가설흙막이의 버팀대 선행하중량과 흙막이 벽체 변형등에 대한 분석

  • Published : 2006.12.01

Abstract

Supporting method of a Temporary retaining wall for underground excavation project are adopted by systems of strut, anchor, nail, raker, etc. Strut system and Raker system of these methods are mostly used preloading jack to minimize deformations of retaining wall. We determinate efficient preloading to analysis these strut-preloadings, deformations of retaining wall, axial forces, and etc.. This study is analysed that preloading applied 0%, 10%, 20%, 30%, ...., 100% for strut and raker installed by CIP temporary retaining wall. This study results that adequate preloadings were determined to analysis correlations of preloading, deformations of wall, maximum bending moment, axial force of strut, and displacement of surrounding.