Development of a Scheduling System for Mould and Die Manufacturing Factory Using Microsoft Project 98

Microsoft Project 98을 이용한 금형공장의 일정계획 시스템 개발

  • 주상윤 (울산대학교 산업공학과) ;
  • 옥경진 (울산대학교 산업공학과)
  • Published : 2000.06.30

Abstract

As moulds and dies are manufactured through complex processes under the make-to-order production environment, it is very difficult that the manufacturing activities as like observance of the due date, trace of the progress, etc are controlled with a real time. In this paper, a schedule-planning system using the commercial software Microsoft Project 98 is developed to control the procedures of mould and die manufacturing with real time. Once an initial schedule is planned from the BOM information in the intranet, it is rescheduled by data collected from machines on the shop floor. The system is suitable to medium- or small-sized manufacturing companies as well as large-sized ones, because it can be installed with a low cost.

Keywords