다수(多数) 기계(機械)의 총비용(總費用)을 최소화(最小化)하는 최적작업순서, 공통납기일 및 작업완료일 결정을 위한 일정계획(日程計劃)
Optimum Scheduling Algorithm for Job Sequence, Common Due Date Assignment and Makespan to Minimize Total Costs for Multijob in Multimachine Systems
초록
This research is concerned with n jobs, m parallel identical machines scheduling problem in which all jobs have a common due date. The objective of the research is to develop an optimum scheduling algorithm for determining an optimal job sequence, the optimal value of the common due date and the minimum makespan to minimize total cost. The total cost is based on the common due date cost, the earliness cost, the tardiness cost and the flow time cost of each job in the selected sequence. The optimum scheduling algorithm is developed. A numerical example is given to illustrate the scheduling algorithm.