Cutting of Concrete Block Using Detonating Cords

도폭선을 이용한 콘크리트 블록 절단 연구

  • Received : 2019.12.16
  • Accepted : 2019.12.27
  • Published : 2019.12.31

Abstract

The method to remove the head of the cast-in-place pile using the detonating cord and horizontal separation plate was proposed in this paper. Plain concrete block was fabricated. Through the blasting test of the concrete block, the charge weight and the burden required for cutting the pile head were identified. The degree of damage of concrete blocks after cutting the head was checked using AUTODYN 2D. As a result of the experiment, it was found that the concrete block was cut using the 10 g/m detonating cord and horizontal separation plate, and the directional cutting of the block using the horizontal separation plate and the block damage caused by the detonating cord were reduced.

도폭선과 수평분리판을 이용한 현장타설 말뚝 두부를 제거하는 방법을 제안하였다. 무근 콘크리트 블록을 제작하였고, 콘크리트 블록 발파실험을 통하여 말뚝 두부 절단에 필요한 도폭선 약량과 최소저항선을 확인하였다. AUTODYN 2D를 이용하여 두부 절단 후 콘크리트 블록의 손상 정도를 확인하였다. 실험결과 10g/m 도폭선과 수평분리판을 이용한 콘크리트 블록 절단을 확인하였고, 수평분리판을 사용하여 블록의 방향성 절단과 도폭선에 의한 블록 손상이 저감됨을 확인하였다.

Keywords

References

  1. 노유송, 2018, 콘크리트 블록에서 인공절리에 따른 발파영향 평가, 화약.발파(대한화약발파공학회지), Vol. 36, No. 3, pp.1-9.
  2. Kim, H. M., 2011, Numerical study on the Breaking Mechanism of Concrete Pile Top using Buried Charge Holders, Chonbuk National University Master degree.
  3. Kim, H. M., 2017, Fracture process analyses of small-scaled concrete columns in controlled blasting utilizing simplified charge holder and steel plate ring, Tech. Energetic Materials, Vol. 78, No. 6, pp. 135-142
  4. KOREA KACOH, 2012, 현장타설 콘크리트 말뚝 두부의 급속처리를 위한 동적파쇄공법 개발, 중소기업청 산학연공동 기술개발사업 최종보고서.
  5. Riedel, W., K. Thomas, S. Hiermaier and E. Schmolinske, 1999, Penetration of Reinforced Concrete by BETA-B-500 Numerical Analysis using a New Macroscopic Concrete Model for Hydrocodes, 9th International Symposium on the Interaction of the Effects of Munitions with Structures, Berlin-Strausberg, Germany, pp. 315-322.