Development and Application of Off-Site Construction Project Management System - Focusing on PC Construction -

Off-Site Construction 프로젝트 관리시스템 개발 및 적용 - PC공사를 중심으로 -

  • Jang, YeEun (Department of Architectural and Urban Systems Engineering, Ewha Womans University) ;
  • Lee, Jae-Man (Building Engineering Team, Research & Development Institute, Lotte E&C) ;
  • Son, JeongWook (Department of Architectural and Urban Systems Engineering, Ewha Womans University)
  • 장예은 (이화여자대학교 건축도시시스템공학과) ;
  • 이재만 (롯데건설기술연구소) ;
  • 손정욱 (이화여자대학교 건축도시시스템공학과)
  • Received : 2022.05.30
  • Accepted : 2022.07.20
  • Published : 2022.08.30

Abstract

This study presents the development process and application effect of project management system to efficiently manage OSC projects which are recently getting more attention. We conducted literature review, case analysis, and expert interviews to identify the characteristics of the OSC project management and to derive the requirements and necessary functions that the management system should have. Based on the results of the preliminary study, the OSC project management system was implemented and the effect was analyzed by applying it to the field. It was found that the management system improved the efficiency and accuracy of management work and reduced unnecessary time and effort at each stage of factory production, transportation, and on-site installation. This study is meaningful in that it identified the characteristics of OSC project management, derived the requirements and necessary functions of OSC project management system, and presented practical applicability by developing management system and analyzing the application effect.

Keywords

Acknowledgement

이 연구는 2022년도 국토교통부/국토교통과학기술진흥원의 지원으로 수행되었음 (과제번호 22ORPS-B158109-03)

