Journal of Korean Institute of Industrial Engineers (대한산업공학회지)
- Volume 26 Issue 2
- /
- Pages.183-192
- /
- 2000
- /
- 1225-0988(pISSN)
- /
- 2234-6457(eISSN)
A Genetic Algorithm for the Parallel-Machine Total Weighted Tardiness Problem
병렬기계에서 납기지연 가중 합을 최소화하기 위한 유전 알고리듬
Abstract
This paper considers the problem of scheduling a set of n jobs on m parallel machines to minimize total weighted tardiness. For the problem a genetic algorithm is proposed, in which solutions are encoded using the random key method suggested by Bean and new crossover operators are employed to increase performance of the algorithm. The algorithm is compared with the Modified Due-Date (MDD) algorithm after series of tests to find appropriate values for genetic parameters. Results of computational tests on randomly generated test problems show that the suggested algorithm performs better than the MDD algorithm and gives good solutions in a reasonable amount of computation time.
Keywords