30 to 100 $m^3/d$, is similar to the simulated amount. It is recommended that before the excavation of a shaft, water inflow is estimated using a numerical model and a grouting test to ensure excavation stability and improve excavation efficiency.

Analysis of Hydro-Mechanical Coupling Behavior Considering Excavation Damaged Zone in HLW Repository (고준위방사성폐기물 처분장에서의 굴착손상대를 고려한 수리-역학적 복합거동 해석)

  • Jeewon Lee;Minju Kim;Sangki Kwon
    • Explosives and Blasting
    • /
    • v.41 no.3
    • /
    • pp.38-61
    • /
    • 2023
  • An Excavation Damaged Zone(EDZ) caused by blasting impact changes rock properties, in situ stress distribution, etc., and its effects are noticeable at around a radioactive waste repository located at deep underground. In particular, the increase in permeability due to the formation of cracks may significantly increase the amount of groundwater inflow and the possibility of radioactive nuclide outflow. In this study, FLAC2D and FLAC3D were used to analyze the mechanical and thermal behaviors for three categories: a)No EDZ, b)Uniform EDZ, and c)Random EDZ. It was found that the tunnel displacement in the Random EDZ case was 423% higher than that in the No EDZ case and was 16% higher than that in the Uniform EDZ case. Tunnel inflow in the Random EDZ was also 17.3% and 10.8% higher than that in the No EDZ and the Uniform EDZ case, respectively. The permeability around the tunnel was increased by up to 10 times in the corner of the tunnel wall and roof due to the stress redistribution after excavation. From the computer simulation, it was found that the permeability around the tunnel wall was partially increased but the overall tunnel inflow was decreased with increase of stress ratio. Mechanical analysis using FLAC 3D showed similar results. Slight difference between 2D and 3D could be explained with the development of plastic zone during the advance of tunnel excavation in 3D.

Analysis of displacement behavior in fractured fault and groundwater flow under tunnel excavation (터널굴착중 굴착면 단층파쇄대와 지하수 용출 구간에서 단계별 변위 거동 특성 분석)

  • Kim, Nag-Young;Park, Gun-Tae;Baek, Seung-Cheol;Lee, Kang-Hyun;Choi, Jin-Woong;Her, Yol
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.19 no.1
    • /
    • pp.71-82
    • /
    • 2017
  • It is necessary to conduct a detailed geotechnical investigation on the tunnel section in order to secure the tunnel design and construction stability. It is necessary for the importance of geotechnical investigation that needed for the analysis of distribution and size of fractured fault zone and distribution of groundwater in tunnel. However, if it is difficult to perform the ground survey in the tunnel design due to ground condition of the tunnel section and the limited conditions such as civil complaint, the tunnel design is performed using the result of the minimum survey. Therefore, if weathered fault zone exists in the face the reinforcement method is determined in the design process to secure the stability of the tunnel. The most important factor in reinforcing the tunnel excavation surface is to secure the stability of the tunnel by performing quick reinforcement. In particular, if groundwater leaching occurs on the excavation surface, more rapid reinforcement is needed. In this study, fractured fault zone exists on the tunnel excavation surface and displacement occurs due to weathered fracture zone. When the amount of groundwater leaching rapidly increased under the condition of displacement, the behavior of tunnel displacement was analyzed based on tunnel collapse. In the study, reinforcement measures were taken because the first stage displacement did not converge continuously. After the first reinforcement, the displacement was not converged due to increased groundwater leaching and the second stage displacement occurred and chimney collapse occurred.

Damage Assessment of Adjacent Structures due to Tunnel Excavation in Urban Areas (II) - Focused on the Variations of Building Stiffness Ratio - (도심지 터널 굴착에 따른 인접구조물의 손상평가에 관한 연구 (II) - 지상 건물의 강성비 변화를 중심으로 -)

  • 김창용;배규진;문현구;박치현;오명렬
    • Journal of the Korean Geotechnical Society
    • /
    • v.15 no.5
    • /
    • pp.81-98
    • /
    • 1999
  • The influence of tunnelling on buildings has become an important issue in urban areas. The problem is an interactive one: not only do tunnelling settlements affect existing structures, but existing structures affect tunnel-induced soil movements. In order to examine the constraint of surface settlement and the degradation of building damage parameters, 3-dimensional elasto-plastic finite element analyses are peformed. Also, in this paper, the results of the parametric studies for the variations of the damage parameters due to the ground movements are presented by utilizing 2-dimensional elasto-plastic finite element models, totally 162 models. The width of a structure, its bending and axial stiffness, its position relative to the tunnel and the depth of tunnel are considered. The interaction is shown by reference to commonly-used building damage parameters, namely angular distortion, deflection ratio, maximum building settlements, maximum differential settlements and horizontal strain. By introducing relative stiffness parameters which combine the bending and axial stiffness of the structure with its width and stiffness of soil, design curves are established. These give a guide as to the likely modification of the greenfield settlement trough caused by a surface structure. They can be used to give initial estimates of likely building damage.

