Abstract
The reason why most scheduling softwares currently using at construction projects adopt PDM (Precedence Diagramming Method) is that it can express an overlapping relationship between activities. However, the overlapping relationships in PDM are represented only by combinations of four overlapping types that connect the start and finish points of two activities, therefore, PDM cannot express efficiently the relationships between any middle points of two activities if they should be represented. This research proposes the method of transforming the four overlapping types of PDM to the overlapping relationships of BDM(Beeline Diagramming Method), new networking technique, that can connect the inter-relationships at any middle points of two activities as well as express multiple overlapping relationships. The proposed method will help not only to improve an efficiency of scheduling but also to upgrade the scheduling technique because BDM technique has a lot of unique advantages in scheduling.
현재 건설사업 실무에 활용되는 대부분의 공정관리 소프트웨어들은 PDM(Precedence Diagramming Method) 기법을 적용하고 있는데 이는 작업 간 중복표시가 가능하기 때문이다. 그러나 기존 PDM방식의 작업 간 중복관계는 선 후행 작업간 착수 및 종료시점을 연결하는 네 가지 조합으로 표시되는데, 실제 건설 사업에서 선 후행 작업 간 중복관계는 작업의 중간시점 어디에서라도 상호 연관관계를 가질 수 있지만 PDM기법은 이를 효율적으로 표현하지 못한다. 따라서 본 연구에서는 작업 간 중복관계를 표시할 때, 작업의 착수와 종료시점에만 국한되지 않고, 작업의 중간 어느 시점에서도 작업 간 상호관계를 연계시킬 수 있을 뿐만 아니라 복수의 중복관계도 표시 할 수 있는 새로운 공정관리 기법인 BDM(Beeline Diagramming Method)기법으로 기존 PDM기법의 네 가지 표현방법을 전환시키는 방법을 제안한다. 이를 통해 기존의 PDM기법으로 작성된 CPM공정계획이 BDM기법의 CPM(Critical Path Method) 공정계획으로 전환이 가능하게 되며, BDM기법의 장점을 활용하여 공정관리의 효율성을 향상시키며 궁극적으로 공정관리의 발전에 기여하고자 한다.