How to Improve the Competency of Agency CM Companies to Conduct the CM at Risk Projects?

용역형 CM사가 책임형 CM 프로젝트를 수행하기 위해 필요한 역량

  • Jeon, Myeongsik (Major in Architectural Engineering, The Graduate School of Engineering, Yonsei University) ;
  • Kang, Youngcheol (Department of Architecture and Architectural Engineering, Yonsei University)
  • 전명식 (연세대학교 공학대학원 건축공학전공) ;
  • 강영철 (연세대학교 건축공학과)
  • Received : 2021.08.19
  • Accepted : 2021.09.23
  • Published : 2021.11.30

Abstract

As the CM at Risk market grows recently, designers and CM companies that have been performing agency CM services have been showing their interests to participate in the CM at Risk projects. With the assumption that agency CM companies with a lot of experiences and know-how in the field of construction project management have created the circumstances to enter the CM at Risk market, this study investigates the competencies necessary for the agency CM companies to carry out the CM at Risk projects. The compentencies to run the CM at Risk projects were identified based on the literature review. A survey was conducted to identify the competencies that need to be supplemented first. The survey results revealed that competency related to partner companies, finance and guarantee, risk and claim, and project cost were identified to have a higher level of complementation compared to other competencies. In addition, considering that the level of competency that need to be secured is high, as the level of holding of all competency is on average 76% of the required level, in the beginning, small-scale CM at Risk projects with relatively low risk are mainly carry out, strengthening competency and then increasing the scale is considered more appropriate strategy.

최근 CMR 시장이 성장함에 따라 그동안 ACM 서비스를 제공해 왔던 기존의 설계사들과 CM사들도 CMR 프로젝트에 참여할 의지를 보이고 있으며 시공 부문을 도입하려는 움직임을 보이고 있다. 이에 본 연구에서는 건설 사업 관리 분야에서 많은 경험과 노하우를 가지고 있는 ACM사들이 CMR 시장에 진입할 여건이 만들어졌다는 가정 하에, 문헌 조사를 통해 CMR 프로젝트 수행을 위한 역량들을 도출하였고 이를 바탕으로 한 설문 조사를 통해, ACM사가 CMR 프로젝트를 수행하기 위해서 보완해야 할 역량을 도출하였다. 그 결과, 협력 업체, 금융 및 보증, 리스크 및 클레임, 사업비와 관련된 역량의 보완 수준이 타 역량에 비해 높은 것으로 분석되었다. 또한 전체 역량의 보유 수준이 요구 수준 대비 평균 76% 정도로서 확보해야 할 역량의 보완 수준이 높음을 고려하였을 때, 초기에는 리스크가 비교적 작은 소규모 CMR 프로젝트 위주로 수행하면서 역량을 강화한 후 수행 규모를 키워 나가는 것이 유리할 것으로 판단된다.

Keywords

Acknowledgement

이 성과는 2021년도 정부(과학기술정보통신부)의 재원으로 한국연구재단의 지원을 받아 수행된 연구임(NRF-2021R1F1A1050519).

