Abstract
The layout of haul routes within a construction site of large complex projects needs to be carefully determined as the productivity of earthwork activity heavily depends on the efficiency of the layout and the routes are not likely to change once they are settled. This paper aims to provide a construction planner with a reliable framework to create an efficient layout of haul routes within a large complex construction site. To construct the framework, five factors affecting haul route layout and the productivity of earthwork activity are described along with the associated rules of thumb recommended by design and field experts. In addition, a methodology based on spatial analysis using raster format in GIS is proposed to further increase haul route efficiency. The proposed planning framework enables a construction planner to easily find a more reliable route layout by thoroughly considering the key factors prior to setting up an earthmoving plan.
토공사는 단지조성 프로젝트에서 단일 공종으로는 가장 큰 비중을 차지하는 공정 중 하나이다. 토공사의 순조로운 진행을 위해 시공계획자는 적재 및 운반장비의 효율적인 조합, 공종과의 연계를 고려한 순차적 시공, 그리고 운반로 레이아웃과 같은 토공사 운영관련 문제들을 해결해야 한다. 특히 단지내 운반로는 토공생산성 및 공사비에 직접적인 영향을 미칠 뿐 아니라 한번 정해지면 그 관성 때문에 다른 경로로 변경하기 어려운 특성이 있기 때문에 신중한 의사결정이 요구된다. 본 연구는 시공계획자의 단지내 운반경로와 관련된 의사결정을 지원하기 위해 지형정보 분석에 기초한 효율적 운반로 발굴 방법론 개발을 목적으로 한다. 이를 위해 단지내 운반경로 레이아웃 결정시 고려되어야 할 필수 요소들을 설계 및 시공 전문가들의 경험법칙에 근거하여 5가지로 구분하여 설명하였다. 또한 효과적인 운반경로 도출을 위하여 GIS 환경에서 상기한 영향요소들을 적절히 반영, 분석할 수 있는 방법론을 제안하였다. 제안된 방법론을 현재 시공이 이루어지고 있는 사례현장에 적용하여 실용성을 검증한 결과 미세한 생산성 향상을 보인 것으로 분석되었다. 본 연구는 개선된 운반효율을 보장하고, 신뢰할 수 있는 단지내 운반로 레이아웃 시공계획 프레임웍을 제공하였다는 점에서 의미가 있다.