An Analysis of Construction Execution Tasks for Successful Residential Mechanical Projects

프로젝트 성공을 위한 효과적인 시공업무 및 영향 분석 - 아파트 설비공사를 중심으로 -

  • Kang, Sang-Hun (Department of Architectural Engineering, Pusan National University) ;
  • Kim, Dae Young (Department of Architectural Engineering, Pusan National University)
  • Received : 2018.10.26
  • Accepted : 2018.11.26
  • Published : 2019.03.31

Abstract

The main purpose of this study is to identify the tasks performed at the construction stage of apartment houses and analyze the major construction tasks that may affect the performance indicators and analyze the impact on project performance. Based on expert opinions through preliminary research, pilot data, construction database, and other research trends, domestic and foreign research trends are divided into five major tasks, and each is divided into process management (P'1 ~ P'6), construction management (C'1 ~ C'5), environmental management (E'1 ~ E'4), quality control (Q'1 ~ Q'5), safety management (S'1 ~ S'5). Subsequently, each major task was subdivided into 24 detailed tasks. An independent t-test was conducted to analyze the impact on cost. We compared the importance of achieving the project goal and identified the construction work of concrete important construction which affects not only the cost but also the schedule performance index for the degree of significance of less than 0.05.

본 연구의 주목적은 공동주택 설비 시공 단계에서 수행되는 업무들을 파악하고 성과지표에 영향을 줄 수 있는 주요 시공업무를 분석하여 프로젝트의 성과에 미치는 영향을 분석하는데 있다. 국내 외 연구동향을 비롯한 선행연구와 예비 데이터 수집(pilot data), 시공업무 데이터베이스 구축을 통한 전문가 의견을 바탕으로 시공업무를 크게 5개의 주요업무로 구분하고 각각을 공정관리(P'1~P'6), 시공관리(C'1~C'5), 환경관리(E'1~E'4), 품질관리(Q'1~Q'5), 안전관리(S'1~S'5)으로 명명하였다. 그 후, 각각의 주요 업무를 세분화 시켜 총 24개의 세부 시공업무로 분류하였다. 원가 및 공기에 대한 영향을 분석하기 위해 independent t-test를 실시하였다. 프로젝트 목표 달성에 따른 중요도를 비교하여 유의도 0.05 이하에 대해 원가뿐만 아니라 공기의 성과지표에 공통적으로 영향을 미치는 구체적인 중요 공사의 시공업무를 파악하였다.

Keywords

GGRHC4_2019_v20n2_60_f0001.png 이미지

Fig. 1. Domestic facility construction contract amount and number

GGRHC4_2019_v20n2_60_f0002.png 이미지

Fig. 2. Data Flow Chart

GGRHC4_2019_v20n2_60_f0003.png 이미지

Fig. 3. Impact of schedule and cost during construction phase of facility

Table 1. Research Trends outside the country

GGRHC4_2019_v20n2_60_t0001.png 이미지

Table 2. Survey content

GGRHC4_2019_v20n2_60_t0002.png 이미지

Table 3. Tasks for Construction work

GGRHC4_2019_v20n2_60_t0003.png 이미지

Table 4. Analysis of the Effect of Schedule Management in Building Construction

GGRHC4_2019_v20n2_60_t0004.png 이미지

Table 5. Analysis of the Effects of Construction tasks on Cost

GGRHC4_2019_v20n2_60_t0005.png 이미지

Table 6. Comparison of Construction Schedule with cost in relation to its effect on the planning phase

