Abstract
Power plant start-up is a complicate process involving hundreds of operations that should be performed either automatically or manually. Several major operations should be proceeded in parallel and each major operation is again broken down into detailed operations that must be carried out in a strict sequence. Even though most of the operations are automated, still substantial portions of the operations are carried out manually and the operational status should be monitored by the crew members, which are quite stressful tasks to be performed in real time. In this paper, a data structure called an Event Sequence Monitoring Graph(ESMG) is proposed for monitoring a sequence of events involved in the power plant start-up process. The ESMG is currently being applied to a thermal power plant with a rated output of 500MW. An application example is shown with the boiler feed water pump system start-up process, which exhibits a good potential for future applications.
화력발전소를 기동하기 위해서는 수많은 기기조작들이 수동 및 자동으로 또한 순차적 및 병렬로 정확하게 진행되어야 한다. 따라서 발전소의 기동 중 긴박하게 이루어지는 수많은 기기 조작들이 모두 제대로 진행되고 있는지의 여부를 실시간으로 감시하는 일은 매우 복잡하고 긴장을 요하는 임무(task)이다. 본 논문에서는 화력 발전소의 기동시퀀스의 정상 진행 여부를 효과적으로 감시하기 위하여 Event Sequence Monitoring Graph(ESMG)라는 자료구조(Data Structure)를 제안하고 그 구현 기법에 대하여 논하고자 한다. 제안하된 ESMG는 용량 500MW 급의 국내 전형적인 표준형 화력발전소의 주 급수펌프 시스템의 기동 시퀀스의 진행 감시에 적용하기 위한 예를 들었으며 향후 유용하게 활용될 수 있는 가능성을 보였다.