References

  1. Altaf, M. S., Bouferguene, A., Liu, H., Al-Hussein, M., & Yu, H. (2018). "Integrated production planning and control system for a panelized home prefabrication facility using simulation and RFID." Automation in Construction, 85, 369-383. https://doi.org/10.1016/j.autcon.2017.09.009
  2. Alvanchi, A., Azimi, R., Lee, S., AbouRizk, S. M., & Zubick, P. (2012). "Off-site construction planning using discrete event simulation." Journal of Architectural Engineering, 18(2), 114-122. https://doi.org/10.1061/(ASCE)AE.1943-5568.0000055
  3. Arashpour, M., Bai, Y., Aranda-mena, G., Bab-Hadiashar, A., Hosseini, R., & Kalutara, P. (2017). "Optimizing decisions in advanced manufacturing of prefabricated products: Theorizing supply chain configurations in off-site construction." Automation in Construction, 84, 146-153. https://doi.org/10.1016/j.autcon.2017.08.032
  4. Bernstein, H. M., Gudgel, J. E., & Laquidara-Carr, D. (2011). "Prefabrication and modularization: ncreasing productivity in the construction industry." McGraw Hill Construction.
  5. Bertram, N., Fuchs, S., Mischke, J., Palter, R., Strube, G., & Woetzel, J. (2019). "Modular construction from projects to products." McKinsey & Company.
  6. Chen, K., Xu, G., Xue, F., Zhong, R. Y., Liu, D., & Lu, W. (2018). "A physical internet-enabled building information modelling system for prefabricated construction." International Journal of Computer Integrated Manufacturing, 31(4-5), 349-361. https://doi.org/10.1080/0951192X.2017.1379095
  7. Chen, W., Zhao, Y., Yu, Y., Chen, K., & Arashpour, M. (2020). "Collaborative scheduling of on-site and off-site operations in prefabrication." Sustainability, 12(21).
  8. Hamilton, I., Rapf, O., Kockat, D. J., Zuhaib, D. S., Abergel, T., Oppermann, M., Otto, M., Loran, S., Fagotto, I., & Steurer, N. (2020). "2020 global status report for buildings and construction." United Nations Environmental Programme.
  9. Hyun, H., Kim, H. G., & Kim, J. S. (2021). "A Business Model for Activating the Small-Scale Public Housing Supply in Urban Area using Off-Site Construction Method - Focusing on Integrated Implementation of Dispersed Small-scale Public Housing Construction Projects -." Journal of the Architectural Institute of Korea, 37(3), 183-193. https://doi.org/10.5659/JAIK.2021.37.3.183
  10. Iqbal, M., Ahmad, N., Waqas, M., & Abrar, M. (2021). "COVID-19 pandemic and construction industry: Impacts, emerging construction safety practices, and proposed crisis management." Brazilian Journal of Operations & Production Management, 18(2), 1-17.
  11. Jeong, G., Lee, H., Park, M., Hyun, H., & Kim, H. (2019). "Cause analysis and reduction of safety accident in modular construction - focusing on manufacturing and construction process." Journal of the Architectural Institute of Korea, 35(8), 157-168.
  12. Jeong, M., Lee, S., Chang, Y., & Kwon, S. (2021). "Smart quality inspection technology for on-site PC members based on off-site construction(OSC)." Proc., Conference of the Architectural Institute of Korea, 745-746.
  13. Kim, H., Hwang, Y., & Kim, K. (2014). "Study on the Application of Multi-skilled labors to Factory Production Process for Securing Economic Feasibility of Modular Unit." Korean Journal of Construction Engineering and Management, 15(1), 11-19. https://doi.org/10.6106/KJCEM.2014.15.1.011
  14. Kim, K.-H., Lim, J.-J., Kim, J.-W., Kim, M.-J., Sohn, J.-R., & Lee, B.-S. (2021). "On-site productivity reduction factors for off-site construction based PC public housing." Proc., Conference of the Architectural Institute of Korea, 712-713.
  15. Kim, M., Park, M., Lee, H.-s., Lee, J., & Lee, K.-P. (2015). "Development of Manufacturing Planning for Multi Modular Construction Project based on Genetic-Algorithm." Korean Journal of Construction Engineering and Management, 16(5), 54-64. https://doi.org/10.6106/KJCEM.2015.16.5.054
  16. Kim, T., Kim, Y.-W., & Cho, H. (2020). "Dynamic production scheduling model under due date uncertainty in precast concrete construction." Journal of Cleaner Production, 257, 120527. https://doi.org/10.1016/j.jclepro.2020.120527
  17. Lee, G., Kim, M., Lee, C., Koo, C., & Kim, T. (2021). "Towards a transportation support system for off-site construction : identifying key functions and diagramming functional blocks." Korean Journal of Construction Engineering and Management, 22(2), 21-30. https://doi.org/10.6106/KJCEM.2021.22.2.021
  18. Lee, H.-R., & Yi, J.-S. (2021). "An analysis of management competency for transportation system of off-site construction project using importance performance analysis." Proc., Conference of the Architectural Institute of Korea, 867-870.
  19. Lee, J.-M., Seok, W.-G., & Park, S.-J. (2020). "Integrated management platform for OSC projects." Construction Engineering and Management, 29-32.
  20. Lee, Y., & Cha, M. (2017). "Application of BIM technology in modular construction." Korea Institute of Building Construction Magazine, 10-16.
  21. Li, C. Z., Xue, F., Li, X., Hong, J., & Shen, G. Q. (2018). "An internet of things-enabled BIM platform for on-site assembly services in prefabricated construction." Automation in Construction, 89, 146-161. https://doi.org/10.1016/j.autcon.2018.01.001
  22. Lim, S.-H., Seol, W.-J., & Chung, J.-S. (2020). "A study on constructability verification for shortening construction period of modular apartments and implement plan." Journal of the Korean Housing Association, 31(6), 1-11.
  23. Liu, J., & Lu, M. (2019). "Robust Dual-Level Optimization Framework for Resource-Constrained Multiproject Scheduling for a Prefab Facility in Construction." Journal of Computing in Civil Engineering, 33(2).
  24. Ma, Z., Yang, Z., Liu, S., & Wu, S. (2018). "Optimized rescheduling of multiple production lines for flowshop production of reinforced precast concrete components." Automation in Construction, 95, 86-97. https://doi.org/10.1016/j.autcon.2018.08.002
  25. Nam, S., & Kim, Y. (2016). "Development of Project Delivery System in Public Sector for Modular Building." Korean Journal of Construction Engineering and Management, 17(4), 49-56. https://doi.org/10.6106/KJCEM.2016.17.4.049
  26. Niu, S., Yang, Y., & Pan, W. (2019). "Logistics planning and visualization of modular integrated construction projects based on BIM-GIS integration and vehicle routing algorithm." Modular and Offsite Construction (MOC) Summit Proceedings, 579-586.
  27. Ribeirinho, M. J., Mischke, J., Strube, G., Sjodin, E., Blanco, J. L., Palter, R., Biorck, J., Rockhill, D., & Andersson., T. (2020). "The next normal in construction." McKinsey and Company.
  28. Salari, S. A.-S., Mahmoudi, H., Aghsami, A., Jolai, F., Jolai, S., & Yazdani, M. (2022). "Off-site construction three-echelon supply chain management with stochastic constraints: a modelling approach." Buildings, 12(2), 119. https://doi.org/10.3390/buildings12020119
  29. Wang, Z., & Hu, H. (2017). "Improved Precast Production-Scheduling Model Considering the Whole Supply Chain." Journal of Computing in Civil Engineering, 31(4), 04017013. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000667
  30. Wang, Z., Hu, H., & Gong, J. (2018). "Framework for modeling operational uncertainty to optimize offsite production scheduling of precast components." Automation in Construction, 86, 69-80. https://doi.org/10.1016/j.autcon.2017.10.026
  31. Yazdani, M., Kabirifar, K., Fathollahi-Fard, A. M., & Mojtahedi, M. (2021). "Production scheduling of off-site prefabricated construction components considering sequence dependent due dates." Environmental Science and Pollution Research, 1-17.
  32. Zhang, W., Kang, K., & Zhong, R. Y. (2021). "A cost evaluation model for IoT-enabled prefabricated construction supply chain management." Industrial Management & Data Systems.