Appropriate Roles of Project Participants for Public Partnership Projects of Railways through the Organizational Behavior Theory

조직행동론을 통해서 본 민간철도 투자사업의 참여자간 갈등유형 및 역할정립 방안에 관한 사례연구

  • 김병일 (연세대학교 공과대학 토목공학과) ;
  • 윤성민 ((미)Texas at Austin대 Department of Civil Architectural and Environmental Engineering) ;
  • 한승헌 (연세대학교 사회환경시스템공학부) ;
  • 김형회 ((주)유신코퍼레이션)
  • Received : 2008.05.02
  • Accepted : 2008.09.19
  • Published : 2008.11.30

Abstract

No proper system exists for private investment projects, and efficient project management is not being achieved due to entanglements of management. Recognizing these circumstances, this paper has diagnosed the hard facts that project management organizations and systems are facing, and presented solutions to the factors that are obstructing the establishment of efficient project management system. This paper carried out focus group interviews on the experts who had participated in the Incheon International Airport Railway construction project, using the methodology of an exploratory case study. The results were systematically analyzed according to organizational behavior and causes corresponding to each of the problems were deduced. Private investment projects were divided into task environments and project organizations based on social science methodology and analyzed, and a final improvement plan for each participating organization was presented. An improvement plan was presented, and it was compared with the case study of Incheon bridge construction project, which is recognized as a model of successful project management, and its appropriateness evaluated.

본 연구는 민간투자사업에 있어서 사업관리 조직이 직면하고 있는 장애요인을 진단하고 효율적인 사업관리 체계 구축을 위한 방안을 제시하고자 한다. 먼저, 본 연구는 사례연구 방법론을 적용하여 인천국제공항철도 건설사업에 참여한 전문가들을 대상으로 표적그룹 인터뷰를 실시해 민간투자사업의 문제점을 조사하였다. 이를 조직행동론에 근거해 장애요인을 사업환경과 프로젝트 조직체로 구분하여 체계화하였고 각 문제별로 대응하는 원인들을 도출하였다. 민간투자사업에 참여하는 집단 간의 관계와 행동의 결과로부터 기인하는 문제점들은 매우 다양하고 복잡한 양상을 띠지만 그 원인을 요약해 보면, 목표의 차이, 지각의 차이, 행동경향의 차이로 구분할 수 있었다. 이들 원인의 기저로서 역할과 책임을 고려하지 못한 계약체계, 사업목적에 대한 근본 인식의 차이, 시공사의 지분참여가 가장 중요한 요소인 것으로 나타났다. 이에 근거하여 본 연구는 참여주체별 역할과 책임을 명확화 함으로써 조직행동론 관점에서 사업관리를 효율화화기 위한 개선방안을 제시하였다.

