Abstract
This paper deals with pre-erection scheduling and erection scheduling in shipbuilding. Among shipbuilding scheduling, the ship erection scheduling in a dock is one of the most important since the dock is the most critical resource in a shipyard. However, it is more reasonable to consider pre-erection scheduling and erection scheduling as unified because they compete with the common constrained resources such as labor, crane, space, and so on. It is very hard to consider two scheduling problems simultaneously, and hence, we approach them sequentially. At first, we propose space resource leveling heuristics in pre-erection scheduling given erection date. And then, considering the manpower resource determined by pre-erection scheduling, we also propose manpower resource leveling heuristics in erection scheduling. Various experimental results with real world data show that the proposed heuristics have good performance in terms of scheduling quality and time.