Explosives and Blasting (화약ㆍ발파)
- Volume 19 Issue 1
- /
- Pages.11-18
- /
- 2001
- /
- 1229-9073(pISSN)
A Case on Design and Construction of Tunnel for Under Passing an Underground Transformer Substation
지중변전실 하부통과를 위한 터널설계 및 시공사례
Abstract
This is a case history on design and cnostruction of tunnel for under passing an underground transformer substation. The original construction plan was cut & cover method to avoid blasting vibrations and displacements of facilities during the construction stages. But this plan was changed to tunnel because of the difficulties from construction period, cost and the required relocation site. As a results of tunnel construction, the relocation of transformer substation and replacements of transmission cables were not necessary. Therefore about 10 months of construction period and 3.5 billion wonts of construction cost were saved. Additionally, quantitative criterion for blasting was provided through the results of blasting vibration analysis.