Development of Optimum Construction Lift Operation System using Sensing Information for High-rise Building

센싱정보를 활용한 초고층 건설용 리프트 최적화 운행 시스템 개발

  • 신중환 (성균관대학교 대학원 u-City공학과) ;
  • 권순욱 (성균관대학교 건축공학과, u-City공학과)
  • Received : 2013.05.31
  • Accepted : 2013.07.10
  • Published : 2013.09.30

Abstract

As recent buildings have been more higher and larger, construction vertical lifting planning and operation is a key factor for successful project in tall building. Although many studies have been trying to set up a construction lifting planning system at early stage, there's not existing a control real-time lift operation control system with respect to during construction stage. Therefore, In this study, we use the sensor device to collect the lift operating data for improvement of lift operation efficiency and develope optimum lift operating system which can perform real-time analysis. Finally, we verify the efficiency of proposed system through comparison between realtime operating data and simulated data using proposing system. In this paper, the proposed system show more efficient moving line compared with previous system. This can contribute to development of unmanned lift system.

건축물이 고층화, 대형화 될수록 수직 양중 계획 및 운영에 관한 중요성이 부각되고 있다. 이에 프로젝트 초기 단계에 실제 모델과 유사한 건설용 리프트 양중계획을 수립하려는 노력이 계속되고 있지만 프로젝트 착수 후 리프트 운행을 컨트롤 할 수 있는 시스템은 부재한 실정이다. 따라서 본 논문에서는 건설용 리프트 운영 효율증대를 위하여 센서를 사용한 리프트 운행 정보를 수집하고 실시간 분석이 가능한 건설용 리프트 최적화 운행 시스템 개발을 실시 및 검증 단계를 수행하여, 양중 효율의 지표가 되는 사용자 대기 시간의 단축을 도모하고 향후 무인 스마트 리프트의 초석이 되는 시스템을 제시하고자 한다.

Keywords

References

  1. 강용탁 (2007). "건설용 리프트카 무인자동운전장치 건설현장 적용에 관한 연구". 건설안전기술, pp. 86-99
  2. 김선국.한갑규 (2008). "건설 리프트의 적정 대수 산정에 관한 연구". 한국건축시공학회 논문집, 제6권 제3호, pp. 119-125 https://doi.org/10.5345/JKIC.2008.8.3.119
  3. 김동진.송영석.임형철 (2002). "고층건축공사의 리프트 양중계획 합리화". 대한건축학회 논문집, 제22권 제2호, pp. 483-486
  4. 신윤석.강경인 (2010). "이산사건 시뮬레이션을 이용한 초고층 건축공사 건설 리프트 양중계획 모델". 한국건설관리학회 논문집, 제9권 제26호, 한국건설관리학회, pp. 119-127
  5. 신윤석 (2011). "초고층 건축공사를 위한 건설 리프트 양중계획 시스템 개발". 대한건축학회 논문집, 제27권 제22호, pp. 227-235
  6. 안병주 (2001). "초고층건물공사 마감자재의 수직.수평이동 계획이 통합된 의사결정모델". 한양대학교 박사학위 논문
  7. 김재준.안병주 (2004). "이산형 시뮬레이션을 사용한 초고층 빌딩 공사 운반 작업의 최적화". 대한건축학회 논문집, 제17권 제2호, pp. 1377-1383
  8. 이종렬.전용석.박찬식 (2004). "고층건축공사 타워크레인 양중시간 예측모델". 정기학술발표대회 논문집, 제5권, 한국건설관리학회, pp. 472-475
  9. 이학주.김대원.조훈희.강경인 (2008). "큐잉이론을 이용한 고층건물 가설리프트 계획 모델 구축에 관한 연구". 정기학술발표대회 논문집, 제8권, 한국건설관리학회, pp. 635-640
  10. 조창연.권순욱.신태홍.진상윤.김예상 (2011). "A development of next generation intelligent liftcar toolkit for vertical material movement management". Automation in Construction, 20, No. 1, pp. 14-27 https://doi.org/10.1016/j.autcon.2010.07.008
  11. 조창연.조문영.신윤석 (2012). "이산사건 시뮬레이션을 이용한 고층건축공사의 타워크레인 양중시간 예측모델". 한국건설관리학회 논문집, pp. 151-158
  12. 최광수.김학길.김용수 (2002). "건설용 리프트의 사용실태 조사 및 문제점 분석에 관한 연구". 대한건축학회 논문집, 제22권 제2호, pp. 479-482
  13. Leung, Arthur W. T. Tam, C. M. and Liu, D. K (2001). "Comparative study of artificial neural networks and multiple regression analysis for predicting hoisting times of tower cranes". Building and Environment, Vol. 36 No. 4, pp. 457-467 https://doi.org/10.1016/S0360-1323(00)00029-9
  14. R, Sacks. Navon, R. and Shapira, A (2005). "Feasibility of Automated Monitoring of Lifting Equipment in Support of Project Control". Journal of construction Engineering and Management, Vol. 131 No. 5, pp. 604-615 https://doi.org/10.1061/(ASCE)0733-9364(2005)131:5(604)
  15. Zhang, P., Harris, F. C., Olomolaiye, P. O. and Holt, G. D (1999). "Location optimization for a group of tower cranes". Journal of construction engineering and management, Vol. 125 No. 2, pp. 115-122 https://doi.org/10.1061/(ASCE)0733-9364(1999)125:2(115)

Cited by

  1. Inclined construction hoist for efficient resource transportation in irregularly shaped tall buildings vol.62, 2016, https://doi.org/10.1016/j.autcon.2015.11.008
  2. Advanced power supply of construction hoists for supertall buildings vol.59, 2015, https://doi.org/10.1016/j.autcon.2015.08.002
  3. A study on method of vertical zoning of construction lift for high-rise building based on lift planning & operation history database 2017, https://doi.org/10.1007/s12205-017-1374-3
  4. Extraction and Analysis of Construction Phase Risk Factors in High-rise Construction Project vol.17, pp.2, 2016, https://doi.org/10.6106/KJCEM.2016.17.2.090