On determining a non-periodic preventive maintenance schedule using the failure rate threshold for a repairable system

  • Lee, Juhyun (Department of Industrial and Management Engineering, Hanyang University) ;
  • Park, Jihyun (Department of Industrial and Management Engineering, Hanyang University) ;
  • Ahn, Suneung (Department of Industrial and Management Engineering, Hanyang University ERICA Campus)
  • 투고 : 2017.05.08
  • 심사 : 2018.03.19
  • 발행 : 2018.08.25

초록

Maintenance activities are regarded as a key part of the repairable deteriorating system because they maintain the equipment in good condition. In practice, many maintenance policies are used in engineering fields to reduce unexpected failures and slow down the deterioration of the system. However, in traditional maintenance policies, maintenance activities have often been assumed to be performed at the same time interval, which may result in higher operational costs and more system failures. Thus, this study presents two non-periodic preventive maintenance (PM) policies for repairable deteriorating systems, employing the failure rate of the system as a conditional variable. In the proposed PM models, the failure rate of the system was restored via the failure rate reduction factors after imperfect PM activities. Operational costs were also considered, which increased along with the operating time of the system and the frequency of PM activities to reflect the deterioration process of the system. A numerical example was provided to illustrate the proposed PM policy. The results showed that PM activities performed at a low failure rate threshold slowed down the degradation of the system and thus extended the system lifetime. Moreover, when the operational cost was considered in the proposed maintenance scheme, the system replacement was more cost-effective than frequent PM activities in the severely degraded system.

키워드

과제정보

연구 과제 주관 기관 : National Research Foundation of Korea(NRF)

