Abstract

In Korea, many nuclear power plants operate at a single site based on geographical characteristics, but the population density near the sites is higher than that in other countries. Thus, multiunit accidents are a more important consideration than in other countries and should be addressed appropriately. Currently, there are many issues related to a multiunit probabilistic safety assessment (PSA). One of them is the quantification of a multiunit PSA model. A traditional PSA uses a Boolean manipulation of the fault tree in terms of the minimal cut set. However, such methods have some limitations when rare event approximations cannot be used effectively or a very small truncation limit should be applied to identify accident sequence combinations for a multiunit site. In particular, it is well known that seismic risk in terms of core damage frequency can be overestimated because there are many events that have a high failure probability. In this study, we propose a quantification method based on a Monte Carlo approach for a multiunit PSA model. This method can consider all possible accident sequence combinations in a multiunit site and calculate a more exact value for events that have a high failure probability. An example model for six identical units at a site was also developed and quantified to confirm the applicability of the proposed method.

Keywords

References

  1. PLG Inc, Seabrook station probabilistic safety assessment, Section 13.3, Risk of two unit station, Prepared for Public Service Company of New Hampshire, PLG-0300, 1983.
  2. T. Hakata, Seismic PSA method for multiple nuclear power plants in a site, Reliab. Eng. Syst. Saf. 92 (2007) 883-894. https://doi.org/10.1016/j.ress.2006.04.022
  3. S. Samaddar, K. Hibino, O. Coman, Technical approach for safety assessment of multi-unit NPP sites subject to external events, Probabilistic Safety Assessment and Management PSAM 12, Honolulu, Hawaii, 2014.
  4. M.A. Stutzke, Scoping estimates of multiunit accident risk, Probabilistic Safety Assessment and Management PSAM 12, Honolulu, Hawaii, 2014.
  5. K. Flemming, On the issues of integrated risk-a PRA practitioners perspective, Proceedings of the ANS International Topical Meeting on Probabilistic Safety Analysis, San Francisco, CA, USA, 2005.
  6. T.D. Duy, D. Vasseur, E. Serdet, Multi units probabilistic safety assessment: methodological elements suggested by EDF R&D, Probabilistic Safety Assessment and Management PSAM 12, Honolulu, Hawaii, 2014.
  7. V. Hassija, C.S. Kumar, K. Velusamy, Probabilistic safety assessment of multi-unit nuclear power plant sites-an integrated approach, J. Loss Prevent. Process Ind. 32 (2014) 52-62. https://doi.org/10.1016/j.jlp.2014.07.013
  8. S. Schroer, M. Modarres, An event classification schema for evaluating site risk in a multi-unit nuclear power plant probabilistic risk assessment, Reliab. Eng. Syst. Saf. 117 (2013) 40-51. https://doi.org/10.1016/j.ress.2013.03.005
  9. K. Ebisawa, T. Teragaki, S. Nomura, H. Abe, M. Shigemori, M. Shimomoto, Concept and methodology for evaluating core damage frequency considering failure correlation at multi units and sites and its application, Nucl. Eng. Des. 288 (2015) 82-97. https://doi.org/10.1016/j.nucengdes.2015.01.002
  10. J.W. Reed, M.W. McCann, J. Iihara, H. Hadidi-Tamjed, Analytical techniques for performing probabilistic seismic risk assessment of nuclear power plants, ICOSSAR '85, 4th International Conference on Structural Safety and Reliability, Kobe, Japan, 1985.
  11. S. Epstein, A. Rauzy, Can we trust PRA? Reliab. Eng. Syst. Saf. 88 (2005) 195-205. https://doi.org/10.1016/j.ress.2004.07.013
  12. S. Han, J. Park, D. Kim, H. Lim, S. Jang, Comparison of various methods to quantify a fault tree for Seismic PSA, Transactions of the Korean Nuclear Society Spring Meeting, Jeju, Korea, 2015.
  13. EPRI, Methodology for developing seismic fragilities, TR-103959, 1994.
  14. S. Han, H. Lim, Top event probability evaluation of a fault tree having circular logics by using Monte Carlo method, Nucl. Eng. Des. 243 (2012) 336-340. https://doi.org/10.1016/j.nucengdes.2011.11.029

Cited by

  1. Feasibility of shared use of alternative AC diesel generator under dual-unit station blackout vol.54, pp.10, 2017, https://doi.org/10.1080/00223131.2017.1359123
  2. Multi-unit Level 2 probabilistic safety assessment: Approaches and their application to a six-unit nuclear power plant site vol.50, pp.8, 2018, https://doi.org/10.1016/j.net.2018.04.005
  3. AIMS-MUPSA software package for multi-unit PSA vol.50, pp.8, 2017, https://doi.org/10.1016/j.net.2018.06.012
  4. Development of logical structure for multi-unit probabilistic safety assessment vol.50, pp.8, 2017, https://doi.org/10.1016/j.net.2018.10.012
  5. A Method to Avoid Underestimated Risks in Seismic SUPSA and MUPSA for Nuclear Power Plants Caused by Partitioning Events vol.14, pp.8, 2021, https://doi.org/10.3390/en14082150
  6. Probability subtraction method for accurate quantification of seismic multi-unit probabilistic safety assessment vol.53, pp.4, 2021, https://doi.org/10.1016/j.net.2020.09.022
  7. Multi-unit nuclear power plant probabilistic risk assessment: A comprehensive survey vol.213, pp.None, 2021, https://doi.org/10.1016/j.ress.2021.107782