A Study on the Standard Time & Loss Time

표준작업시간과 손실시간에 관한 연구 - Radiator 제조공정의 시간연구사례를 중심으로 -

  • 강경식 (명지대학교 공업경영학과)
  • Published : 1981.12.01

Abstract

The object of this paper is to Study the work measurement which is one of the principal technique in work study for the improvement of Productivity in the foundry industry. Most of domestic mechanical enterprise using the expensive foreign machinerise is inoufficient for the standardization of the operation method and time. Therefore, the improvement of operation and productivity through the introduction of the work measurement is an urgent task. Therefore, this paper is contribute to the improvement of operation and to reduce the loss time through the application of the work measurement based on the case study conducted at W-Foundry Corporation. The summary of this study is follows; 1. The measurement of operation efficiency can be accomplished by the standard time. 2. The detailed causes and counter-proposal of loss time can be established, 3. More than 50% of loss time is attributed to c/p.