  • PDF

A Study on Track Deformation Characteristics of Turnout System by Adjacent Excavation Work on Urban Transit (인접굴착공사에 따른 도시철도 분기기 궤도의 변형 특성에 관한 연구)

  • Kim, Hae-Sung;Choi, Jung-Youl;Chung, Jee-Seung
    • The Journal of the Convergence on Culture Technology
    • /
    • v.8 no.5
    • /
    • pp.477-482
    • /
    • 2022
  • The structure of the turnout track is very complex, so it is a facility that is more difficult to maintain and requires detailed management than a general track type. The purpose of this study is to analyze the effect on the deformation of the turnout system of the ground section due to the excavation work adjacent to the serviced urban railways. In this study, based on finite element analysis for each stage of adjacent excavation, the track deformation for each major location of turnout system was analyzed in consideration of the layout of the turnout system installed on the ground section, and the safety and stability was confirmed by comparing it with the track irregularity regulation. As a result of the study, it was found that the major construction stage affecting the track deformation of the turnout system on the ground section was the final stage of excavation. In addition, although the vertical displacement which is a vertical irregularity occurred relatively large, it was analyzed that the horizontal deformation was dominant overall, because of the excavation site is located on the side of the turnout system. In addition, it was analyzed that the amount of displacement at each major location of the turnout system is different, and there is a possibility that there may be a twist irregularity due to the deviation of the track deformation for each location according to the distance from the excavation site. Therefore, it was analyzed that it is necessary to classify and manage the importance of the track deformation of the turnout system of actual operating line, including additional displacement due to adjacent excavation, based on the track irregularity that has occurred at each location where the major deformation characteristics occur.

A Case Study on Vibration Control Method at Urban Area Using FINECKER Plus (FINECKER Plus를 이용한 도심지 진동제어 시공사례)

  • Min Hyung-Dong;Jeong Min-Su;Park Yun-Seok;Hwang Ui-Jin;Park Jun-Ho
    • Explosives and Blasting
    • /
    • v.24 no.1
    • /
    • pp.49-56
    • /
    • 2006
  • There are many restrictions with a rock breaking method by using explosives in the urban area due to such safety problems as vibration, noise, and flying rock. Therefore, the use of FINECKER Plus which is mainly used as a rock breaking method (Ministry of Construction and Transportation, 2003) is gradually increasing. Accordingly, construction cases applying FINECKER Plus to the construction sites in the urban area was introduced in case studies. In addition, a comparative test on the same volume of charge applied to 360g of 1 new product 1 set and 180g of the existing FlNECKER Plus 2 sets was conducted. As a result of the test, the two cases were equivalent in breaking efficiency and the level of noise and vibration, and as for the method, the working time decreased by 32%, thus, it was proven to be excellent in terms of construction.

A Study on the Estimation of Load Distribution Factors Considering Excavation Methods and Initial Stress Conditions (굴착방법과 초기지압 조건을 고려한 하중분배율의 산정 연구)

  • Park, Yeon-Jun;Ryu, Il-Hyung
    • Tunnel and Underground Space
    • /
    • v.21 no.3
    • /
    • pp.192-204
    • /
    • 2011
  • In this study, 3-D analyses were conducted while taking every construction stage into account. Then 2-D analyses were conducted which yield the same results with the 3-D results. The crown settlement normalized by the ultimate value was compared during the process to overcome the discrepancy caused by different dimensions. When a bench or a core is left uncut to give extra support to the face and eventually the whole excavation boundary, this extra supporting effect also has to be included in the analysis. In this study, this effect is also implemented in terms of the load distribution factor. When the length of the bench is very short compared to the diameter of the tunnel in such cases as in short bench cut or in mini-bench cut, the supporting effect of the face does not disappear even after the bench is completely excavated and supported since the face is still too close to the point of interest. The 4th load distribution factor was defined to stand for the advance of the face after the completion of the excavation cycle. The 4th load distribution factor turned out to be very useful in determining the load distribution factors when a tunnel is excavated by bench cut with various bench lengths under different initial conditions.

A Study on the Drilling Methods to reduce Overbreak in Tunnel Blasting (터널발파 작업시 여굴 저감을 위한 천공방법 연구)

  • 김양균;김형철;유정훈
    • Explosives and Blasting
    • /
    • v.21 no.2
    • /
    • pp.1-13
    • /
    • 2003
  • Overbreak or underbreak is one of the most important factors in evaluating the results of a tunnel blasting. Overbreak, which depends on the quality of rock, the type and quantity of explosives, and drilling conditions, has been a target of challenge to many blasting engineers because it directly affects construction cost. Drilling is generally known as one of the primary factors to generate overbreak. This study presents a real working model to reduce overbreak based on the analysis of drilling accuracy and overbreak generated from various working methods related to drilling. As the first step of the study, 45 experiments have been performed. The factors investigated are: marking contour line, the position of perimeter holes, the change of look-out with drilling rig position, and the proper space between perimeter holes. It is concluded that workers and engineers' will and efforts are the most important factors to reduce overbreak and that improving drilling method and pattern could reduce overbreak to a considerable amount.

Analysis of Tensile Force of Nail and Displacement of Soil Nailed Wall at Stepwise Excavation (단계별 굴착시 쏘일네일링 벽체의 변위와 네일의 인장력 분석)

  • 전성곤
    • Journal of the Korean Geotechnical Society
    • /
    • v.15 no.6
    • /
    • pp.71-86
    • /
    • 1999
  • The displacements of soil nailed wall and the nail tensile force for 11 soil nailing sites were investigated by using measurements obtained from inclinometer and strain gauge. The maximum horizontal displacement which occurred between 5% and 15% of the final excavation depth was found to be below 0.3% and 0.2% of excavation depth for well and poorly constructed sites. It was also found that the maximum horizontal displacements for 0.4%, 0.3% and 0.2% of excavation depth occurred when the ratios of nail length to final excavation depth were 0.5, 0.5~0.6 and 0.6~0.7. But the maximum horizontal displacement increased by 0.3% of excavation depth when the ratio was above 0.7. This was probably due to the shallow excavation depth and the deep soil stratum. The non-dimensional maximum tensile force of nail, K, from ground surface to $(0.6H_f)$ of the final excavation depth was less than 0.8 and decreased linearly between $(0.6H_f)$ and the final excavation depth. Also, the maximum tensile force was found to reach up to 60% of the ultimate tensile force at final excavation.

  • PDF