Abstract
The time and cost is the most important information for the construction project management. Currently, a lot of studies have been done in order to clearly relate them with each other, but there have been some difficulties. Because of the characteristic of Korean government contract law, the construction project in Korea is managed by only cost and the time and cost information is distinctly separated. In order to manage all the major construction project information smoothly, the time and cost information should have relation with each other. This study suggest methods for relating the time and cost information, especially for road construction project of MOCT. Through the survey of construction field engineers and case study of the road construction project, several alternatives to improve the usability of construction information are suggested in this study. These alternatives can support relating other construction information.
공정과 공사비는 건설사업의 관리에 매우 중요한 두 가지 축으로써, 이들을 통합 관리하려는 많은 노력이 진행중이나, 많은 어려움을 겪고있는 상황이다 내역체계의 특성으로 인해, 국내의 경우는 내역과 공정체계의 두 가지 축을 중심으로 건설사업정보를 통합 관리할 수 있다. 본 연구에서는 지방국토관리청의 도로공사를 중심으로 내역체계와 공정체계를 연계 활용할 수 있는 방안을 제시하고 있으며, 이를 위해, 위해 도로공사 현장 사례를 분석하고, 설문조사를 통하여 문제점을 분석하고, 이를 개선하기 위해 통합건설정보분류체계를 기반으로 시설물별 공통WBS와 부위별 수량산출서를 작성하는 방안을 제시하고 있다. 이러한 방안은공정과 내역의 연계활용뿐만 아니라, 타 정보와의 연계 활용의 기반을 제공할 수 있다.