Abstract
Earned Value Management(EVM) has been used to manage and forecast defense project schedule and cost over the last two decades in the world. However to support the lacking ability of schedule analysis in traditional EVM, earned schedule(ES) has been introduced as a tool to more accurately estimate schedule performance. This paper compares which method EVM or ES, provides more accurate schedule predictors in 32 Korean defense research and development projects. As a result of comparison, the ES method can predict the future schedule more reliably than the EVM method. We also analyze early warning function of schedule performance index considering project duration extension point. Through the analysis results, we confirm that both the EVM and the ES method lack the ability of the early warning in terms of the current schedule management criterion.