4D BIM based Workspace Planning Process in Building Construction Project

4D BIM 기반의 건설프로젝트 작업공간 계획 프로세스

  • Received : 2013.06.18
  • Accepted : 2013.08.26
  • Published : 2013.09.30

Abstract

Each participant in building construction project requires their own workspace to execute their activities. In this environment, inappropriate workspace planning in construction site causes workspace conflicts which result in a loss of productivity, safety hazard and poor-quality issues. Therefore, workspace should be regarded as one of the most important resources and constraints have to be managed at construction site. However, current construction planning techniques such as Gantt chart, network diagram and critical path method have proven to be insufficient to workspace planning. This paper contains formalized process for workspace planning in 4D BIM environment to prevent workspace related problems in construction project. The proposed process in this paper represents workspace occupation status for each activity and suitable solutions for identified workspace conflicts by integrating workspace attributes and activity execution plan. Based on the result of this study, project manager will be able to prevent probable workspace conflicts and negative effect on project performance by devising appropriate workspace plan during preconstruction phase.

건설프로젝트에서는 다양한 참여자들이 제한된 공간에서 각자의 작업공간을 차지하며 작업을 수행한다. 작업공간에 대한 부적절한 계획은 건설프로젝트의 생산성 감소, 작업 위험 증가 및 품질 저하 등의 문제로 이어지기 때문에 작업공간은 건설프로젝트에서 고려하여야 할 중요한 요소 중 하나이다. 그러나 기존의 건설프로젝트 공사 계획 수립을 위한 방법들은 건설프로젝트에서의 작업공간을 고려하지 못하는 한계가 있었다. 따라서 본 연구에서는 체계적이지 못한 작업공간 계획으로 인하여 발생하는 작업공간 간섭 문제를 예방하기 위하여 4D BIM(Building Information Model) 기반의 작업공간 계획 프로세스를 제안한다. 제안된 프로세스는 각 작업공간의 특성과 공사수행계획을 반영하여 각 액티비티의 작업공간 점유상태를 표현하고 이를 바탕으로 발생 가능한 작업공간 간섭을 발견한다. 또한 각 액티비티와 작업공간의 특성 그리고 공사수행계획 등을 고려하여 발견된 작업공간 간섭에 대한 해결책을 도출한다. 본 연구의 결과를 바탕으로, 프로젝트 관리자는 본 공사 수행 이전에 공사에 필요한 작업공간을 미리 계획함으로써 서로 다른 액티비티 작업공간 사이의 간섭을 예방하고 건설프로젝트에서의 불필요한 손실을 예방할 수 있다.

