자원 제약을 고려한 조선산업에서의 탑재 일정계획에 관한 연구
A Study on the Erection Scheduling for Shipbuilding Considering Resource Constraints
- 발행 : 2001.09.30
초록
Scheduling for shipbuilding processes has many alternative solutions since it has long time horizon and handles many jobs. This requests the scheduling system to generate and search feasible alternative solutions in short period of time. Among shipbuilding schedules, the ship erection schedule in a dock is the most important since the dock is the most critical resource in shipyard. In this research, we model the erection scheduling problem for shipbuilding and develop a new problem solving method using CST(Constraint Satisfaction Technique) and ILOG Scheduler. Experimental results show that the proposed scheduling method outperforms the existing manual scheduling methods in terms of schedule performance and required time.