DOI QR코드

DOI QR Code

Optimal Operation Scheme of MicroGrid System based on Renewable Energy Resources

신재생 에너지원 기반의 마이크로그리드 최적운영 방안

  • Received : 2011.05.04
  • Accepted : 2011.07.19
  • Published : 2011.08.01

Abstract

This paper presents an optimal operation of microgrid systems and considering a tie-lines capacities that concerned each grid. The microgrid system consists of a wind turbine, a diesel generator, and a fuel cell. An one day load profile and wind resource for wind turbine generator were used for the study. For the grid interconnection, tie-line capacities were applied as constraints. The capacity constraints of tie-lines in production cost analysis are very important issues in the operation and planning of microgrid. In optimization, the Harmony Search (HS) algorithm is used for solving the problem of microgrid system operation which a various generation resources are available to meet the customer load demand with minimum operating cost. The application of HS algorithm to optimal operation of microgrid proves its effectiveness to determine optimally the generating resources without any differences of load mismatch.

Keywords

References

  1. Venkataramanan, G., C. Marnay. "A Larger Role for Microgrids" IEEE Power & Energy Magazine, Vol. 6, Num. 3, May/June 2008, pp.78-82.
  2. Lasseter, R., "MicroGrids," , IEEE Power Engineering Society Winter Meeting, 2002.,New York, NY, 2002, p. 305-08.
  3. Krishnamurthy, S., T.M. Jahns, R.H. Lasseter. "The Operation of Diesel Gensets in a CERTS Microgrid" IEEE, Power and Energy Society General Meeting - Conversion and Delivery of Electrical Energy in the 21st Century, 2008
  4. Sakis Meliopoulos, "Challenges in Simulation and Design of Grids," Proceedings of the 2002 IEEE/PES Winter Meeting, 2002.,New York, NY, 2002.
  5. Geem, Z.W., Tseng, C-L. and Park, Y. ''Harmony search for generalised orienteering problem: best touring in China'', Book Advanced in Natural Computation, Vol. 361, No. 2, Springer Berlin/Heidelberg, 2005
  6. Lee, K.S. and Geem, Z.W. ''A new meta-heuristic algorithm for continuous engineering optimisation: harmony search theory and practice'', Computer Methods in Applied Mechanics and Engineering, Vol. 194, pp.3902--3933, 2005 https://doi.org/10.1016/j.cma.2004.09.007
  7. Levitin, G., Lisniaski, A. and Elmakis, D. ''Structure optimisation of power system with different redundant elements'', Electric Power System Research, Vol. 43, pp.19-27, 1997 https://doi.org/10.1016/S0378-7796(97)01155-3
  8. Mohamed, F., and Heikki, k. "System Modelling and Online Optimal Management of MicroGrid," accepted for publication in the 6th International Workshop on Large-Scale Integration of Wind Power and Transmission Networks for Offshore Wind Farms ., 26-8 October 2006, Delft, The Netherlands.
  9. www.cumminspower.com/Commercial1/Diesel/S1215.pdf
  10. J. F. Manwell, J. G. McGowan, A. L. Rogers, Wind Energy explained, John Wiley & Sons, 2002
  11. Hernandez-Aramburo, C. A., and Green, T. C., and Mugniot, N., "Fuel Consumption Minimization of a Microgrid", IEEE Transactions On Industry Applications, vol. 41, Issue. 3, May/June. 2005, p. 673-681. https://doi.org/10.1109/TIA.2005.847277
  12. Michalewicz, Z., "A Survey of Constraint Handling Techniques in Evolutionary Computation Method" Proc. 4th Annual Conference on Evolutionary Programming, pp. 135-155, 1995