An algorithm for resolution of resource conflicts in scheduling

  • Published : 1992.06.01

Abstract

A two phase heuristic algorithm has been developed for the resolution of resource conflicts in a single project scheduling problem. Phase 1 of the algorithm generates a feasible schedule by repairing resource conflicts. Phase 2 finds local improvements in the schedule found in phase 1. Then, the algorithm has been applied to multi project and job shop scheduling. Computational results are compared with those of dispatching procedures. Index Terms-disjunctive constraints, heuristic algorithm, project scheduling, job-shop scheduling.