Computational Design of Bifurcation: A Case Study of Darundi Khola Hydropower Project

  • Received : 2015.06.09
  • Accepted : 2016.10.17
  • Published : 2017.03.31

Abstract

Bifurcation refers to wye division of penstock to divide the flow symmetrically or unsymmetrically into two units of turbine for maintaining economical, technical and geological substrates. Particularly, water shows irrelevant behavior when there is a sudden change in flow direction, which results into the transition of the static and dynamic behavior of the flow. Hence, special care and design considerations are required both hydraulically and structurally. The transition induced losses and extra stresses are major features to be examined. The research on design and analysis of bifurcation is one of the oldest topics related to R&D of hydro-mechanical components for hydropower plants. As far as the earlier approaches are concerned, the hydraulic designs were performed based on graphical data sheet, head loss considerations and the mechanical analysis through simplified beam approach. In this paper, the multi prospect approach for design of Bifurcation, incorporating the modern day's tools and technology is identified. The hydraulic design of bifurcation is a major function of dynamic characteristics of the flow, which is performed with CFD analysis for minimum losses and better hydraulic performances. Additionally, for the mechanical design, a simplified conventional design method as pre-estimation and Finite Element Method for a relevant result projections were used.

Keywords

References

  1. F. Flemming, J. Foust, J. Koutnik, R.K. Fisher, 2009, "Overload Surge Investigation using CFD Data ," International Journal of Fluid Machinery and Systems, Vol. 2, No. 4, pp 315-323. https://doi.org/10.5293/IJFMS.2009.2.4.315
  2. J. H. Bambei, 2012, "Steel Penstock," Ed. 1 ASCE Publications.
  3. K.S. Ltd.,2012, "Technical Highlights Vol. 5" Retrived 2014, from KOBE: http://www.kobelco-welding.jp/education-center/technical-highlight/vol05.html
  4. R.K. Malik, P. Paudel, 2009, "Flow Modeling of the first trifurcation made in Nepal, Hydro Nepal: Journal of Water, Energy and Environment, Kathmandu, Nepal," Vol. 5, pp.
  5. A. Adamkowski, 2001, "Case Study: Lapino Power Plant Penstock Failure," Journal of Hydraulic Engineering, Vol. 7, pp. 547-555.
  6. A.W.W.A. Staff, "Steel Pipe: A Guide for Design and Installation" Ed: 4, American Water Works Association.
  7. D.S. Miller, 1990, "Internal Flow Systems 2," Cranfield: BHRA.
  8. S. Chitrakar, M. Cervantes, B.S. Thapa, 2014, "Fully coupled FSI analysis of Francis turbines exposed to sediment erosion," International Journal of Fluid Machinery and Systems, Vol. 7, No. 3. pp. 101-109. https://doi.org/10.5293/IJFMS.2014.7.3.101
  9. C.A. Aguirre, R. G. R. Camacho, "Head losses analysis in symmetrical trifurcations of Penstocks - High Pressure Pipeline Systems CFD," AGHEM.
  10. Bureau of Indian Standards, 1995, "Pressure Vessels". IS 11639-2.
  11. Bureau of Indian Standards, 1969, "Code for unfired pressure vessels," IS 2825.
  12. American Iron and Steel Institute, 1998, "Buried Steel Penstock".
  13. X. Huan, L. Houlin, T. Minggao, C. Jianbao, 2013, "Fluid-Structure Interaction Study on Diffuser Pump With a Two-Way Coupling Method" International Journal of Fluid Machinery and Systems, Vol. 6, No. 2, pp. 87-93. https://doi.org/10.5293/IJFMS.2013.6.2.087