Abstract
In this study, in-depth site investigation related to design and construction of pile foundation was carried out, especially with respect to 103 large-scale bridges located in South Korea. As a result, the depths and location of investigation was unsatisfactory at the foundation investigation process. Moreover, pile load tests were not performed when the capacity of the file is calculated in planning phase, and it was difficult to determine the load capacity limit due to the fact that loading capacity was not specified in pile-loading test. The design criteria related to pile foundation does not reflect the reality of the construction site, and that causes over design, and economic inefficiency in budget. Therefore, the purposes of this study is to review case studies related to the bearing capacity of pile foundations and suggest improvements in the construction specifications.
본 연구에서는 말뚝기초의 설계 및 시공과 관련하여 국내 103 개소 대형교량건설현장에 대한 실태를 조사 분석하였다. 그 결과, 지반조사 단계에서 지지층에 대한 심도확인과 조사위치 배치기준 적용이 미흡한 것으로 나타났다. 설계단계에서는 말뚝시험시공 없이 지지력을 산정하는 경우가 많았으며, 말뚝재하시험 시 재하용량 적용기준이 불명확하여 극한(또는 항복)지지력을 확인할 수 없었다. 재하시험을 수행하더라도 시험결과의 반영이 미흡하여 경제성을 검토하지 않는 등의 문제점이 나타났다. 말뚝기초 설계기준이 현장여건을 제대로 반영하지 못하여 과다설계가 될 경우 경제성을 기할 수 없다. 따라서, 말뚝기초의 지지력과 관련된 기존문헌을 고찰하고, 교량기초 설계 및 시공사례 분석을 통하여 시방서의 일부 내용을 개선하도록 제안하였다.