Abstract
This case study deals with an excavation blasting carried out at "Sooseo-Pyeongtek ${\bigcirc}$-${\bigcirc}$ section construction site" in the vicinity of residential area. Originally, the sequential blasting (multi-stage blasting) using electric detonators was planed in this area. However, there was a concern that the sequential blasting method could increase the construction cost by delaying the construction period due to possible complaints from local residents. As an alternative, electronic deck blasting technique was taken in order to meet the ground vibration regulation (0.2cm/s, in apartment area) and to keep the construction schedule. The performance of the electronic deck charge blasting was two times better than the sequential blasting with electric detonators and the level of ground vibration was also within the regulatory value (0.2cm/s). In particular, it was shown that the use of electronic detonater eDevII, which was developed for tunnel, could provide more convenient and electrically safer working condition.
본 사례는 "수서~평택 고속전철 ${\bigcirc}$-${\bigcirc}$공구 건설공사"로서 공사구간 내에 아파트 등이 매우 근접하여 위치하며, 설계도서에 근거한 다단식 전기발파의 적용은 민원 등으로 인한 공사기간 지연과 더불어 공사관련 민원이 예상되어 공사비 증가가 발생할 것으로 판단된다. 이에 대안 굴착공법으로 당 현장의 진동허용기준(0.2cm/s, 아파트)를 준수하고 공사기간을 합리적으로 단축시켜 경제성과 안정성을 동시에 확보할 수 있는 전자 데크발파 공법을 검토하였다. 시험시공 결과 원 설계인 전기 다단 발파에 비하여 현저히 시공성을 향상시켰으며, 발파 진동 또한 현장 내 진동허용기준(0.2cm/s)이하의 안정적인 수준으로 계측되었다. 특히 터널용 전자뇌관 eDevII를 사용함으로써 작업에 편의성을 더했으며, 전기적으로 안전해 수직구 발파작업 환경에서 전기적인 위험성을 크게 개선할 수 있을 것이라 판단된다.