A Case Study on the Vibration Propagation Characteristics by Underwater Rock Cutting Work

수중 쇄암작업에 따른 진동 전파 특성에 관한 시공 사례

  • 임대규 ((주)대영지오발파엔지니어링) ;
  • 신영철 ((주)대영지오발파엔지니어링) ;
  • 김영민 ((주)대영지오발파엔지니어링) ;
  • 이충언 (SK건설)
  • Received : 2015.06.16
  • Accepted : 2015.06.26
  • Published : 2015.06.30

Abstract

The common underwater rock removal methods involve underwater blasting and crane's chisel dropping impact method. From an environmental point of view, these methods cause ground vibrations and underwater noise. At the site for this study, a method of dropping heavyweight chisel is selected to remove the underwater bedrock near the ferry rack in the course of improving the cargo handling ability of the loading dock. A prediction formula for the vibration was obtained based on the measurement and evaluation of the vibrations caused by the chisel dropping impacts during the test droppings. The prediction formula was successfully applied to the main construction for securing the stability of the structure.

수중 암반 제거 방법은 화약을 사용한 수중발파와 크레인에 장착된 쇄암봉 낙하 충격을 이용하는 방법 등이 널리 이용된다. 이와 같은 암반 제거 방법은 환경적인 요인에서 지반 진동과 수중 소음을 유발하게 된다. 본 연구 대상 현장은 하역 부두의 접안능력을 향상시키기 위해 기 설치된 잔교식 돌핀 구조물에 근접한 지역의 수중 기반암을 쇄암봉 낙하에 의해 제거하도록 설계되어 있다. 시험시공을 통하여 쇄암봉 낙하 충격으로 유발되는 진동에 대한 계측, 평가를 거쳐 진동 추정식을 획득하였고, 이를 본 공사에 반영하여 구조물에 대한 안전성을 확보하였다.

Keywords

References

  1. 네스트 E&C, 2003, 시화조력발전소 건설공사 발파설계보고서, pp. 40.
  2. 에스큐엔지니어링(주), 2013, V-Project OO부두 정밀안전진단, pp. 14.
  3. 이수관, 2009, 해양교통시설기초 암반파쇄와 겔파쇄, 2009년도 공동학술대회"해양산업의 녹색성장을 위한 선도전략"논문집, pp. 419-424.
  4. 환경부, 2010, 진동레벨과 진동속도의 상관성 분석 등에 관한 연구, pp. 13.