Cost Estimating Method of Public Building Construction through Construction Scale

공사규모에 따른 공공건축물 공사비의 산정방법

  • Yim, Jin-Ho (Graduate School, Chungbuk National University) ;
  • Park, Jun-Mo (Institute of Construction Technology, Chungbuk National University) ;
  • Kim, Ok-Kyue (Department of Architectural Engineering, Chungbuk National University)
  • Received : 2014.11.10
  • Accepted : 2015.03.26
  • Published : 2015.06.20

Abstract

As there are a lot of differences in the public building construction cost depending on the construction scale of actual construction cost system, a lot of problems occur in the estimation of the cost. So, the development of a predictive model depending on the construction scale shall be used in a way that it is applied to the case selectively and differently. This study drew a cost estimating model through a regression analysis. For this, 42 construction sites which were ordered during 2011 to 2012 by Public Procurement Service data were selected as a historical data. Based on the application of the model to new construction and the verification of its effect, the reasonable model for estimating the construction cost has been suggested.

공공건축물공사의 실적공사비제도에서 공사규모에 대한 건축공사비 차이가 크게 나타나므로, 산정방식에서 많은 문제점으로 제기된다. 이에 공사규모에 따라서 선별적, 차등적으로 적용할 예측모형의 개발이 필요하다. 이에 본 연구는 조달청에서 2011~2012년에 발주한 이미 준공된 42개 현장의 실적자료에서 공사규모 $5,000m^2{\sim}20,000m^2$으로 선정하여, 회귀분석을 통해서 추정된 모형을 도출하였다. 이를 근거로 신규공사에 적용하여 검증함으로써 합리적인 건축공사비 예측모형을 제시하였다.

Keywords

References

  1. Yim JH, Park JM, Kim OK. Presumption Method for Optimum Correction Rate of Total Construction Cost Using the Median based on Historical Data Analysis in Public Office Buildings. Journal of Korean Institute of Building Construction. 2014 Oct;14(5):415-22. https://doi.org/10.5345/JKIBC.2014.14.5.415
  2. Phaobunjong Kan. Parametric Cost Estimating Model for Conceptual Cost Estimating of Building Construction Projects. [Dissertation]. [Austin (Texas)]: University of Texas at Austin 2002. 18-20 p.
  3. Seo JO, Ryu HG, Lee DR. Development of Public Office Cost Estimating Framework in Feasibility and Design Stage. Journal of the Architectural Institute of Korea (Structure & Construction). 2008 Mar;23(3):158-60.
  4. Yoo CK, Song JK, Lee YS, Kim JJ. An Empirical Study on Construction Cost Estimation in Public Work. Journal of the Korea Institute of Building Construction, 2009 Feb;9(1):65-73 https://doi.org/10.5345/JKIC.2009.9.1.065
  5. Koo WY, Kim JG, Lee JS, Park HG. Cost Estimating Method for the Public Office Building at the Early Stage. Proceeding of conference in the 7th Korean Institute of Construction Engineering and Management; 2007 Nov 9-10; Busan, Korea. Seoul (Korea): Korean Institute of Construction Engineering and Management; 2007. p. 261-6.
  6. Lee HS, Jung MJ, Park MS, Son BS. Cost Estimating for Public Facilities at Early Stage Using Functional Area Cost. Korean Journal of Construction Engineering and Management. 2010 Nov;11(6):3-13.
  7. Park WW, Orderer project cost management and performance construction cost advantage Survey of Japan. Korea Construction Economy Research Institute;2006:11(98), p.55
  8. Potts, Keith F.,Pathchel, Brendan, Major Construction Works_Contractual & Financial Management. Longman Group Ltd; 1995. 42 p.
  9. An SH, Lee YH. Management․Economic Statistics. Seoul (Korea): Pakyoungsa; 2003. 324 p.
  10. Kim TK. u-Can Regression Analysis. 1st ed. Seoul (Korea): Human & Welfare. 2006. 53 p.
  11. Paul Teetor. R Cookbook. 1st ed. Sebastopel: O'Reilly Media; 2011. 254-98 p.
  12. Albert Hamilton. Management by Projects achieving success in a changing world. London (UK): Thomas Telford House; 1997. 250-4 p.