Fig. 1. Research methods and scope
Fig. 2. The Cost and Time of construction and its effect on the facility planning phase
Table 1. Research Trends in the inside of the country
Table 2. Research Trends in the outside of the country
Table 3. Facility construction plan scheme
Table 4. Analysis of construction planning and its effect on construction schedule
Table 5. Analysis of work flow planning and its effect on construction cost
Table 6. Comparison of Construction time with Cost in Relation to the planning phase
참고문헌
- Arena, P., Caponetto, R., Fortuna, L., and Xibilia, M. G. (1992). "Genetic algorithms to select optimal neural network topology." In Circuits and Systems, Proceedings of the 35th Midwest Symposium on, pp. 1381-1383.
- Ashworth A. Cost studies of buildings (1999). Harlow:Addison Wesley Longman Ltd, 3rd ed. UK, p. 444.
- Ballard, G. (2000). "Lean project delivery system." Lean Construction Institute White, Lean Construction Institute, Ketchum, Id., p. 8.
- Ballard, G., Harper, N., and Zabelle, T.R. (2003). "Learning to see work flow: an application of lean concepts to precast concrete fabrication." Engineering Construction and Architectural Management, 10(1), pp. 6-14. https://doi.org/10.1108/09699980310466505
- Ballard, G., and Howell, G. (1998). "Shielding Production: Essential Step in Production Control." Journal of Construction Engineering and Management, 124(1), pp. 11-17. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:1(11)
- Ballard, G., and Howell, G. (2003). "Lean Project Management." Building Research & Information, 31(2), pp. 119-133. https://doi.org/10.1080/09613210301997
- Ballard, G., and Zabelle, T.R. (2000). "Lean design: Process, tools, and techniques." Lean Construction Institute White Paper No. 10, Lean Construction Institute, Ketchum, Id.
- Cha, H.S., and Kim, T.K. (2008). "Developing measurement system for key performance indicators on building construction projects." Korean Journal of Construction Engineering and Management, KICEM, 9(4), pp. 120-130.
- Cho, Y.S., and Cha, H.S. (2010). "A Study of project characteristics and project performance level of difficulty." Korean Journal of Construction Engineering and Management, KICEM, 11(6), pp. 78-88. https://doi.org/10.6106/KJCEM.2010.11.6.78
- CII. (2011). Enhanced work packaging: Design through workface execution (Doctoral dissertation).
- COAA (Construction Owners Association of Alberta). (2007). Workface planning model and implementation guide.
- Elazouni, A.M., Ali, A.E., and Abdel-Razek, R.H. (2005). "Estimating the acceptability of new formwork systems using neural networks." Journal of construction engineering and management, 131(1), pp. 33-41. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:1(33)
- ELECTRI International (2009). Construction Project Management: A Practical Guide for Building and Electrical Contractors, J. Ross Publishing, Fort Lauderdale, FL.
- Guo, S.J. (2002). "Identification and Resolution of Work Space Conflicts in Building Construction." Journal of Construction Engineering and Management, 128(4), pp. 287-295. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(287)
- Hanna, A.S., and Skiffington, M.A. (2010). "Effect of Preconstruction Planning Effort on Sheet Metal Project Performance." Journal of Construction Engineering and Management, 136(2), pp. 235-241. https://doi.org/10.1061/(ASCE)0733-9364(2010)136:2(235)
- Horman, M.J., Orosz, M.P., and Riley, R.D. (2006). "Sequence Planning for Electrical Construction." Journal of Construction Engineering and Management, 132(4), pp. 363-372. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:4(363)
- Kim, D.W., An, S.H., Cho, H., Jeong, J.W., Lee, B.H., Doh, N.L., and Kang, K.I. (2009). "Development of conceptual model of construction factory for automated construction." Building and Environment, 44(8), pp. 1634-1642. https://doi.org/10.1016/j.buildenv.2008.10.009
- Koo, B. (2008). "Analyzing Site Reliability for Residential, Civil and Plant Projects using Lean Construction Principles." Journal of The Korean Society of Civil Engineers, 28(5D), pp. 655-664.
- Ko, Y.J., and Cha, H.S. (2011). "A Development of Project Performance Predicting System (PPS) considering Construction Project Characteristics." Korean Journal of Construction Engineering and Management, KICEM, 12(1), pp. 62-72. https://doi.org/10.6106/KJCEM.2011.12.1.62
- Lee, H. (2006). "An Improvement Scheme of Process Quality in The Korean Building Projects." Journal of the Korean Association for Spatial Structures, 6(3), pp. 51-57.
- Lee, H.S., Lee, B.N., Kim, W.Y., Yoo, J.H., and Song, S.H. (2005). "A Study on the Evaluation of PMIS and Development Strategy for Construction Companies." Korea Institute of Construction and Industry, p. 121.
- Menches, C.L., and Hanna, A.S. (2006). "Conceptual Planning Process for Electrical Construction." Journal of Construction Engineering and Management, 132(12), pp. 1306-1313. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:12(1306)
- Nasr, Z.J.B. (2009). "Electrical Project Management Model." The University of Texas at Austin, Austin.
- Park, J.I. (2005). Technical Status of Building Equipment Korean Society for Mechanical Engineering lecturers and other publications, pp. 5-19.
- Reder AD. Cost model for reinforced concrete beam and slab structures in building [dissertation]. Fort Collins: Colorado State University; 2005. pp. 150.
- Ryu, H.G., and Son, B.S. (2010). "Problems and Suggestions for Improvement Derived from an Analysis of the Work of the Urban & Residence Environment Improvement Project-Focused on the Establishment of Preparation Committee and Association Committee." Journal of the Korea Institute of Building Construction, 10(3), pp. 39-47. https://doi.org/10.5345/JKIC.2010.10.3.039
- Singh, S. (1990). "Cost model for reinforced concrete beam and slab structures in buildings." Journal of Construction Engineering and Management, 116(1), pp. 54-67. https://doi.org/10.1061/(ASCE)0733-9364(1990)116:1(54)
- Wilson AJ. Experiments in probabilistic cost modelling (1983). In: Brandon PS, editor. Building Cost Techniques; New Direction. London: E&FN Spon, pp. 169-80.
- Yu, I.H., Jung, Y.S., Chin, S.Y., and Kim, K.R. (2006). "Analysis of quantified characteristics of the performance indicators for construction companies." Korean Journal of Construction Engineering and Management, KICEM, 7(4), pp. 154-163.