참고문헌

  1. Ahmad, R. and Kamaruddin, S. (2012), "An overview of timebased and condition-based maintenance in industrial application", Comput. Ind. Eng., 63(1), 135-149. https://doi.org/10.1016/j.cie.2012.02.002
  2. Ahn, S. and Kim, W. (2011), "On determination of the preventive maintenance interval guaranteeing system availability under a periodic maintenance policy", Struct. Infrastruct. E., 7(4), 307-314. https://doi.org/10.1080/15732470802587129
  3. Barlow, R. and Hunter, L. (1960), "Optimum preventive maintenance policies", Oper. Res., 8(1), 90-100. https://doi.org/10.1287/opre.8.1.90
  4. Bouguerra, S., Chelbi, A. and Rezg, N. (2012), "A decision model for adopting an extended warranty under different maintenance policies", Int. J. Prod. Econ., 135(2), 840-849. https://doi.org/10.1016/j.ijpe.2011.10.022
  5. Canfield, R. (1986), "Cost optimization of periodic preventive maintenance", IEEE T. Reliab., 35(1), 78-81. https://doi.org/10.1109/TR.1986.4335355
  6. Dieulle, L., Berenguer, C., Grall, A. and Roussignol, M. (2003), "Sequential condition-based maintenance scheduling for a deteriorating system", Eur. J. Oper. Res., 150(2), 451-461. https://doi.org/10.1016/S0377-2217(02)00593-3
  7. Doostparast, M., Kolahan, F. and Doostparast, M. (2014), "A reliability-based approach to optimize preventive maintenance scheduling for coherent systems", Reliab. Eng. Syst. Safe, 126, 98-106. https://doi.org/10.1016/j.ress.2014.01.010
  8. Doyen, L. and Gaudoin, O. (2004), "Classes of imperfect repair models based on reduction of failure intensity or virtual age", Reliab. Eng. Syst. Safe, 84(1), 45-56. https://doi.org/10.1016/S0951-8320(03)00173-X
  9. El-Ferik, S. and Ben-Daya, M. (2006), "Age-based hybrid model for imperfect preventive maintenance", IIE Trans., 38(4), 365-375. https://doi.org/10.1080/07408170500232545
  10. Huang, T.L., Zhou, H., Chen, H.P. and Ren, W.X. (2016), "Stochastic modelling and optimum inspection and maintenance strategy for fatigue affected steel bridge members", Smart Struct. Syst., 18(3), 569-584. https://doi.org/10.12989/sss.2016.18.3.569
  11. Huang, Y. S., Chen, E. and Ho, J. W. (2013), "Two-dimensional warranty with reliability-based preventive maintenance", IEEE T. Reliab., 62(4), 898-907. https://doi.org/10.1109/TR.2013.2285051
  12. Jaturonnatee, J., Murthy, D. and Boondiskulchok, R. (2006), "Optimal preventive maintenance of leased equipment with corrective minimal repairs", Eur. J. Oper. Res., 174(1), 201-215. https://doi.org/10.1016/j.ejor.2005.01.049
  13. Kijima, M. (1989), "Some results for repairable systems with general repair", J. Appl. Probab., 26(1), 89-102. https://doi.org/10.2307/3214319
  14. Liao, W., Pan, E. and Xi, L. (2010), "Preventive maintenance scheduling for repairable system with deterioration", J. Intell. Manuf., 21(6), 875-884. https://doi.org/10.1007/s10845-009-0264-z
  15. Lin, D., Zuo, M.J. and Yam, R.C. (2001), "Sequential imperfect preventive maintenance models with two categories of failure modes", Nav. Res. Log., 48(2), 172-183. https://doi.org/10.1002/1520-6750(200103)48:2<172::AID-NAV5>3.0.CO;2-5
  16. Lin, Z.L., Huang, Y.S. and Fang C.C. (2015), "Non-periodic preventive maintenance with reliability thresholds for complex repairable systems", Reliab. Eng. Syst. Safe, 136, 145-156. https://doi.org/10.1016/j.ress.2014.12.010
  17. Lin, Z.L. andHuang, Y.S. (2010), "Nonperiodic preventive maintenance for repairable systems", Nav. Res. Log., 57(7), 615-625. https://doi.org/10.1002/nav.20418
  18. Lu, B., Zhou, X. and Li, Y. (2016), "Joint modeling of preventive maintenance and quality improvement for deteriorating singlemachine manufacturing systems", Comput. Ind. Eng., 91, 188-196. https://doi.org/10.1016/j.cie.2015.11.019
  19. Martorell, S., Sanchez, A. and Serradell, V. (1999), "Age-dependent reliability model considering effects of maintenance and working conditions", Reliab. Eng. Syst. Safe, 64(1), 19-31. https://doi.org/10.1016/S0951-8320(98)00050-7
  20. Nakagawa, T. (1979), "Optimum policies when preventive maintenance is imperfect", IEEE T. Reliab., 4, 331-332.
  21. Nakagawa, T. (1988), "Sequential imperfect preventive maintenance policies", IEEE T. Reliab., 37(3), 295-298. https://doi.org/10.1109/24.3758
  22. Nakagawa, T. and Mizutani, S. (2009), "A summary of maintenance policies for a finite interval", Reliab. Eng. Syst. Safe, 94(1), 89-96. https://doi.org/10.1016/j.ress.2007.04.004
  23. Nguyen, D. and Murthy, D. (1981), "Optimal preventive maintenance policies for repairable systems", Oper. Res., 29(6), 1181-1194. https://doi.org/10.1287/opre.29.6.1181
  24. Park, D.H., Jung, G.M. and Yum, J.K. (2000), "Cost minimization for periodic maintenance policy of a system subject to slow degradation", Reliab. Eng. Syst. Safe, 68(2), 105-112. https://doi.org/10.1016/S0951-8320(00)00012-0
  25. Park, K.H., Lee, S.Y., Yoon, J.H., Cho, H.N. and Kong, J.S. (2008). "Optimum maintenance scenario generation for existing steel-girder bridges based on lifetime performance and cost", Smart Struct. Syst., 4(5), 641-653. https://doi.org/10.12989/sss.2008.4.5.641
  26. Roach, D. (2009), "Real time crack detection using mountable comparative vacuum monitoring sensors", Smart Struct. Syst., 5(4), 317-328. https://doi.org/10.12989/sss.2009.5.4.317
  27. Schutz, J. and Rezg, N. (2013), "Maintenance strategy for leased equipment", Comput. Ind. Eng., 66(3), 593-600. https://doi.org/10.1016/j.cie.2013.05.004
  28. Sheu, S.H. and Chang, C.C. (2009), "An extended periodic imperfect preventive maintenance model with age-dependent failure type", IEEE Trans. Rel., 58(2), 397-405. https://doi.org/10.1109/TR.2009.2020103
  29. Toledo, M.L.G., Freitas, M.A., Colosimo, E.A. and Gilardoni, G. L. (2016), "Optimal periodic maintenance policy under imperfect repair: A case study on the engines of off-road vehicles", IIE Trans., 48(8), 747-758. https://doi.org/10.1080/0740817X.2016.1147663
  30. Wang, H. (2002), "A survey of maintenance policies of deteriorating systems", Eur. J. Oper. Res., 139(3), 469-489. https://doi.org/10.1016/S0377-2217(01)00197-7
  31. Yanez, M., Joglar, F. and Modarres, M. (2002), "Generalized renewal process for analysis of repairable systems with limited failure experience", Reliab. Eng. Syst. Safe, 77(2), 167-180. https://doi.org/10.1016/S0951-8320(02)00044-3
  32. Yeh, R.H. and Chang, W.L. (2007), "Optimal threshold value of failure-rate for leased products with preventive maintenance actions", Math Comput. Model, 46(5), 730-737. https://doi.org/10.1016/j.mcm.2006.12.001
  33. Zhao, Y. (2003), "On preventive maintenance policy of a critical reliability level for system subject to degradation", Reliab. Eng. Syst. Safe, 79(3), 301-308. https://doi.org/10.1016/S0951-8320(02)00201-6
  34. Zhou, X., Xi, L. and Lee, J. (2007), "Reliability-centered predictive maintenance scheduling for a continuously monitored system subject to degradation", Reliab. Eng. Syst. Safe, 92(4), 530-534. https://doi.org/10.1016/j.ress.2006.01.006
  35. Zhou, X., Xi, L. and Lee, J. (2009), "Opportunistic preventive maintenance scheduling for a multi-unit series system based on dynamic programming", Int. J. Prod. Econ., 118(2), 361-366. https://doi.org/10.1016/j.ijpe.2008.09.012