Keywords

References

  1. 이현수.박길재.박문서.류한국 (2010). "고층 건축공사의 공간 활용을 위한 공정계획 모델", 대한건축학회 논문집, 제26권 제6호, pp. 129-138
  2. 박문서.양영준.이현수.한상원.지세현 (2011). "건축물 마감공사 자재 배치 최적화 모델", 한국건설관리학회 논문집, 제12권 제1호, 한국건설관리학회, pp. 43-52 https://doi.org/10.6106/KJCEM.2011.12.1.43
  3. Akinci, B., Fischer, M. Kunz, J. and Levitt, R. (2002a). "Representing work spaces generically in construction method models." Journal of Construction Engineering and Management, ASCE, 128(4), pp. 296-305 https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(296)
  4. Akinci, B., Fischer, M., Levitt, R., and Carlson, R. (2002b). "Formalization and automation of time-space conflict analysis." Journal of Computing in Civil Engineering, ASCE, 16(2), pp. 124-134 https://doi.org/10.1061/(ASCE)0887-3801(2002)16:2(124)
  5. Akinci, B., Fischer, M., and Kunz, J. (2002c). "Automated Generation of Work Spaces Required by Construction Activities." Journal of Construction Engineering and Management, ASCE, 128(4), pp. 306-315 https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(306)
  6. Chau, K. W., Anson, M., and Zhang, J. P. (2004). "Four-Dimensional Visualization of Construction Scheduling and Site Utilization." Journal of Construction Engineering and Management, ASCE, 130(4), pp. 598-606 https://doi.org/10.1061/(ASCE)0733-9364(2004)130:4(598)
  7. Chavada, R., Dawood, N. and Kassem, M. (2012). "Construction workspace management: the development and application of a novel nD planning approach and tool." Journal of Information Technology in Construction, 17, pp. 213-236
  8. Chua, D., Yeoh, K., and Song, Y. (2010). "Quantification of Spatial Temporal Congestion in Four - Dimensional Computer-Aided Design." Journal of Construction Engineering and Management, ASCE, 136(6), pp. 641-649 https://doi.org/10.1061/(ASCE)CO.1943-7862.0000166
  9. Dawood, N. and Z. Mallasi (2006). "Construction workspace planning: Assignment and analysis utilizing 4D visualization technologies." Computer-Aided Civil and Infrastructure Engineering, 21(7), pp. 498-513 https://doi.org/10.1111/j.1467-8667.2006.00454.x
  10. DeLoura, M.. A., Ahamd, A., Bilas, S., Boer, J., Dietrich, S. and Dybsand, E., et al. (2000). Game programming germs, Charles River Media, Inc., USA, pp. 502-516
  11. Eastman, C. Teicholz, P., Sacks, R., and Liston, K. (2008). BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers, and Contractors, John Whiley & Sons Inc., USA, pp. 25-64
  12. Guo, S. J. (2002). "Identification and resolution of work space conflicts in building construction." Journal of Construction Engineering and Management, ASCE, 128(4), pp. 287-295 https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(287)
  13. Kelsey, J., Winch, G., and Penn, A. (2001). "Understanding the Project Planning Process: Requirements Capture for the Virtual Construction Site." University College London, UK, Bartlett Research
  14. Mallasi, Z. (2006). "Dynamic quantification and analysis of the construction workspace congestion utilising 4D visualisation." Automation in Construction, 15(5), pp. 640-655 https://doi.org/10.1016/j.autcon.2005.08.005
  15. Moller T. and Haines E. (2002). Real time Rendering, 2nd ed., A K Peters, Ltd., USA, pp. 631-668
  16. National BIM Standard-United States Version 2, National BIM Standard-United States Project Committee, (2013.06.10)
  17. Oglesby, C. H., Parker, H. W., and Howell, G. A. (1989). Productivity Improvement in Construction, McGraw-Hill Inc, USA
  18. Riley, D. R., and Sanvido, V. E. (1995). "Patterns of Construction-Space Use in Multistory Buildings." Journal of Construction Engineering and Management, ASCE, 121(4), pp. 464-473 https://doi.org/10.1061/(ASCE)0733-9364(1995)121:4(464)
  19. Riley, D. R., and Sanvido, V. E. (1997). "Space planning method for multistory building construction." Journal of Construction Engineering and Management, ASCE, 123(2), pp. 171-180 https://doi.org/10.1061/(ASCE)0733-9364(1997)123:2(171)
  20. Thabet, W. Y., and Beliveau, Y. J. (1994). "Modeling Work Space to Schedule Repetitive Floors in Multistory Buildings." Journal of Construction Engineering and Management, ASCE, 120(1), pp. 96-116 https://doi.org/10.1061/(ASCE)0733-9364(1994)120:1(96)
  21. Tommelein, I. D., and Zouein, P. P. (1993). "Interactive Dynamic Layout Planning." Journal of Construction Engineering and Management, ASCE, 119(2), pp. 266-287 https://doi.org/10.1061/(ASCE)0733-9364(1993)119:2(266)
  22. Talmaki, S. and V. R. Kamat (2012). "Real-Time Hybrid Virtuality for Prevention of Excavation Related Utility Strikes." Journal of Computing in Civil Engineering, ASCE (On-line Published)
  23. Winch, G. M., and North, S. (2006). "Critical space analysis." Journal of Construction Engineering and Management, ASCE, 132(5), pp. 473-481 https://doi.org/10.1061/(ASCE)0733-9364(2006)132:5(473)

Cited by

  1. Workspace Generation and Interference Optimization Algorithm by Work-type using 3D Model Object in a Construction Project vol.34, pp.6, 2014, https://doi.org/10.12652/Ksce.2014.34.6.1911