GGRHC4_2019_v20n2_60_t0006.png 이미지

References

  1. Arena, P., Caponetto, R., Fortuna, L., and Xibilia, M. G. (1992). "Genetic algorithms to select optimal neural network topology." In Circuits and Systems, Proceedings of the 35th Midwest Symposium on, pp. 1381-1383.
  2. Ballard, G., Harper, N., and Zabelle, T.R. (2003). "Learning to see work flow: an application of lean concepts to precast concrete fabrication." Engineering Construction and Architectural Management, 10(1), pp. 6-14. https://doi.org/10.1108/09699980310466505
  3. Ballard, G., and Howell, G. (1998). "Shielding Production: Essential Step in Production Control." Journal of Construction Engineering and Management, 124(1), pp. 11-17. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:1(11)
  4. Ballard, G., and Howell, G. (2003). "Lean Project Management." Building Research & Information, 31(2), pp. 119-133. https://doi.org/10.1080/09613210301997
  5. Cho, Y.S., and Cha, H.S. (2010). "A Study of project characteristics and project performance level of difficulty." Korean Journal of Construction Engineering and Management, KICEM, 11(6), pp. 78-88. https://doi.org/10.6106/KJCEM.2010.11.6.78
  6. Rojas, E.M. (Ed.). (2009). "Construction project management: A practical guide for building and electrical contractors." J. Ross Publishing.
  7. Eriksson, P.E. (2010). "Improving Construction Supply Chain Collaboration and Performance: A Lean Construction Pilot Project." Supply Chain Management: An International Journal, 15(5), pp. 394-403. https://doi.org/10.1108/13598541011068323
  8. Hanna, A.S., and Skiffington, M.A. (2010). "Effect of Preconstruction Planning Effort on Sheet Metal Project Performance." Journal of Construction Engineering and Management, 136(2), pp. 235-241. https://doi.org/10.1061/(ASCE)0733-9364(2010)136:2(235)
  9. Kim, J.Y., and Kim, E.S. (2010). "The State of Schedule Management and the Recognition of Duration Shortening." Journal of the Korea Institute of Building Construction, 10(5), pp. 87-94. https://doi.org/10.5345/JKIC.2010.10.5.087
  10. Koskela, L., Howell, G., and Tommelein, I. (2002). "The Foundations of Lean Construction." Design and Construction: Building in Value, R. Best, and G. de Valence, eds., Butterworth-Heinemann, Elsevier, Oxford, UK.
  11. Jorgensen, B., and Emmitt, S. (2008). "Lost in transition: the transfer of lean manufacturing to construction." Engineering, Construction and Architectural Management, 15(4), pp. 383-398. https://doi.org/10.1108/09699980810886874
  12. Jung, S.O., Kim, Y.S., Chin, S.Y., and Yoon, S.W. (2005). "A Proposal the Assessment Criteria and Conceptual Methodology of Performance Measurement based on Efficiency through Construction Project Life Cycle." Journal of the Architectural Institute of Korea, 21(7), pp. 139-48.
  13. Mao, X., and Zhang, X. (2008). "Construction process reengineering by integrating lean principles and computer simulation techniques." Journal of Construction Engineering and Management, 134(5), pp. 371-381. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:5(371)
  14. Menches, C.L., and Hanna, A.S. (2006). "Conceptual planning process for electrical construction." Journal of construction engineering and management, 132(12), pp. 1306-1313. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:12(1306)
  15. Menches, C.L. (2006). "Effect of pre-construction planning on project performance." University of wisconsin-Madison, Madison.
  16. Nasr, Z.J.B. (2009). "Electrical Project Management Model." The University of Texas at Austin, Austin.
  17. Seo, J.W., and Kang, K.I. (2009). "The analysis of defects types and patterns in high-rise residential buildings." Journal of the Korea Institute of Building Construction, 9(2), pp. 93-101. https://doi.org/10.5345/JKIC.2009.9.2.093
  18. Sin. Y.I., and Kim, H.S. (2004). "Performance Measurement Techniques and Best Practice in Construction Projects." Journal of the Architectural Institute of Korea, 20(3), pp. 105-112.
  19. Soewin, E., and Chinda, T. (2018). "Factors affecting construction performance: exploratory factor analysis." In IOP Conference Series: Earth and Environmental Science, 140(1), 012102. https://doi.org/10.1088/1755-1315/140/1/012102
  20. Zavadskas, E.K., Vilutienė, T., Turskis, Z., and Saparauskas, J. (2014). "Multi-criteria analysis of Projectsʼ performance in construction." Archives of Civil and Mechanical Engineering, 14(1), pp. 114-121. https://doi.org/10.1016/j.acme.2013.07.006