계약기간연장조항의 연장절차 개선방향에 관한 연구

A Study on the Improvement Direction of Contract Period Prolongation Process

  • 투고 : 2011.09.29
  • 발행 : 2012.01.25

초록

Construction contract is generally regarded as a contract for work. Contrary to sales contract, a special feature of construction contract is to make the object according to Owner's direction and/or material. Various problems may occur and effect construction period during construction process. To treat the problems after a conclusion of the contract, Contract period prolongation clause was introduced and has been revised in the General Conditions of Government Construction Contract. But, there has been pointed out that the reality of in situ situation is not properly reflected in this clause. Therefore, the problems of the prolongation clause was analysed. And the role of contract parties and the new prolongation process was suggested in this study.

키워드

참고문헌

  1. 건설기술관리법시행령
  2. 국가를 당사자로 하는 계약에 관한 법률
  3. 국가를 당사자로 하는 계약에 관한 법률 시행령
  4. 국가를 당사자로 하는 계약에 관한 법률 시행규칙
  5. 기획재정부, 회계예규 공사계약일반조건, 2010.11
  6. 재정경제부(현 기획재정부), 유권해석 41301-954, 1999.4.2
  7. 재정경제부, 유권해석 41301-167, 2001.1.31
  8. 조영준, 이론과 실무-건설계약관리, 한올출판사, 2010, 서울, p.111.
  9. 조영준, 이상범, 공공건설사업에서 계약기간 연장 처리방법 개선에 관한 연구, 한국건설관리학회논문집, v6. n3. 2005. 6
  10. 한국건설산업연구원, 서울특별시 공사계약특수조건 표준화 연구, 2002
  11. 한국원가관리협회(책임연구원 강성원), 공사기간 연장에 따른 간접비 지급방안 개선, 기획재정부 국고국 회계제도과, 2010, 7.
  12. 현학봉, 건설공사 계약관리와 클레임-FIDIC 개정판 및 공사 계약일반조건을 중심으로, 일간 건설신문, 2003, p.304.
  13. Lal, Hamish, Quantifying and managing disruption claims, Thomas Telford, 2003, London, p.3.
  14. Trickey, Geoffrey and Hackette, Mark, The Presentation and Settlement of Contractors' Claims, Taylor & Francis, 2ed. 2005, London, p.23.