Keywords

References

  1. 국토연구원(2004) 민간투자사업 업무수행 일반지침.
  2. 국토연구원(2005) 1999-2004 민간투자지원센터 백서, 국토연구원, p. 553.
  3. 기획예산처(2007) 민간투자사업 기본계획.
  4. 기획예산처(2007) 재정사업에 대한 예비타당성 조사시 민간투자사업 발굴 - 부족한 SOC 시설투자 조기확충, 민간투자제도팀 보도자료.
  5. 박민생, 변상우, 김학돈(2006) 조직론의 이해, 형설출판사
  6. 박영민, 김수용, 김대영, 조훈희(2006), SOC 민간투자사업의 CM 업무 수행구조 제안 한국건설관리학회지, 한국건설관리학회, 제7권 제4호.
  7. 송병록(2004). 민간투자제도 운영성과에 대한 평가와 향후 개선과제. 국토연구원 민간투자지원센터.
  8. 신경림, 장연집, 김영경, 이금재, 최명민, 김혜영, 김옥현, 김영혜(2004) 질적 연구방법 포커스 그룹. 현문사.
  9. 이군희(2003) 사회과학 연구방법론, 법문사.
  10. 이복남, 최석인, 장현승(2005) 국내 용역형 CM/PM 시장 활성화를 위한 개선 방안, 한국건설산업연구원.
  11. 이재철(2005) 민자유치사업의 문제점과 개선방안, 국회예산정책처, 사업평가 현안분석.
  12. 이학종(1997) 조직행동론 : 이론과 사례연구, 세경사.
  13. 장상문, 민간투자 SOC 사업에서 CM의 필요성과 기대효과 (공항철도를 중심으로), 제12회 CM FORUM, 한국건설관리학회, p. 7.
  14. 철도청(1997). 인천국제공항철도 사업 추진계획.
  15. 한국건설산업연구원(2004) 인천국제공항철도 사업관리 조직 및 시스템점검 보고서, 한국건설산업연구원, p. 29.
  16. Askar, M. M. and Gab-Allah, A. A. (2002) Problem facing parties involved in build, operate, and transport projects in Egypt, Journal of Management in Engineering, Vol. 18, No. 4, pp. 173-178. https://doi.org/10.1061/(ASCE)0742-597X(2002)18:4(173)
  17. Berggren, C., Söderlund, J., and Anderson, C. (2001) Client, contractors, and consultants : The consequence of organizational fragmentation in contemporary project environments, Project Management Journal, PMI, Vol. 32, No. 3, pp. 39-48.
  18. Bresnen, M., Goussevskaia, A., and Swan, J. (2005) Organizational routines, situated learning and process of change in project-based organizations, Project Management Journal, PMI, Vol. 36, No. 3, pp. 27-41.
  19. Culp, G. and Smith, A. (2005) Leadership effectiveness and behavior, Leadership and Management in Engineering, Vol. 5, No. 2, pp. 39-48. https://doi.org/10.1061/(ASCE)1532-6748(2005)5:2(39)
  20. Hyväry, I. (2006) Success of projects in different organizational conditions, Project Management Journal, PMI, Vol. 37, No. 4, pp. 31-41. https://doi.org/10.1177/875697280603700404
  21. Kumaraswamy, M. M. and Zhang, X. Q. (2001) Governmental role in BOT-led infrastructure development, International Journal of Project Management, Vol. 19, No. 4, pp. 195-205. https://doi.org/10.1016/S0263-7863(99)00069-1
  22. Kumaraswamy, M. M., Ling F. Y. Y., Rahman, M. M., and Phng, S. T. (2005) Constructing relationally integrated teams, Journal of Construction Engineering and Management, Vol. 131, No. 10, pp. 1076-1086. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:10(1076)
  23. Larson, E. W. and Gobeli, D. H. (1989) Significant of project management structure on development success, IEEE Transaction in Engineering Management, Vol. 36, No. 2, pp 119-125. https://doi.org/10.1109/17.18828
  24. McCarthy, S. C. and Tiong, R. L. K. (1991) Financial and contractual aspects of build-operate-transfer projects, International Journal of Project Management, Vol. 9, No. 4, pp. 222-227. https://doi.org/10.1016/0263-7863(91)90030-Y
  25. Thamhain, H. J. (2004) Team leadership effectiveness in technology- based project environments, Project Management Journal, PMI, Vol. 35, No. 4, pp. 35-46.
  26. Tiong, R. L. K., Yeo, K. T., and McCarthy, S. C. (1992) Critical success factors in winning BOT contracts, Journal of Construction Engineering and Management, Vol. 118, No. 2, pp. 217-228. https://doi.org/10.1061/(ASCE)0733-9364(1992)118:2(217)
  27. Tiong, R. L. K. (1996) CSFs in competitive tendering and negotiation model for BOT projects, Journal of Construction Engineering and Management, Vol. 122, No. 3, pp. 205-211. https://doi.org/10.1061/(ASCE)0733-9364(1996)122:3(205)
  28. Yiu, T. W. and Cheng, S. O. (2007) Behavioral transition: A framework for the construction conflict-tension relationship, IEEE Transaction in Engineering Management, Vol. 54, No. 3, pp 498-505. https://doi.org/10.1109/TEM.2007.900784