The demolition works of high building in korea are expecting to increase rapidly in the near future, and its general demolition methods can be divided into mechanical demolition method and explosive demolition method. The selection of the right demolition method relies on many variable elements according to environmental and geographical elements. But, generally, the most important element of those is a economical profit. Accordingly, This study estimates each demolition cost dividing into mechanical demolition method and explosive demolition method of high building in city. And the estimating of the demolition cost makes it possible to do comparative analysis for the economical efficiency of each method more objectively than any other selective elements. Also, the analysis for the economical efficiency helps to forecast the activated time of the explosive demolition method in domestic.

고층건물의 해체공사는 멀지 않은 장래에 급속도로 증가할 것으로 예상되며, 이들의 일반적인 해체방법은 기계식해체공법과 발파해체공법으로 대별할 수 있다. 해체공법의 결정은 해당건물이 가지는 지리적, 환경적 요인에 따라 많은 변동요인들이 있지만 일상적인 경우라면 경제성 판단이 공법선정의 가장 중요한 요인으로 작용한다. 따라서 본 연구에서는 다른 해체공법 선정요인들 보다는 객관적인 비교가 가능한 도심지 고층건물의 해체비용을 기계식공법과 발파공법으로 구분하여 산출하였으며, 이것의 비교 분석을 통하여 발파해체공법의 향후 활성화 시점을 전망하였다.

Keywords

References

  1. 대한주택공사, 구조물의 해체공법에 관한 연구(I), 1996. 6
  2. 대한주택공사, 성도건설주식회사, 한국중공업주식회사, 발파해체공법의 설계 및 시공기술 개발연구, 1997. 12
  3. RC구조물 발파해체공사의 품기준설정연구, 1998.10
  4. 대한주택공사, 성도건설주식회사, 재개발지구내 중고층건축물의 발파해제공법에 관한 연구, 1997. 7
  5. 대한주택공사, 서울 천연지구내 지장물의 효율적인 해체공사 설계방안 수립, 2000. 6
  6. 대한주택공사, 해체공사의 설계 및 견적기준 정립 연구, 2000.10
  7. 대한주택공사, 고층아파트의 발파해제 기술개발, 2002. 6
  8. 解休工法硏究會, 解本I法と積算, (財)經濟調査會, 1995
  9. Dowding, C.H., Ground motions and air-blast effect of explosive demolition of structures, ASCE, J of Const. Engr, And Mangt, Vol.120, No.4, 1994. pp.838-856