Abstract
This study is based on the reseach about conte. track$(Dugso\~wonju)$ double line electric railway tunnel. Authors conducted test blasting to examine the effect of blasting pollution. To be conducted safe and effective work by using this result studies sailable substitution excavation method. No-vibration section generates continuously the vibration of breaker working to go abreast necessarily secondary fragmentation working and according to judging that application is actually difficult in case of the condition of study site, the period of construction, the cost of construction, the efficiency of construction, pre-heavy caliber horizontally boring working + line drilling method + vibration control secondary blasting method excavation working is possible from level within blast vibration standard.
본 연구는 중앙선(덕소-원주간) 복선전철 터널공사론 기초로 한 것으로 주변 보안물건에 대한 피해가 발생되지 않도록 시험발파를 통한 발파 환경 영향권 분석을 실시하고, 그 결과를 상호 비교, 분석하여 안전하고 효율적인 공사가 수행될 수 있도록 적합한 대체 굴착공법의 적용에 대하여 연구하였다. 시험발파를 통해 제시된 대체굴착공법을 이용하여 더 안전하고 효과적인 작업을 수행한 수 있었으며, 무진동 구간은 일반적으로 2차 작업이 병행되므로 breaker 작업에 의한 진동이 지속적으로 발생되어 연구지역의 경우 적용이 사실상 어렵다고 판단됨에 따라 선대구경 수평보링 공법+라인드릴링 공법+다분할 미진동 소발파 공법을 적용함으로써 발파진동 기준치 이내의 수준으로 굴착작업이 가능하였다.