The Comparison of Work Time between Field Fabrication Method and Partial Prefabrication Method of Rebar work

벽체철근 일반조립과 부분 선조립 공법의 작업시간 비교에 관한 연구

  • Published : 2018.11.16

Abstract

Reinforced concrete works account for 40 to 50 percent of the total construction work. However, the shortage of construction workers is a problem in the delay of the construction period of reinforced concrete. The partial rebar prefabrication is one of the ways to shorten construction period. Thus, this study compared the partial rebar prefabrication and field fabrication method through work sampling. As a result, the partial rebar prefabrication showed a significant decrease in time compared to field fabrication method. As a result of this study, it is expected to be used as a reference for the efficient selection of reinforced concrete methods.