Abstract
A small hydropower plant(SHP) using cooling water discharged from the power plant was constructed in Samcheonpo. This study presents predicted and measured hydrological data in the construction process of small hydropower plant in order to evaluate characteristics of water level variation of cooling water discharge channel which is a key factor in the design of SHP since the water level rise of channel is related to impact on circulating water system of the existing power plant. Various methods were applied for prediction of water level variation in the design stage from simple empirical formula to sophisticated 3-dimensional CFD method. Measured results reveal that mean value was similar between measured and predicted, but measured results were larger than predicted in deviation. Moreover, simple formula, i.e. standard weir equation and Honma equation, were more useful before installation of SHP, but sophisticated methods during operation of SHP.
삼천포 화력발전소에서 냉각수로 이용되고 방류되는 해수를 이용한 소수력 발전소를 건설하였다. 본 연구에서는 해양소수력 발전소 건설시 가장 중요한 문제인 기존 화력발전소의 순환수 계통에 미치는 영향을 평가하기 위한 방안으로 배수로 수위의 해양소수력 건설 이전, 건설 중, 건설 이후 해양소수력 운전 상태에서의 변화를 예측한 값과 실제 계측값을 분석하였다. 설계시 일반적으로 이용되는 개수로 수리식에서부터 Flow 3D를 이용하여 3차원적인 수리해석 기법을 이용하는 것까지 다양한 예측을 시도하였고 관측을 통하여 검증하고자 하였다. 예측치와 실제 관측치의 비교 결과, 수위의 전체적인 평균값은 예측치와 관측치가 유사하였지만 수위의 변화 폭은 건설 중과 해양소수력 운전 상태에서 매우 크게 나타났다. 또한, 소수력 건설 이전에는 표준위어식과 Honma식의 예측값이 관측값과 가장 유사하였으나, 소수력 건설 이후에는 HEC-2, HEC-RAS, Flow-3D의 예측값이 실측값과 가까운 결과를 보였다.