활동기준예방에 의한 프로젝트 품질코스트 최소화

Minimizing Project Quality Costs by Activity-Based Prevention

  • 김종열 (한양대학교 산업공학과) ;
  • 강창욱 (한양대학교 ERICA 캠퍼스 산업경영공학과) ;
  • 황인극 (공주대학교 산업시스템공학과)
  • Kim, Jong-Yul (Dept. of Industrial Engineering, Hanyang University) ;
  • Kang, Chang-Wook (Dept. of Industrial and Management Engineering, ERICA Campus, Hanyang University) ;
  • Hwang, In-Keuk (Dept. of Industrial and Systems Engineering, Kongju National University)
  • 투고 : 2011.10.19
  • 심사 : 2011.10.28
  • 발행 : 2011.12.31

초록

Traditional quality control for manufacturing or service sector is not suitable for the quality control of a project as the project is one-time task constrained by time, cost, and quality. To meet the internal and external customers' requirements, quality costs approach to the project will be effective. Hence, we propose PONC (price of nonconformance) estimation procedure and a mathematical model, which are focused on activity-based prevention in the execution step and warranty step of EPLC (extended project life cycle). This procedure and model will help project manager develop preventive action plan for project quality costs minimization from nonconformance risk activities and PONC estimates information.

키워드

참고문헌

  1. 김종열, 강창욱, 황인극; "클레임코스트를 고려한 프로젝트의 시간-비용 혼합정수계획모형", 한국산업경영시스템학회지, 34(3) : 77-85, 2011.
  2. Abdelsalam, H. M. E. and Gad, M. M.; "Cost of quality in Dubai : An analytical case study of residential construction projects," International Journal of Project Management, 27 : 501-511, 2009. https://doi.org/10.1016/j.ijproman.2008.07.006
  3. Avots, I.; "Information systems for matrix organisations in Cleveland David," 1st ed., Matrix management systems handbook Van Nostrand Reinhold, New York, 1984.
  4. Babu, A. J. G. and Suresh, N.; "Project Management with Time, Cost, and Quality Considerations," European Journal of Operational Research, 88 : 320-327, 1996. https://doi.org/10.1016/0377-2217(94)00202-9
  5. Barnes, N. M. L. and Wearne, S. H.; "The future for major project management," International Journal of Project Management, 11(3) : 135-142, 1993. https://doi.org/10.1016/0263-7863(93)90046-P
  6. Burke, R.; "Project Management Planning and Control, Stratford Upon Avon," Management Press, 1995.
  7. Cervone, H. F.; "Project risk management," OCLC Systems and Services : International Digital Library Perspectives, 22(4) : 256-262, 2006. https://doi.org/10.1108/10650750610706970
  8. Cnuddle, M.; "Lack of quality in construction economic losses," in Proceddings of 1991 European Symposium on Management, Quality and Economics in Housing and other Building Sectors, 508-515, 1991.
  9. Crosby, P. B.; "Quality Is Free," McGraw-Hill, New York, 1979.
  10. Crosby, P. B.; "Quality Without Tears," Penguin Books, Ontario, 1984.
  11. Dale, B. G. and Plunkett, J. J.; "Quality Costing," Chapman and Hill, London, 1995.
  12. Elmaghraby, S. E. and Salem, A.; "Optimal linear approximation in project compression," IIE Transactions, 16(4) : 339-347, 1984. https://doi.org/10.1080/07408178408975253
  13. Feigenbaum, A. V.; "Total quality control," Harvard Business Review, 34(6) : 93-101, 1956.
  14. Ford, L. R. and Fulkerson, D. R.; "Flows in net works," Princeton University Press, New Jersey, 1962.
  15. Goyal, S. K.; "A note on simple CPM time-cost tradeoff algorithm," Management Science, 21(6) : 718-722, 1975. https://doi.org/10.1287/mnsc.21.6.718
  16. Hall, M. and Tomkins, C.; "A Cost of Quality Analysis of a Building Project: towards a Complete Methodology for Design and Build," Construction Management and Economics, 19 : 727-740, 2001. https://doi.org/10.1080/01446190110066146
  17. Juran, J. M. and Gryna, F. M.; "Quality Planningand Analysis," McGraw-Hill, 2nd ed., 1980.
  18. Kapur, K. C.; "An algorithm for the project cost/duration analysis problem with quadratic and convex cost functions," IIE Transactions, 5 : 314-322, 1973.
  19. Kelley, J. E. and Walker, M. R.; "Critical Path Planning and Scheduling : An Introduction," Mauchly Associate, Ambler, PA, 1959.
  20. Kelley, J. E.; "Critical-path planning and scheduling : mathematical basis," Operations Research, 9(3) : 296-320, 1961. https://doi.org/10.1287/opre.9.3.296
  21. Kendrick, T.; "Identifying and Managing Project Risk," AMACOM, New York, 2003.
  22. Khang, D. and Myint, Y.; "Time, cost and quality tradeoff in project management: a case study," International Journal of Project Management, 17(4) : 249-256, 1999. https://doi.org/10.1016/S0263-7863(98)00043-X
  23. Kim, J. Y., Kang, C. W., and Hwang, I. K.; "A Practical Approach to Project Scheduling : Considering the Potential Quality Loss Cost in the Time-Cost Tradeoff Problem," Published online of : International Journal of Project Management, 2011.
  24. Koushki, P. A., Al-Rashid, K., and Kartam, N.; "Delays and cost increases in the construction of private residential projects in Kuwait," Construction Management and Economics, 23 : 285-294, 2005. https://doi.org/10.1080/0144619042000326710
  25. Lamberson, L. R. and Hocking, R. R.; "Optimum time compression in project scheduling," Management Science, 16(10) : B597-B606, 1970.
  26. Project Management Institute; "A Guide to the Project Management Body of Knowledge," 4th ed., PMI Publications, Pennsylvania, 2008.
  27. Shenhar, A. J., Levy, O., and Dvir, D.; "Mapping the dimensions of project success," Project Management Journal, 28(2) : 5-13, 1997.
  28. Siemens, N.; "A simple CPM time-cost tradeoff algorithm," Management Science, 17(6) : B354-B363, 1971.
  29. Siemens, N. and Gooding, C.; "Reducing project duration at minimum cost : a time/cost trade-off algorithm," OMEGA, 3 : 569-581, 1975.
  30. Wit, A. D.; "Measurement of project success," Project Management, 6(3) : 164-170, 1988. https://doi.org/10.1016/0263-7863(88)90043-9