References

  1. Ahn, C.W., Ahn, Y.H., and Lee, S.H. (2016). "Role of Design Company for CM at Risk Delivery Method." Proceeding of annual conference of the architectural institute of Korea, AIK, 36(2), pp. 1,056-1,057.
  2. Ahn, E.J., Yoo, B.G., Lee, Y.S., and Kim, J.J. (2008). "Measuring of the Performance of a Construction Management Project from Viewpoints of Project Participants-Focusing on Owner, Construction Manager, Designer and Constructor-" Korean Journal of Construction Engineering and Management, KICEM, 9(3), pp. 194-205.
  3. Ahn, K.H. (2009). "A study on countermeasures for the change CM at Risk." Master's thesis, Department of Construction Management, Master of Graduate School of Engineering, Hanyang University.
  4. Ahn, Y.H. (2013). "CM at Risk (CM at Risk) delivery method in US public architecture." Korean Journal of Construction Engineering and Management, KICEM, 14(4), pp. 69-72.
  5. Ahn, Y.H., and Lee, S.H. (2016). "Application of Preconstruction Service in CM at Risk delivery method." Korean Journal of Construction Engineering and Management, KICEM, 17(6), pp. 27-30.
  6. Ahn, Y.H. (2017). "Contractor's Roles of Construction Management Project Delivery System in the United States." Journal of the Korea Institute of Building Construction, KIC, 17(3), pp. 20-27.
  7. Bae, Y.H. (2019). 2019 Construction Management(CM) Capability Assessment and Disclosure Data Collection, CMAK, p. 24.
  8. Byun, I.W., and Kim, Y.S. (2012). "An Analysis of Core Competence of Pre-construction Service of the Making Inroads into Oversea Construction Market (for the Entry in the International Construction Business)." Korean Journal of Construction Engineering and Management, KICEM, 13(2), pp. 80-90. https://doi.org/10.6106/KJCEM.2012.13.2.080
  9. Chang, C.K., Lee, B.N., Choi, S.I., and Lee, D.K. (2006). "Understanding CM at Risk and Diagnosing the Possibility of Introduction." CERIK.
  10. Chun, B.G. (2008). "Strategies for responding to CM service providers following the introduction of CM at Risk." Korean Journal of Construction Engineering and Management, KICEM, 9(3), pp. 13-16.
  11. Gee, H.K. (2007). "Application of Construction Management (CM) Delivery System by Characteristics of Facility." Master's thesis, Department of Construction Management, The Graduate School of Construction Engineering, Chung-Ang University.
  12. Han, J.H., Kim, K.T., and Ahn, Y.H. (2018). "Major Risk Factors to Implement CM at Risk Pilot Project on the Public Sector." Korean Journal of Construction Engineering and Management, KICEM, 19(3), pp. 61-69. https://doi.org/10.6106/KJCEM.2018.19.3.061
  13. Han, J.H. (2019). "Risk factors to Implement CM at risk Projects." Master's thesis, Department of Architectural Engineering, The Graduate School, Hanyang University.
  14. Han, T.H. (2017). "Construction Industry Innovation and Pre-Con Service of GS E&C." Journal of the Korea Institute of Building Construction, KIC, 17(3), pp. 40-47.
  15. Kim, H.S. (2016). "Is the construction industry ready for 'CM at Risk'?" eDNEWS, (Aug. 16, 2016).
  16. Kim, J.G., Jung, J.H., and Lee, H.G. (2009). "Response measures of construction companies following the introduction of the CM at Risk method." Journal of the Regional Association of Architectural Institute of Korea, AIKRA, 11(1), pp. 159-166.
  17. Kim, J.H. (2002). "Current status of CM in foreign countries." Monthly Building Culture, JeongSeongD&M, pp. 146-151.
  18. Kim, S.C., Park, C.J., Lee, S.Y., and Son, J.H. (2007). "Establishing the Education Strategy in strengthening Construction Management's ability in Large-scaled Construction Company." Korean Journal of Construction Engineering and Management, KICEM, 8(5), pp. 109-118.
  19. Kim, S.S., and Kim, J.Y. (2017). "Activities of CM at Risk Based on the performing experience of Posco A&C." Journal of the Korea Institute of Building Construction, KIC, 17(3), pp. 48-51.
  20. Kim, W.Y. (2017). "The domestic introduction of CM at Risk." Review of Architecture and Building Science, AIK, 61(5), pp. 34-38.
  21. Koh, B.W. (2017). "The role of architects in CM at Risk (CM at Risk) projects." Journal of the Korea Institute of Building Construction, KIC, 17(3), pp. 12-19.
  22. Koo, S.K. (2017). "Risk Factor Assessment for Guaranteed Maximum Price Contract in CM at Risk." Master's thesis, Graduate School, University of Seoul.
  23. Lee, C.J., and Ahn, Y.H. (2016). "A Benchmarking study on Pre-construction Estimating Services of Overseas Construction Companies for the CM at Risk Firm's competitiveness." Proceeding of annual conference of the architectural institute of Korea, AIK, 36(2), pp. 1,043-1,044.
  24. Lee, C.J. (2017). "Benchmarking of Foreign General Cotractor's Pre-construction Services for a CM at risk Project to Improve Contractor's Competitiveness." Master's thesis, Department of Architectural Engineering, The Graduate School, Hanyang University.
  25. Lee, C.J., Lee, S.H., and Ahn, Y.H. (2017). "Benchmarking of US General Contractor's Pre-construction Services for a CM at Risk Project to Improve Contractor's Competitiveness." Journal of the Korea Institute for Structural Maintenance and Inspection, KSMI, 21(3), pp. 9-18.
  26. Lee, H.K. (2004). "Construction Management Services in Pre-construction Phase based on Client Needs Analysis." Master's thesis, Department of Architecture, Graduate School, Ajou University Graduate School.
  27. Lee, J.S., and Lee, S.H. (2017). "Strategies for Successful Establishment of CM at Risk." Journal of the Korea Institute of Building Construction, KIC, 17(3), pp. 32-39.
  28. Lee, K.D. (2015). "A Study on the Analysis of main Barriers for the Activation of CM at Risk in the Domestic Construction Industry." Master's thesis, Department of Architectural Engineering, Graduate School, Kyungpook National University.
  29. MOLIT. (2016). "Awareness gap widens depending on the experience of self-driving cars." Ministry Of Land Infrastructure and Transport, (Dec. 26, 2016)
  30. Park, B.S. (2019). "A Study on the Bid Evaluation Method for Selecting CM at Risk Contractors in Korea." Master's thesis, Graduate School, Chungbuk National University.
  31. Park, K.M., and Kim, C.D. (2016). "Improvement through Analysis of Current Open Book Policy for the Korean CM at Risk." Korean Journal of Construction Engineering and Management, KICEM, 17(2), pp. 3-11. https://doi.org/10.6106/KJCEM.2016.17.2.003
  32. Park, S.H. (2014). "Cases and Challenges of Construction Management at Risk (CMAR)." Korean Journal of Construction Engineering and Management, KICEM, p. 7.
  33. Park, S.H. (2016). "Proposal for the CM at Risk pilot project." eDNEWS, (Oct. 6, 2016).
  34. Park, Y.W. (2011). "A Study on the Improved Evaluation Methodology of Selecting Construction Manager." Doctoral dissertation, Department of Architectural Engineering, The Graduate School, Tongmyong University.
  35. Ryu, H.G., Lee, S.W., and Choi, J.H. (2020). "Evaluation of Capability for Practicing CM at Risk in Korea." Korean Journal of Construction Engineering and Management, KICEM, 21(2), pp. 79-87.
  36. Shin, S.H. (2004). "A Plan for Application of CM at Risk to the Public Construction Sector in Korea." Master's thesis, Department of Architectural Engineering, Graduate School, University of Seoul.
  37. Son, K.N. (2018). "Importance Analysis of Obstacle Factors on the CM at Risk Projects using AHP Method." Master's thesis, Department of Construction Management, Master of Graduate School, Hanyang University.
  38. Yoo, S.K., Choi, S.I., and Son, C.B. (2009). "An Analysis of Capability of CM at Risk in Major Construction Company." Korean Journal of Construction Engineering and Management, KICEM, 10(5), pp .85-94.