Engineering Geological Analysis for the Quarry Located at the Construction Site of the New Susan Harbor

부산 신항만 건설현장의 채석장에 대한 지질공학적 고찰

  • 최정찬 (부경대학교 환경지질과학과)
  • Published : 2003.09.01

Abstract

A quarry is operated for filling-up the New Busan Harbor which is under construction, but actual rock quality is something different from the primary design. Therefore, object of this study is to classify whole rock quality for the quarry through site investigation and laboratory analyses because unexpected large amount of wasted rock is produced. For this object, various analyses were performed such as surveying, Schimidt Hammer test. joint spacing investigation and laboratory analyses using DIPS & RockWorks programs for evaluating joint sets and sizes of rock fragments after blasting. As a result, it is expected that large amount of wasted rock under ${\Phi}100mm$ is produced after blasting because of high joint density.

현재 건설중에 있는 부산 신항만의 매립을 위해 채석장이 가동중에 있으나, 실제 공사 중 채석된 암석이 당초 설계와는 다른 암질을 포함하고 있다. 따라서, 당초 설계와는 달리 많은 폐석이 발생되어 정상적인 공사추진에 애로사항이 있으므로, 현장조사 및 실내작업을 통하여 지정된 채석장에 대한 전체적인 암질을 구분하는 것이 본 연구의 목적이다. 이를 위해 측량, Schimidt Rock Hammer 시험, 절리간격조사를 시행하였고 실내에서 DIPS 및 Rockworks 프로그램을 이용하여 절리의 방향성 및 발파 후 암괴의 크기를 분석하였다. 그 결과 본 지역에는 절리밀도가 높아 토석 채취시 ${\Phi}100mm$ 이하의 필터사석이 많이 발생하는 것으로 분석되었다.

Keywords

References

  1. 한국의 지질 대한지질학회
  2. 부산신항 준설토 투기장(2차) 실시설계보고서 부산지방해양수산청, 부산항건설사무소
  3. 토목기술자를 위한 지질조사 및 암반분류 신희순;선우춘;이두화
  4. 한국지질도 (1:50,000) 언양 도폭 설명서 이윤종;이인기
  5. Engineering Rock Mass Classification Bieniawski,Z.T.
  6. RockWorks;Tutorials and Cases Studies RockWare
  7. Instruction Manual of Rock Hammer Sanyo Testing Machines Co. Ltd.
  8. Civ. Eng. S. Afr. v.17 Geological factors significant in the assessment of rippability Weaver,J.M.