Development of a methodology for analysing and quantifying the impact of delay factors affecting construction projects

  • Shebob, Abdulhamid (School of Science and Engineering (SSE), Teesside University) ;
  • Dawood, Nashwan (School of Science and Engineering (SSE), Teesside University) ;
  • Shah, Raj K. (School of Science and Engineering (SSE), Teesside University)
  • Received : 2012.02.20
  • Accepted : 2012.08.15
  • Published : 2012.09.01

Abstract

Delays are one of the biggest problems facing by the construction industry and they have significant financial and social impact in construction projects. The paper presents a framework of Delay Analysis System (DAS) with the aim of analysing the impact of delay factors in Libyan construction projects. The system has designed by integrating the possible delay factors, critical activities of a project using@risk simulator. A case study of building project was demonstrated to identify the impact of delays and the sensitivity of delay factor. The case study result showed that the project might be delayed by 97 to 103 days in comparison to the planned duration. The developed DAS is a tool for analysing and identify the impacts of delay factors and assist to construction manager to take necessary measure in reducing the delay impact. The paper provides a methodology for analysing the possible delay impact in a construction project and informing to construction manager in advance of the possible delay factors.

Keywords

References

  1. A.A. Bubshait, M.J. Cunningham, "Comparison of delay analysis methodologies", Journal of Construction Engineering and Management, vol. 124, no. 4, pp. 315-322, 1998. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:4(315)
  2. S. AbouRizk, P. Knowles, U.R. Hermann, "Estimating labor production rates for industrial construction activities", Journal of Construction Engineering and Management, vol. 127, no. 6, pp. 502- 511, 2001. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:6(502)
  3. O. Abdelnaser, J. Peter, A. Mahmood, A. Hussin, H. Aziz, "Causes of construction delays", case studies in Langkawi Island, Malaysia, Paper presented at International Conference on built environmental in Kuala Lumpur, Malaysia, organized by University of Malaya, 2005.
  4. S.M. Ahmed, S. Azhar, P. Kappagntula, D. Gollapudil, "Delays in construction: a brief study of the Florida construction industry", Proceedings of the 39th Annual ASC Conference, Clemson University, Clemson, SC, USA, pp. 257-266, 2003.
  5. W.A.M. Alaghbari, "Factors affecting construction speed of industrialized building systems in Malaysia", Master's thesis, University Putra Malaysia, Serdang, 2005.
  6. A.H. Al-Moumani, "Construction Delay: a quantitative analyses", International Journal of Project Management, vol. 18, no. 1, pp. 51-59, 2000. https://doi.org/10.1016/S0263-7863(98)00060-X
  7. S.A. Assaf, M. Al-Khalil, M. Al-Hazmi, "Causes of Delay in Large Building Construction Projects", Journal of Project Management in Engineering, vol. 11, no. 2, pp. 45-50, 1995.
  8. D.K.H. Chua, Y.C. Kog, P.K. Loh, E.J. Jaselskis, "Model for construction budget performance neural network approach", Journal of Construction Engineering and Management, vol. 123, no. 3, pp. 214-222, 1997. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:3(214)
  9. N. Dawood, "Estimating project and activity duration: a risk management approach using network analysis", Construction Management and Economics, vol. 16, no. 1, pp. 41- 48, 1998. https://doi.org/10.1080/014461998372574
  10. Y. Frimpong, J. Oluwoye, I. Crawford, "Statistical methods", 2nd ed., Academic, New York, 2003.
  11. General People's Committee, Regarding permission for investors to execute their investment activities in Libya, decision no. (22) 2003.
  12. A.S. Hanna, M. Gunduz, "Early warning signs for distressed projects", Canadian Journal of Civil Engineering, vol. 32, no. 5, pp. 796-802, 2005. https://doi.org/10.1139/l05-032
  13. P. Jaskowski, S. Biruk, "The conceptual framework for construction project risk assessment", Reliability: Theory & Applications, vol. 2, no. 3, pp. 27-35, 2011.
  14. E.J. Jaselskis, D.B. Ashley, "Optimal allocation of project management resources for achieving success", Journal of Construction Engineering and Management, vol. 117, no. 2, pp. 321-340, 1991. https://doi.org/10.1061/(ASCE)0733-9364(1991)117:2(321)
  15. Y.C. Kog, D.K.H Chua, P.K. Loh, E.J. Jaselskis, "Key determinants for construction schedule performance", International Journal of Project Management, vol. 17, no. 6, pp. 351-359, 1999. https://doi.org/10.1016/S0263-7863(98)00058-1
  16. S.T. Kometa, P.O. Olomolaiye, F.C. Harris, "Attributes of UK construction clients influencing project consultants' performance", Journal of Construction Management and Economics, vol. 12, no. 5, pp 433-443, 1994. https://doi.org/10.1080/01446199400000053
  17. S. Lee, D.W. Halpin, "Predictive tool for estimating accident risk", Journal of Construction Engineering and Management, vol. 129, no. 4, pp. 431-436, 2003. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:4(431)
  18. N.R. Mansfield, "Causes of delay and cost overruns in Nigerian construction project", International Journal of Project Management, vol. 12, no. 4, pp. 254-260, 1994. https://doi.org/10.1016/0263-7863(94)90050-7
  19. M. Mezher, W. Tawil, "Causes of delays in the construction industry Lebanon", Engineering Construction and Architectural Management, vol. 5, no. 3, pp. 251-260, 1998.
  20. C.A.R. Morano, C.G. Martins, M.L.R. Ferreira, "Application of techniques for the identification of risk in the E & P ventures Engevista", vol. 8, no. 2, pp. 120-133, 2006.
  21. R. Sonmez, J.E. Rowings, "Construction labor productivity modelling with neural networks", Journal of Construction Engineering and Management, vol. 124, no. 6, pp. 498-504, 1998. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:6(498)
  22. S.O. Ogunlana, K. Prokuntong, V. Jearkjirm, "Construction Delays in Fast Growing Economy Comparing Thailand with Other Economies", International Journal of Project Management, vol. 14, no. 1, pp. 37-45, 1996. https://doi.org/10.1016/0263-7863(95)00052-6
  23. W. Alaghbari, M.R.A. Kadir, A. Salim, Ernawati "The significant factors causing delay of building construction projects in Malaysia", Engineering, Construction and Architectural Management, vol. 14, no. 2, pp. 192-206, 2007. https://doi.org/10.1108/09699980710731308
  24. Y. Kim, K. Kim, D. Shin, "Delay Analysis Method Using Delay Section" Journal of construction engineering and management, vol. 131, no. 11, pp. 1155-1164, 2005. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1155)
  25. E.K. Zaneldin, "Construction claims in United Arab Emirates: Types, causes, and frequency", International Journal of Project Management, vol. 24, no. 5, pp. 453-459, 2006. https://doi.org/10.1016/j.ijproman.2006.02.006
  26. T.M. Zayed, D.W. Halpin, "Pile Construction Productivity Assessment", Journal of Construction Engineering and Management, vol. 131, no. 6, pp. 705-714, 2005. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:6(705)

Cited by

  1. A quantitative risk assessment methodology for construction project vol.43, pp.7, 2018, https://doi.org/10.1007/s12046-018-0846-6