A Study on the Feasibility of IGCC under the Korean Electricity Market

국내 전력거래제도하에서 IGCC 사업성 확보를 위한 정책 제언

  • Ko, Kyung-Ho (Power Generation Lab, KEPCO Research Institute)
  • 고경호 (한국전력공사 전력연구원 수화력발전연구소)
  • Received : 2010.10.25
  • Accepted : 2011.02.18
  • Published : 2011.02.28

Abstract

An IGCC was evaluated as one of the next generation technologies that would be able to substitute for coal-fired power plants. According to "The 4th Basic Plan of Long-term Electricity Supply & Demand" which is developed by the Electricity Business Acts, the first IGCC will be operated at 2015. Like other new and renewable energy such as solar PV, Fuel cell, The IGCC is considered as non-competitive generation technology because it is not maturity technology. Before the commercial operation of an IGCC in our electricity market, its economic feasibility under the Korean electricity market, which is cost-based trading system, is studied to find out institutional support system. The results of feasibility summarized that under the current electricity trading system, if the IGCC is considered like a conventional plant such as nuclear or coal-fired power plants, it will not be expected that its investment will be recouped within life-time. The reason is that the availability of an IGCC will plummet since 2016 when several nuclear and coal-fired power plants will be constructed additionally. To ensure the reasonable return on investment (NPV>0 IRR>Discount rate), the availability of IGCC should be higher than 77%. To do so, the current electricity trading system is amended that the IGCC generator must be considered as renewable generators to set up Price Setting Schedule and it should be considered as pick load generators, not Genco's coal fired-generators, in the Settlement Payment.

Keywords

References

  1. 김미영, "300MW급 IGCC를 위한 건식 분류층 석탄가스화 공정의 동적 상태 모사", 한국수소 및 신에너지학회논문집, Vol. 21, No. 5, 2010, p. 461.
  2. 정재화, "한국형 300MW급 IGCC 실증플랜트를 위한 가스화공정 Test Bed 구축 및 단위공정 국산화 개발", 전력연구원, 2010, pp. 52-141.
  3. NETL, "Cost and Performance Baseline for Fossil Energy Plant", 2007, pp. 79-145, 189-197.
  4. 전력거래소, "2010년도 전력시장 통계", 2010, pp. 12-20.
  5. 지식경제부, "제4차 전력수급기본계획", 2008, pp. 9-37, 63-88.
  6. 한국전력거래소, "전력시장운영규칙", 2008, pp. 6-36.
  7. NEA/IEA, "Projected costs of generation electricity", 2010, pp. 60-92.
  8. Alex Klein, "Comparative Costs of energy in Europe", Emerging energy research, 2007, pp. 1-14.
  9. 이창호, "300MW급 IGCC 실증플랜트 사업의 2단계 사업비 산정 및 정부지원금 확보방안 연구", 2009, pp. 3-19.
  10. 정래혁, "P-Pool 모형을 활용한 장기 전력시장가격(SMP) 전망", 대한전기학회 논문집, 2009.
  11. 김도상, "석탄가스화복합발전 기술개발(II)", KOPEC, 1999, pp. 71-73.
  12. IEA, "World Energy Outlook 2009", IEA, 2009.
  13. 한국은행, "생산자물가지수", web-database.