Abstract

Steel roof construction is on the most important and critical factors in the large spatial construction and necessary to be prepared under a radical planning. Therefore, the major management factors of steel roofing structure assembly must be critically reviewed during planning. Through the review process, it is necessary to reduce the construction cost, to prevent delays in the construction schedule, and to minimize construction errors. However, domestically due to the lack experience in large spatial constructions, a planning of roof construction is limited to have a radical planning. Especially due to unclear organization of the management factors in hierarchy, using them in reality for construction planning is difficult and reliability is low. Therefore, in this study, the goal is to conduct the major management factors in the large spatial construction. To achieve this, we have reviewed and analyzed the numbers of construction plans and construction reports and conducted a total 68 of the management factors. Based on the conducted factors, we have interviewed 16 experts with experience in large spatial construction. From the interview result, we have deduced the factors scored above 4.20 of 10 for critical factors. The results of this study will be used as a guidance for planning steel roofing structure assembly in large spatial construction. The critical factors will be provided to the site mangers for the quality management of large spatial constructions in practice.

Keywords

References

  1. Shin, D. W., & Park, C. S., "An Analysis of Preparation and Evaluation Practice of Building Construction Plan Documents at the Bidding Stage", Journal of the Architectural Institute of Korea Structure & construction, Vol.16, No.7, pp.95-103, 2000
  2. Daewoo E&C, Gwangmyeong speedom project construction report, Daewoo E&C, Seoul, 2013
  3. Hanwha E&C, Philippine arena project construction report, Hanwha E&C, Seoul, 2015
  4. Hyundai Development Company, Gocheok sky dome construction report, Hyundai Development Company, Seoul, 2016
  5. Jung, H. M., Lee, S. Y., & Jee, S. W., "The Case Study on the Erection Method of Large Span Structures", Journal of Korean Association for Spatial Structure, Vol.7, No.2, pp.97-104 2007
  6. Kang, C. U., Park, K. H., & Choe, M. K., "A Study on Condition Analysis of Lifting Planning for Roof System of Large Span Spatial Structure", Journal of the Architectural Institute of Korea Structure & Construction, Vol. 27, No.11, pp.95-102, 2011
  7. Park, K. H., "A Study on the Lifting Planning Process Model for Roof System of Large Span Spatial Structures", Doctorial Dissertation, Keimyung University, 2012